Explanation of Solution
Maximizing the Net Present Value (NPV):
According to the given information, a company contains 9 projects under consideration. Each project the NPV is added and the capital required by every project during the next two years.
Now consider “xi” be the fraction of investment that is undertaken as i = 1, 2, K, 9
The objective function is to maximize the NPV of the investment.
Maximize
Constraint 1:
At 1st year, $50 million is available for investment.
The expression is:
Constraint 2:
At 2nd year, $20 million is available for investment.
The expression is:
Trending nowThis is a popular solution!
Chapter 3 Solutions
Introduction to mathematical programming
- The WIX Company Civil Engineers consists of two divisions. The divisions are Water and Waste Water. The company sells engineering services to various customers. The following are the bill rates for the various staff classifications: Vice President $200/hour Senior Engineer $180/hour Staff Engineer $150/hour. The two divisions expect to bill the following hours: Water- 10000 hours, vice president at 10% of the time, 30% of Senior Engineer time and remaining to Staff Engineers. Waste Water- 6000 hours, vice president at 20% of the time, 20% of Senior Engineer time and remaining to Staff Engineers. The Direct Labor costs per hours are as follows: Vice President $80/hour Senior Engineer $60/hour Staff Engineer $40/hour. The utilization for each staff members are as follows: Vice President 60% Senior Engineer 80% Staff Engineer 90%. The company has the following other costs: Admin Salaries $90,000 Rent $100,000 Utilities $6,000 Benefits $76,000 Assume 20% of time for each staff member…arrow_forwardWorkers at a particular company are paid at a rate of 150.00 per hour for up to 40 hours of work at hour over that is paid at a rate of 1.5 times the normal rate. From the worker’s gross pay, 14% is withheld for income tax, 5% withheld for social security system tax, and 13% is withheld for state income tax. An additional 10% is withheld if the worker has 3 or more covered dependents to cover extra cost of health insurance. Draw the flowchart and write or code the C program that outputs the worker’s gross pay, each withholding and the net take home pay for the week.arrow_forwardWorkers at a particular company are paid at a rate of 150.00 per hour for up to 40 hours of work at hour over that is paid at a rate of 1.5 times the normal rate. From the worker’s gross pay, 14% is withheld for income tax, 5% withheld for social security system tax, and 13% is withheld for state income tax. An additional 10% is withheld if the worker has 3 or more covered dependents to cover extra cost of health insurance. Draw the flowchart and code the C program that outputs the worker’s gross pay, each withholding and the net take home pay for the week.arrow_forward
- A company manufactures three products 1, 2, and 3. Each product requires production time in three departments as shown below: PRODUCT DEPARTMENT 1 DEPARTMENT 2 DEPARTMENT 3 1 3 hr/unit 2 hr/unit 1 hr/unit 2 4 hr/unit 1 hr/unit 3 hr/unit 3 2 hr/unit 2 hr/unit 3 hr/unit There are 500, 400, and 300 hours of production time available in the three departments, respectively. If products 1, 2, and 3 contribute $3, $4, and $2.5 per unit to profit, answer the following questions: (You may attach your solution or write in the box) a) Define the decision variables (2 marks). b) Write all constraints (3 marks). c) Write the objective function (define whether it is a maximization or minimization) (1.5 marks)arrow_forwardA company manufactures 3 products in 2 different factories. The cost of production and time required for production for each product varies depending on which factory produces it. The time and cost required for production of each product in each factory is provided in the tables in this worksheet. Demand for products 1, 2 and 3 are 200, 240 and 100 units, respectively. There are a total of 3,000 hours available in each factory. Additionally, at least 60% of the total units of Product 1 must be produced in Factory A, and at least 40% of of the total units of Product 2 must be produced in Factory B. Create a linear programming model and use the Solver add-in to determine the optimal production plan that will minimize total cost. Note: The cost is per unit not per hour. All demand must be met.arrow_forwardAn oil and gas exploration firm invested $2,000,000 in drilling for natural gas in a new gas field. The firm's geologist believes the field has the potential to produce gas for many years. The revenue resulting from the gas well the first year after drilling is $600,000; based on previous experiences with similar types of wells, it is expected the annual revenue will decrease at an annual rate of 3%. Likewise, the costs of operating the well the first year totals $100,000; costs are expected to increase at an annual rate of 7%. If the firm's MARR is 17%, how long will it take for the firm to recover its investment? Hint: Using Excel's Goal Seek or SOLVER tool leave cell for the number of years required to recover the investment empty. Click here to access the TVM Factor Table calculator. n = L1 yearsarrow_forward
- The Livewright Medical Supplies Company has a total of 12 salespeople it wants to assign to three regions-the South, the East, and the Midwest. A salesperson in the South earns $600 in profit per month for the company, a salesperson in the East earns $540, and a salesperson in the Midwest earns $375. The southern region can have a maximum assignment of five sales- people. The company has a total of $750 per day available for expenses for all 12 salespeople. A salesperson in the South has average expenses of $80 per day, a salesperson in the East has average expenses of $70 per day, and a salesperson in the Midwest has average daily expenses of $50. The company wants to determine the number of salespeople to assign to each region to maximize profit. a. Formulate an integer programming model for this problem. b. Solve this model by using the computer.arrow_forwardAssuming all Ghanaians who are at least 18 years can choose between going to school or learning a trade. GHC 100 is invested every month for a person who chooses to go to school by the government till the person attains age 30 years provided he/she completes university. If he/she does not complete university, the payment is stopped at the time he/she exited. If the person chooses to learn a trade, the government pays GHC 2000 as apprentice fee to the madam or master who will take the person as an apprentice, and invest GHC 70 a month till age 30 years. If the person does not complete the apprenticeship, the payment is stopped at the time he/she exited. Remember that persons who are less than 18 years or 30 years and above do NOT qualify to enroll on this program. You are to write a c++ program for the above scenario. Your program should a) compute the total investment made for the person if he/she either finishes or exited along the way. b) display the results.arrow_forwardAssuming all Ghanaians who are at least 18 years can choose between going to school or learning a trade. GHC 100 is invested every month for a person who chooses to go to school by the government till the person attains age 30 years provided he/she completes university. If he/she does not complete university, the payment is stopped at the time he/she exited. If the person chooses to learn a trade, the government pays GHC 2000 as apprentice fee to the madam or master who will take the person as an apprentice, and invest GHC 70 a month till age 30 years. If the person does not complete the apprenticeship, the payment is stopped at the time he/she exited. Remember that persons who are less than 18 years or 30 years and above do NOT qualify to enroll on this program. You are to write a c++ program for the above scenario. Your program should a) request a person’s name, age, what he/she wants to do (go to school or learn a trade), time of exit if any and disqualify the person if…arrow_forward
- Assuming all Ghanaians who are at least 18 years can choose between going to school or learning a trade. GHC 100 is invested every month for a person who chooses to go to school by the government till the person attains age 30 years provided he/she completes university. If he/she does not complete university, the payment is stopped at the time he/she exited. If the person chooses to learn a trade, the government pays GHC 2000 as apprentice fee to the madam or master who will take the person as an apprentice, and invest GHC 70 a month till age 30 years. If the person does not complete the apprenticeship, the payment is stopped at the time he/she exited. Remember that persons who are less than 18 years or above 30 years do NOT qualify to enroll on this program.You are to write a java program for the above scenario. Your program should a) request a person’s name, age, what he/she wants to do (go to school or learn a trade), time of exit if any and disqualify the person if he/she does not…arrow_forwardSprocket manufacturing. The manager of this production firm is faced with a potential problem: shortages in the supply of a vital gear sprocket. He is considering the development of an in-house capability to make the sprockets, knowing that the firm needs 35,000 such sprockets each year. If the firm elects to make the sprockets internally, then it must select one of the three possible production processes. Each has different costs, as shown in Table 10.17. Adopting a manual process may lead to union problems. The manager estimates the probability of these problems as 25%, and knows that if they do occur, then the variable cost will increase by $0.50 per sprocket. Further, if the semi-automatic or fully automatic option is selected, then additional training of personnel will be required. The amount and therefore the cost of training are uncertain. For the semi-automatic process, the fixed cost of basic training will add $15,000. However, there is a 20% chance the workers will need extra…arrow_forwardSteelco manufactures two types of steel at three different steel mills. During a given month, each steel mill has 200 hours of blast furnace time available. Because of differences in the furnaces at each mill, the time and cost to produce a ton of steel differs for each mill. The time and cost for each mill are shown in the table below. Each month, Steelco must manufacture at least 500 tons of steel 1 and 600 tons of steel 2. Formulate an LP to minimize the cost of manufacturing the desired steel.arrow_forward
- Operations Research : Applications and AlgorithmsComputer ScienceISBN:9780534380588Author:Wayne L. WinstonPublisher:Brooks ColeNp Ms Office 365/Excel 2016 I NtermedComputer ScienceISBN:9781337508841Author:CareyPublisher:Cengage