Traffic and Highway Engineering
Traffic and Highway Engineering
5th Edition
ISBN: 9781305156241
Author: Garber, Nicholas J.
Publisher: Cengage Learning
Question
Book Icon
Chapter 6, Problem 19P
To determine

The graph of average individual delay versus the repair period and use this graph to discuss the effect of the expected repair time on the average delay.

Expert Solution & Answer
Check Mark

Explanation of Solution

Given:

We have been given the following information:

We have been given the following information:

Total number of lanes = 3,

  V=90%of6000,

  tinc=2hr,

Mean free flow speed of the highway = 55 mi/h,

Jam density = 135 veh/mi/ln,

  Cr=4000.

Following is the lay out of the given highway section:

  Traffic and Highway Engineering, Chapter 6, Problem 19P , additional homework tip  1

Calculation:For the expected repair period of 1 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

Themaximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr=12( 90%of60004000)( 60004000)2( 60005400)

  dr=(54004000)(2000)2(600)

  dr=( 1400)( 20)12dr=2333.33=2334hr.

The total delay is dr=2334hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be foundusing the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×1.=5400Veh.

The number of vehicles that will be affected by the incident is 5400Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =23345400.=0.432hr.

The average individual is 0.432hr.

For the expected repair period of 1.5 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity and,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

Themaximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 1.52( 90%of60004000)( 60004000)2( 60005400)dr=2.25( 54004000)( 2000)2( 600)dr=2.25( 1400)( 20)12dr=5250hr.

The total delay is dr=5250hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×1.5.=8100Veh.

The number of vehicles that will be affected by the incident is 8100Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =52508100.=0.648hr.

Theaverage individualdelay is 0.648hr.

For the expected repair period of 2.5 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity and,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

The maximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 2.52( 90%of60004000)( 60004000)2( 60005400)dr=6.25( 54004000)( 2000)2( 600)dr=6.25( 1400)( 20)12dr=14583.33hr.dr=14584hr.

The total delay is dr=14584hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.5.=13500Veh.

Therefore, the number of vehicles that will be affected by the incident is 13500Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =1458413500.=1.0803hr.

The average individualdelay is 1.0803hr.

For the expected repair period of 2.75 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

Therefore, the maximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 2.752( 90%of60004000)( 60004000)2( 60005400)dr=7.5625( 54004000)( 2000)2( 600)dr=7.5625( 1400)( 20)12dr=17645.83hr.dr=17646hr.

Therefore, the total delay is dr=17646hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.75.=14850Veh.

The number of vehicles that will be affected by the incident is 14850Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =1764614850.=1.188hr.

the average individual delay is 1.188hr.

For the expected repair period of 3.0 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity and,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

The maximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 3.02( 90%of60004000)( 60004000)2( 60005400)dr=9.0( 54004000)( 2000)2( 600)dr=9.0( 1400)( 20)12dr=21000.00hr.

The total delay is dr=21000.00hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×3.00.=16200Veh.

The number of vehicles that will be affected by the incident is 16200Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =2100016200.=1.30hr.

The average individual delay is 1.30hr.

Plot the graph of average individual delay versus the repair period is as follows:

  Traffic and Highway Engineering, Chapter 6, Problem 19P , additional homework tip  2

Conclusion:

Therefore, for 1.0 hour : Themaximum queue length that will be formed is qmax=2800Veh, total delay is dr=2334hr ,number of vehicles that will be affected by the incident is 5400Veh and theaverage individual is 0.432hr.

For 1.5hour:

Themaximum queue length that will be formed is qmax=2800Veh ,total delay is dr=5250hr ,number of vehicles that will be affected by the incident is 8100Veh and the average individual is 0.648hr.

For 2.50hour:

Themaximum queue length that will be formed is qmax=2800Veh.

The total delay is dr=14584hr.

The number of vehicles that will be affected by the incident is 13500Veh.

The average individual delayis 1.0803hr.

For 2.75hour:

Themaximum queue length that will be formed is qmax=2800Veh.

The total delay is dr=9334hr.

The number of vehicles that will be affected by the incident is 10800Veh.

The average individual delay is 1.188hr.

For 3.0 hour:

Themaximum queue length that will be formed is qmax=2800Veh.

The total delay is dr=21000.00hr.

The number of vehicles that will be affected by the incident is 16200Veh.

The average individual delay is 1.30hr.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The following chart shows the average number of hours commuters spend in traffic delays per year at the six most congested cities in the U.S. Most Congested Cities Baltimore New York Houston Los Angeles Chicago Washington 0 10 O C OD OB Ο Α 20 30 40 50 Average Hours per Year 60 70 80 Which of the following statements is not correct? A) Houston commuters have a higher average number of hours spent per year in traffic delays when compared to New York commuters. B) Los Angeles commuters have a lower average number of hours spent per year in traffic delays when compared to Washington commuters. C) Baltimore commuters have the lowest average number of hours spent per year in traffic delays. D) Chicago commuters have the highest average number of hours spent per year in traffic delays.
Can someone please show me how to solve this step by step. Thank you Suppose you are hired by the UHM Transportation and Traffic Lab (TTL) to analyze vehicle arrivals at one lane of the interchange bridge connecting I-25 and I-40 for the period from 12:00am to 4:00am in a weekday. It is known that vehicle arrivals follow a Poisson process at this location. There is a single-loop detector embedded on this lane at the end of the interchange bridge. Since you do not want to go to the bridge to count vehicles at this time period, you decided to use the loop detector data for the analysis. Of the 720 20-second intervals (the loop detection system stores data every 20 seconds), 508 intervals were identified to have at least one vehicle detected. Assume the loop detector is free of error. Please estimate the vehicle arrival rate (vehicles per second) for this lane. With the estimated arrival rate, please calculate the probability of having three or more vehicles detected in a 20-second…
A highway bridge is currently scheduled to be inspected once every two years. There is a 3% probability that during an inspection a major defect will be found. Compute the probability that in the next 12 years no defects will be found in the bridge. Assume statistical independence concerning finding defects in different inspections.
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning