Question
Chapter 2, Problem 17P
Summary Introduction
Interpretation: The multifactor productivity estimate for the given information is to be determined.
Concept Introduction:
The multifactor productivity enables an organization to identify how effective their processes are as it computes and involves all the costs involved in the production process.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A manufacturing company produced first unit in 15:00 hours and dollar 2,50,000 worth of material, equipment usage, and supplies. The second unit took 13 hours and used dollar two lakh worth of materials, equipment usage and supplies. Labour is dollar 15 per hour.
Determine the total production cost for additional 10 units after the second unit was completed round the final amount to nearest integer
Problem 1:
A company that processes fruits and vegetables is able to produce 400 cases of canned peaches
in one and half hour with four workers. Each worker is paid 2 Rials per hour. What is labor
productivity in terms of cases/hour, cases/rial?
A small electronic company assembles power supplies for use in bread maker, cake mixer
and food processor. It wants to set up an assembly line to make its operations more efficient
and plan to use line balancing with the incremental utilization heuristic. The demand for
power supplies is 200 per hour, and the productive time per hour is 52 minutes. The
following table provides details on its operation (with time in minutes):
Time to
perform task
0.56
0.34
0.11
0.09
0.43
0.22
0.62
0.35
0.21
0.57
0.33
Tasks that must
Task
A
immediately precede
A
A
A
F
G
B,C
D
E
H.
F,G
H
K
1,J
(a) Compute the cycle time.
(b) Compute the theoretical minimum number of workstations.
(c) Draw a precedence diagram for the production line to show precedence
relationships.
Chapter 2 Solutions
Practical Operations Management
Ch. 2 - Prob. 1DQCh. 2 - Prob. 2DQCh. 2 - Prob. 3DQCh. 2 - Prob. 4DQCh. 2 - Prob. 5DQCh. 2 - Prob. 1PCh. 2 - Prob. 2PCh. 2 - Prob. 3PCh. 2 - Prob. 4PCh. 2 - Prob. 5P
Ch. 2 - Prob. 6PCh. 2 - Prob. 7PCh. 2 - Prob. 8PCh. 2 - Prob. 9PCh. 2 - Prob. 10PCh. 2 - Prob. 11PCh. 2 - Prob. 12PCh. 2 - Prob. 13PCh. 2 - Prob. 14PCh. 2 - Prob. 15PCh. 2 - Prob. 16PCh. 2 - Prob. 17PCh. 2 - Prob. 18PCh. 2 - Prob. 19PCh. 2 - Prob. 20PCh. 2 - Prob. 21PCh. 2 - Prob. 22PCh. 2 - Prob. 23PCh. 2 - Prob. 1.1QCh. 2 - Prob. 1.2QCh. 2 - Prob. 1.3QCh. 2 - Prob. 2.1QCh. 2 - Prob. 2.2QCh. 2 - Prob. 2.3QCh. 2 - Prob. 3.1QCh. 2 - Prob. 3.2QCh. 2 - Prob. 3.3QCh. 2 - Prob. 3.4Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Labour Intensity (manhour/unit) Planned production (units) Product A 1,500 15 2.000 C 4.500 D 2.000 16 500 Calculate manpower needs A manufacturing company plans following production and labour intensity of their products for the next year:The company expect to meet the performance standard at 100 %. In average there are annually 20 days of vacation, 7 days of sickness, and 4 day of other absence. The manufacture works in two-shifts with 7.75 working hours per shift. Annually there are 252 working days. 1. Calculate the need of workers to cover the production. The answer is:arrow_forwardTemaTire Services (TTS) decided to hire a new mechanic to handle all tire changes for customers ordering a new set of tires. Two mechanics have been shortlisted for the job. One mechanic has limited experience, can be hired for GH¢14 per hour, and can service an average of three customers per hour. The other mechanic has several years of experience, can service an average of four customers per hour, but must be paid GH¢20 per hour. Historical data shows that customers arrive at the TTS garage at the rate of twocustomers per hour. 5a)Assuming Poisson arrivals and exponential service times, compute the following for eachmechanic:(i).Average number of customers waiting(ii).Average number of customers in the system(iii).The average time spent in the queue(iv).The average time spent in the system(v).The probability that no queues would build up(vi).The probability that exactly two customers are waiting at any given time.(vii).The probability that up to two customers are waiting at any…arrow_forwardTemaTire Services (TTS) decided to hire a new mechanic to handle all tire changes for customers ordering a new set of tires. Two mechanics have been shortlisted for the job. One mechanic has limited experience, can be hired for GH¢14 per hour, and can service an average of three customers per hour. The other mechanic has several years of experience, can service an average of four customers per hour, but must be paid GH¢20 per hour. Historical data shows that customers arrive at the TTS garage at the rate of twocustomers per hour. 5a)Assuming Poisson arrivals and exponential service times, compute the following for eachmechanic:(i).Average number of customers waiting(ii).Average number of customers in the system(iii).The average time spent in the queue(iv).The average time spent in the system(v).The probability that no queues would build up(vi).The probability that exactly two customers are waiting at any given time.(vii).The probability that up to two customers are waiting at any…arrow_forward
- The following information was a collected and calculated from a excavating activity that included a change order. Use the following information to calculate how many worker hours were added to this activity because of the change order. Non-Impacted Impacted Units Produced 2,000 CY 3,000 CY 0.125 WRK-HR CY WRK-HR Productivity 0.15arrow_forwardTema Tire Services (TTS) decided to hire a new mechanic to handle all tire changes for customers ordering a new set of tires. Two mechanics have been shortlisted for the job. One mechanic has limited experience, can be hired for GH¢14 per hour, and can service an average of three customers per hour. The other mechanic has several years of experience, can service an average of four customers per hour, but must be paid GH¢20 per hour. Historical data shows that customers arrive at the TTS garage at the rate of two customers per hour. b) If the company assigns a customer waiting cost of GH¢30 per hour, which mechanic provides the lower operating total cost (TC)? c) With the aid of a sketch, show the economic relationship between service cost and waiting costs, and justify whether or not it is necessary for TTS to keep investing in better and/or additional mechanics until waiting time reduces to zearrow_forwardFast Burger Inc. is building a new restaurant near a college football stadium. The restaurant will be open 16 hours per day, 360 days per year. Managers have concluded that the restaurant should have the capacity to handle a peak hour demand of 120 customers. Assume front-counter service personnel can take and assemble orders at the service rate of 14 customers per hour and the target labor utilization rate for this job is 70 percent. According to the information, determine the the number of front-service counter people that should be assigned to this peak demand period. Only for non-integer results, round your answer UP to the nearest integer. For example, if your answer is 5.05, type 6; if your answer is 5, type 5. Your Answer: Answerarrow_forward
- SkyChefs, Inc., prepares in-flight meals for a number of major airlines. One of the company’s products is grilled salmon in dill sauce with baby new potatoes and spring vegetables. During the most recent week, the company prepared 4,300 of these meals using 1,250 direct labor-hours. The company paid its direct labor workers a total of $11,250 for this work, or $9.00 per hour. According to the standard cost card for this meal, it should require 0.30 direct labor-hours at a cost of $8.50 per hour. Required: 1. What is the standard labor-hours allowed (SH) to prepare 4,300 meals? 2. What is the standard labor cost allowed (SH × SR) to prepare 4,300 meals? 3. What is the labor spending variance? 4. What is the labor rate variance and the labor efficiency variance?arrow_forwardDev A restaurant earns $3,950 in sales from 64 guests for Monday’s dinner. Four (4) back-of-the-house employees work the full three-hour dinner shift that night. What is the back-of-the-house team’s sales per person-hour rate? What is the back-of-the-house team’s covers per person-hour rate?arrow_forwardAt Symtecks, the output of a specific process is valued at $100 per unit. The cost of labor is $50 per hour including benefits. The accounting department provided the following information about the process for the past four weeks: Week 1 Week 2 Week 3 Week 4 Units Produced 1,124 1,310 1,092 981 Labor ($) 12,735 14,842 10,603 9,526 Material ($) 21,041 24,523 20,442 18,364 Overhead ($) 8,992 10,480 8,736 7,848 a. Use the multifactor productivity ratio to see whether recent process improvements had any effect and, if so, when the effect was noticeable.b. Has labor productivity changed? Use the labor productivity ratio to support your answer.arrow_forward
- A restaurant earns $3,950 in sales from 64 guests for Monday’s dinner. Four (4) back-of-the-house employees work the full three-hour dinner shift that night. What is the back-of-the-house team’s sales per person-hour rate? What is the back-of-the-house team’s covers per person-hour rate?arrow_forwardAvis Company is a car rental company that is located three miles from the Los Angeles airport (LAX). Avis is dispatching a bus from its offices to the airport every 2 minutes. The average traveling time (round-trip) is 20 minutes.a. How many Avis buses are traveling to and from the airport?b. The branch manager wants to improve the service and suggests dispatching buses every 0.5 minutes. She argues that this will reduce the average traveling time from the airport to the Avis offices to 2.5 minutes. Is she correct? If your answer is negative, what will the average traveling time be?arrow_forwardData Products, Inc., packages and distributes a variety ofpersonal computer-related products. A time study hasbeen conducted for a job packaging 3.5-inch personalcomputer diskettes for shipment to customers. The jobrequires a packager to place 20 diskettes in a rectangularplastic bag, close the bag with a twist tie, and place thefilled bag into a bin, which is replaced by another workerwhen it is filled. The job can be broken into four basic elements. The elemental times (in minutes) were ob-tained from the time study for 10 job cycles shown in the following table. a. Using an allowance factor of 16%, determine the stan-dard time for this job. b. Determine the number of cycles for this time studysuch that the company would be 95% confident that theaverage time from the time study is within 4% of thetrue average cycle time.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,