Planning an innovative house. A local electric company wants to build an experimental house that will conserve energy. Company officials believe the project breaks down naturally into the following tasks (the time required for each task is given in parentheses):
1. Draw plans for house (2 months)
2. Design energy systems for house (6 months)
3. Develop new insulation techniques (3 months)
4. Purchase land (4 months)
5. Build conventional shell of house (6 months)
6. Install new energy systems (2 months)
7. Install new insulation (1 month)
8. Finish the remaining conventional parts of the house (3 months)
9. Landscape (1 month)
10. Perform tests to determine energy usage in house (8 months)
Determine a reasonable list of dependencies for these tasks, then draw a PERT diagram and develop a schedule for these tasks. Answers will vary.
Want to see the full answer?
Check out a sample textbook solutionChapter 4 Solutions
Mathematics All Around (6th Edition)
- Solar energy generation along highways. The potential of using solar panels constructed above national highways to generate energy was explored in the International Journal of Energy and Environmental Engineering (December 2013). Two-layer solar panels (with 1 meter separating the panels) were constructed above sections of both east-west and north-south highways in India. The amount of (kilowatt-hours) supplied to the country's grid by the solar panels above the two types of highways was determined each month. The data for several randomly selected months are provided in the table. The researchers concluded that the "two-layer solar panel energy generation is more viable for the north-south oriented highways as compared to east- west oriented roadways." Compare the mean solar energy amounts generated for the two types of highways using a 95% confidence interval. Does the interval support the re- energy searchers' conclusion? Month East-West North-South February April July September…arrow_forwardHectic Repair Org. HRO) helps repair homes that are structurally weakened by minor earthquakes. After an earthquake, SmartProtect, an insurance company of some affected customers in the area estimates that the standard time to perform a preliminary damage assessment on an average-sized house would be about two hours. On behalf of the affected customers, SmartProtect is willing to pay a HRO employee doing such damage assessments $65 per hour. Suppose that Michael (an employee at HCRO who does flood damage assessment) takes three hours to complete the assessment on an average-sized house. What is Michael efficiency based on the standard time estimated by SmartProtect? a. Approximately one hundred and fifty percent. b. About one-third of an assessment job per hour c. Approximately one hundred and thirty dollars per assessment d. Approximately one hundred and ninety five dollars per assessment (before taxes) e. Approximately sixty seven percent.arrow_forwardThe production level needed from the agricultural sector, the manufacturing sector, and the energy sector is ..... ....... ....... units.arrow_forward
- XYZ Company has the following capacity per month based on the following: 23 working days per month 1 shift operation at 8 hours per shift. 40 minutes break per shift per employee XYZ company produces bicycles and has the following Capacities per process. Frame Welding: 40 bikes per hour per machine Painting: 20 bikes per hour per worker Assembly : 25 bikes per hour per worker Inspection: 35 bikes per hour per worker If the company needs 3,000 bikes per month, can the company deliver based on the abovementioned capacities? YES or No? Show Excel Computation. No No answer text provided. Yes No answer text provided.arrow_forwardFloods: Rapid drainage of floodwater is crucial to prevent damage during heavy rains. Several designs for a drainage canal were considered for a certain city. Each design was tested five times, to determine how long it took to drain the water reservoir. The following table presents the drainage times, in minutes. Channel Type Drainage Time 1 41.5 43.2 50.2 41.2 24.2 2 38.8 48.2 51.0 38.1 25.2 3 32.7 33.5 35.0 22.7 24.7 4 26.5 30.7 33.1 23.8 26.7 5 45.1 47.3 48.4 37.1 40.0 Construct an ANOVA table. Round your answers to four decimal places. One-way ANOVA: Drainage Time Source DF SS MS F P Minutes Error Totalarrow_forward2. Floods: Rapid drainage of floodwater is crucial to prevent damage during heavy rains. Several designs for a drainage canal were considered for a certain city. Each design was tested five times, to determine how long it took to drain the water in a reservoir. The following table presents the drainage times, in minutes. Channel Type Drainage Time 1 41.4 43.4 50.0 41.2 2 38.7 48.3 51.1 38.3 3 32.6 33.7 34.8 22.5 4 26.3 30.9 33.3 23.8 5 44.9 47.2 48.5 37.1 a. Construct an ANOVA table. b. Can you conclude that there is a difference in the mean drainage times for the different channel designs? Use the α = 0.01 level of significance.arrow_forward
- 1.2 Section Exercis A nurse mixes 70 cc of a 60% saline solution with a 30% saline solution to produce a 44% saline solution. How much of the 30% solution should he use? The amount of 30% saline solution needed is C. Save For Later Submit Assignment Check Answer © 2021 McGraw Hill LLC. All Rights Reserved. Terms of Use Privacy Center MacBook Airarrow_forward: 39% in 30m 20 CALENDAR Travel to Home Today at 11:02 PM Green Street f... Lumen... Sign In or School.. ohm Rukayat Balogun오 | User Settings My Classes Log Out ork manager ges Forums Calendar Gradebook 1:30am Fall 2018> Assessment pplications of Systems of Equations Due in 11 hours, 28 minutes. Due Fri 12/21/2018 10:00 am Monico needs to mix a 10% alcohol solution with a 50% alcohol solution to create 100 milli!eters of a 26% solution. How many millileters of each solution must Monico use? Answer: Monico must mix -milli!eters of 10% solution and milli!eters of 50% solution. Points possible: 1 Unlimited attempts License Submit onarrow_forwardQ. 1 The discharge analysis report of Anywhere Health Care Facility shows 1752 discharges (including deaths) for October 2020. Fifty-two deaths were also shown in the report. Find gross death rate. Q. 2 Inpatient deaths at Anywhere Health Care Facility for 2020 totalled 150. Inpatient deaths that occurred less than 48 hours after admission to the facility totalled 75. Total discharges (including deaths) were 25,546. Calculate net death rate. Q. 3 Anywhere Health Care Facility performed 692 surgical procedures during March and administered 652 anaesthetics. Deaths resulting from the administration of an anaesthetic totalled five for the month. Find Anaesthesia death rate. Q. 4 Surgery was performed on 492 patients in the Anywhere Health Care Facility during March, and 27 of those patients died within 10 days of surgery. Find Postoperative death rate. Q.5 In the month of June 4500 inpatients days were served in a hospital with 150 beds. Calculate the percentage of inpatient occupancy…arrow_forward
- ] < 8Algebra 1.Benchmark1.Fall22 S Module 1: The Road to Revolution DUE September 30 | Schoology Question 7 O O esc O A. ©2022 B. C. Tina has two part-time jobs. • She earns $12 per hour working at a store. . She earns $30 per lawn mowed working for a landscaper. Her goal is to earn $1,800 to pay her monthly expenses. The situation can be modeled by the formula below, where g represents the hours Tina works in the grocery store and m represents the number of lawns mowed. 1,800 12g + 30m After Tina learns how many hours she is scheduled to work in the grocery store, she has to figure out how many lawns she needs to mow that month. Which equation shows the formula correctly rearranged to find m given g ? M=- M = - m = D. m = 1 5 2 --- 1 → 5 29 g + 1,800 25 ▶▶ 2 5 g+150 g+60 g+1,800 Illuminate EducationTM, Inc. Q Zoom in 2 0 #3 $ 4 er dº K testing.illuminateed.com X District Assessment Results 2022-2023 - Destiny Murdock <6 = MacBook Pro & 7 8 ( с 9 Questi 0arrow_forwardThe principle of redundancy is used when system reliability is improved through redundant or backup components. Assume that a student's alarm clock has a 8.2% daily failure rate. Complete parts (a) through (d) below.arrow_forwardFarm Fact #3: In 2007, Massachusetts maple producers set 230,000 taps to collect sap, which, after boiling produced 30,000 gallons of maple syrup. It takes about 40 gallons of sap to produce one gallon of syrup." And "Suppose the sap is collected in gallon buckets that hang under each tap, and the maple season lasts one month? And "Read the label of a "pancake syrup" bottle to find out how much maple syru it contains." How many gallons of syrup did each tap yleld? How many gallons of sap did each tap yield? What extra information would you need ot estimate the number of sugar maple trees that were tapped? How many times a day (how often) will the buckets of sap need to be emptled? (What fraction of a bottle of generic "pancake syrup" is pure maple syrup?) What fraction of the cost of generic "pancake syrup" can you attribute to the cost of pure maple syrup?arrow_forward
- Algebra & Trigonometry with Analytic GeometryAlgebraISBN:9781133382119Author:SwokowskiPublisher:Cengage