A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=5.
Q: This section explains project scheduling strategies such as the WBS, Activity Definition, and…
A: Scheduling is the process of arranging the production activities in order to complete the…
Q: Consider the AON graph of a project shown below. AA Figure 19.17 Аз A6 A7 Ag A2 A5 The activity…
A: The concept of AON Diagram is mostly used in project management. The AON diagram is a network…
Q: Critical Path Method (CPM) helps project manager to plan all tasks that must be completed as part of…
A: Given data is
Q: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C.…
A: Network diagram as per given information:
Q: There is a running project in the company that you work for, which has the following activities:…
A: Given data is
Q: The network diagram below (activity on arrow) shows the activities needed to complete a project to…
A: ANSWER IS AS BELOW:
Q: A new project is to be completed. The following activities need to be completed in the order shown,…
A: Find the estimated time calculation below:
Q: The plans and documents that can be created from WBS are called often called as: A. The plans B.…
A: The plans and documents that can be created from WBS are called often called as: The plans The…
Q: The following bar chart shows the activities for a project. The total project cost is $1,545. Total…
A: Given information, Activity Total Cost Time (Weeks) 1 2 3 4 5 6 7 8 9 10 A 120…
Q: Compare and contrast the three common CPM methods (e.g., single time estimate, three activity time…
A: The critical path method is a technique that is used in project management to define critical and…
Q: Describe and differentiate these steps.
A: PERT and CPM both are tools of project management that helps in scheduling the tasks of the…
Q: Project scheduling strategies such as the Work Breakdown Structure (WBS), Activity Definition (AD),…
A: Introduction- A project schedule is a timeline that illustrates the start and end dates of all…
Q: What is the use of Total float(TF), Free Float(FF), Independent float(IF) in scheduling. How it…
A: A Small Introduction about Project Management Project the executives' gives construction and…
Q: A schedule for two processors has been created for the following project which has a finishing time…
A: A network diagram along with activity timings is given:
Q: Given the following activity network: Ki A1 Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3…
A: Given data The activity A1 takes 5 weeks The activity A2 takes 8 weeks The activity A3 takes 2…
Q: Draw a network diagram that represents the following activities of a project: Activity Immediate…
A: A network is a graphical representation of a project, depicting the flow as well as the sequence of…
Q: A project plan consisting of ten events has predecessor relationships as under. Immediate…
A: In the AOA network diagram, Arrows are used to represent the activities
Q: In an AON graph of a project, there only exists one path from the first to the last activity.True or…
A: b. False
Q: On a piece of scratch paper, draw the early-start Gantt Chart associated with this table and…
A: A gantt chart refers to the graphical representation of the schedule of the project. It is a chart…
Q: AA Аз A6 Ag A7 A2 A1 A5 The activity times are 3, 4, 2, 5, 7, 2, 2, and 3 days for activities A,…
A: The critical path consists of the longest sequence of activities from project start to finish that…
Q: 2 Paint Window Install Sills Windows (2) (2) Remove Siding Add New Siding a Paint Exterior (2) (4)…
A: Find the Given details below: Activity Duration 1-2 2 1-3 2 1-4 1 2-6 2 3-6 4 4-5 4…
Q: How long it will take for each activity on the network chart is all but one of the following. O…
A: Answer: Estimated duration
Q: Project scheduling strategies such as the Work Breakdown Structure (WBS), Activity Definition (AD),…
A: WORK BREAKDOWN STRUCTURE: Work breakdown structure is an organized methodology used to split an…
Q: A project has eight activities that need to be completed (Activity A to H) and will be completed in…
A: ES = maximum (EF of all immediate predecessor) EF = ES + duration Minimum project duration = largest…
Q: What are the differences between the Forward Pass, the Backward Pass, Total float, and Free float in…
A: Project Scheduling: In the project scheduling, Forward pass and Backward pass help…
Q: The table below contains data for the installation of new equipment in a manufacturing process for a…
A: Since you have submitted a question with multiple subparts, as per guidelines, we have answered the…
Q: snip
A: Given: Task A must be completed to before B and C are started. Task C must be completed before task…
Q: Activities, preceding activities, normal and crashed completion times of each of the activities and…
A: Forward Pass: Early Start (ES) = Maximum EF value from immediate Predecessor(s) Early Finish (EF) =…
Q: Activity-On-Node (AON) networks for the project.
A: A network diagram is a graphical representation of a project based on visualizing the activity…
Q: You have prepared the following schedule for a project in which the key resources is a tractor.…
A: SOLUTION:
Q: Microsoft Project in Project Schedule Management
A: Out of all the softwares for Project Management, the one which has been popular over years is…
Q: Activities A, B, C, and D are on the critical path of the network diagram below: The cost and…
A: According to the questions Task Cost Time (Days) A $2,5000 4 B $5,000 3 C $10,000 6 D…
Q: A simple CPM network has three activities, G, H, and I. G is an immediate predecessor of H and of I.…
A: ANSWER IS AS BELOW:
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Project length is the evaluation of the amount of time needed by a specific project activity carried…
Q: Project scheduling methods such as the Work Breakdown Structure (WBS), Activity Definition (AD), and…
A: Below is the solution:-
Q: Amanufacturer is designing a product layout for a new product production. It plans to use a…
A: Cycle time is the actual total time incurred in manufacturing a product by the team members in an…
Q: A manufacturer is designing a product layout for a new product productionIt plans to use a…
A: The cycle time is the amount of time it carries to achieve a specific task from start to finish. You…
Q: The following is a table of activities associated with a project at Ralay crash cost to reduce…
A: Network Diagram :
Q: As discussed in class, in using Critical Path Method (CPM) in Project Management, A. the critical…
A: The Path having the longest duration is Critical Path. It indicates the total time needed to…
Q: Given the following activity network: A1 A3 activity A1 takes 5 weeks, A2 takes 10 weeks, and A3…
A: Given dataActivity A1 = 5 weeksActivity A2 = 10 weeks Activity A3 = 7 weeks
Q: Amanufacturer is designing a product layout for a new product production. It plans to use a…
A: A demand forecast refers to when historical data and other information get employed for making…
Q: Given the activities of a project; their optimistic (to), most likely (tm) and pessimistic (tp) time…
A: As the table is missing form your question. I am considering the table given below because I have…
Q: In making a forward pass through a network, three activities are immediate predecessors for activity…
A: For the given statement, the last option is the correct answer. The largest EF for the three…
Q: Constraints in project management are some important factors that everyone must work within to…
A: Any project has restrictions and hazards that must be handled in order for the project to be…
Q: Project scheduling fulfills several functions. What exactly are they?
A: The term "schedule" pertains to a sort of timeline. Scheduling is a project management component…
Q: PERT is different from CPM in 'that
A: PERT or Project evaluation or review technique is a strategy used in project management to…
Q: A simple CPM network has three activities, N, O, and P. N is an immediate predecessor of O and of P.…
A: ANSWER IS AS FOLLOW:
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- A simple CPM network has three activities, G, H, and I. G is an immediate predecessor of H and of I. H is an immediate predecessor of I. The activity durations are G = 5, H = 2, 1 = 2. O A. The critical path is H-I, duration 4. B. The network has no critical path. O C. The critical path is G-H-I, duration 3. O D. The critical path is G-I, duration 7. E. The critical path is G-H-I, duration 9.a. Determine the expected activity completion times. b. Identify the critical path. *Please answer letter A and B above. Note: to = optimistic, tm = most likely, and te = expected time.Consider a project that has been modeled as in the table below. Part a) Draw the PERT/CPM network for this project and determine the project’s expected completion time μP and its critical path. Part b) Suppose the standard deviations of the activity durations are σA = 2, σB = 1, σC = 0, σD = 2, σE = 3, and σF = 0. Then please estimate the standard deviation of the overall project’s standard deviation σP . Part c) Suppose for the standard Normal random variable Z, we know P[−1 ≤ Z ≤ +1] ' 68%, P[−2 ≤ Z ≤ +2] ' 95%, and P[−3 ≤ Z ≤ +3] ' 99.7%. Then, approximately what time T is one for which there is only a less than 2.5% chance for the completion time to beat (be shorter than)? *Please answer a-c and type your work and answers or write them neatly please* Thank you
- Consider a project that has been modeled as in the table below. Part a) Draw the PERT/CPM network for this project and determine the project’s expected completion time μP and its critical path. Part b) Suppose the standard deviations of the activity durations are σA = 2, σB = 1, σC = 0, σD = 2, σE = 3, and σF = 0. Then please estimate the standard deviation of the overall project’s standard deviation σP . Part c) Suppose for the standard Normal random variable Z, we know P[−1 ≤ Z ≤ +1] ' 68%, P[−2 ≤ Z ≤ +2] ' 95%, and P[−3 ≤ Z ≤ +3] ' 99.7%. Then, approximately what time T is one for which there is only a less than 2.5% chance for the completion time to beat (be shorter than)? *Please answer a-c and either type your work and answers or write them neatly showing each step, please* NO EXCEL Thank you!The following represents a project that should be scheduled using CPM: ACTIVITY A B C D E F G H IMMEDIATE PREDECESSORS A A B C, D D, E F,G b. What is the critical path? ⒸA-D-G-H OB-E-G-H ⒸA-C-F-H A-D-F-H Probability TIMES (DAYS) b Project completion time a 1 1 2 1 1 3 1 2 m 2 2 2 8 2 4 3 3 6 9 11 9 3 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. 11 11 11 X Answer is not complete. days d. What is the probability of completing this project within 19 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS ACTIVITY A ABCDEFGH B-E-G-H b. What is the critical path? A-C-F-H OA-D-F-H A-D-G-H A A B C,D D, E F,G Project completion time a LLL23312 TIMES (DAYS) m •WNNW: 3 2 2 3 4 4 4 4 b 5 3 3 4 11 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. days 565
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: a. the critical activities for the leadership training program development project are: _____ b. the project length for the leadership training program development project= __ days. c. Slack time for each of the activities is: Activity: Slack time: A ______ B ______ C ______ D ______ E ______ F ______ G ______Consider the following activity description with associated cost data shown in Table 1. The cost data represents the total cost and should be considered linear with time. Table 1: Crash Cost Table Activity Immediate Predecessor Normal Duration (days) Normal Cost ($) Crash Duration (days) Crash Cost ($) A --- 5 50 3 150 B --- 4 40 2 200 C B 7 70 5 250 D A, C 2 20 1 50 E A, C 5 125 1 525 F B 10 80 7 290 G D 7 50 3 250 H E, F 6 60 3 180 Reduce the project duration to minimum duration and calculate the cost. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.In the space provided below create the network diagram that shows the relationship (logic) of project activities shown below and then number each event. 1. In a given project activities "A, B and C are initial activities that may begin at the same time 2. -----"D" cannot begin until "A" is complete. 3. ----- "B" must be complete before E can begin. 4. ----- "F" cannot start until "C" is finished. 5. ----- "G" cannot begin until "B" is finished. 6. ----- "G" and "D" must be done before "H" can begin. 7. ----- "I" cannot begin until "B" is finished. 8. ----- "J" can begin only after "F" and "I" are complete. 9. ----- Once "E" is complete, "K" can begin. 10. ---- The project will be finished when "H" "J" and "K" are complete.
- Activity Normal_time Crash_time Normal_cost Crash_cost Slack A 31 17 4800 6200 В 14 14 5500 5500 C 34 18 5100 6600 21 17 4500 6800 E 15 15 5300 5300 F 17 17 5300 5300 The table shows normal time, crash time, normal cost, crash cost and slack time of activities in a project. According to this table which activity must be crashed first? Assume there is only one critical path. (Only type the name of the activity, Example: A. @orsdemir. Copyrighted content. Cannot be posted.) 0ㅇ11 2 0Example: Undertaking by a contractor to implement a contracting for excavation works according to the scheme below, undertaking to complete the work within a period of 36 weeks with a probability of 99% between in light of the contractor's probability. The actual time period for the completion of the project within the PERT technology? Act. a b te u C.P 1-2 7 8. 6.33 1 1 *1,2 2-3 6. 9 6.33 0.66 0.443 *2 2-4 3 7 8. 6.5 0.83 .693 *1 2-5 4 6. 0.33 3-6 9. 10 8.66 0.66 0.443 *2 4-7 6. 8 11 8.166 0.83 .693 *1 5-7 4 7 5.83 0.5 6-8 7 10 7.16 0.83 .693 *2 7-8 4 8 7.5 0.83 .693 *1 8-9 4 7 9 6.83 0.83 .693 *1,2Three critical path activities from the same critical path are candidates for crashing on a CPM network. What is the crash cost per unit time for activity A? What is the crash cost per unit time for activity B? Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? Assuming no other paths become critical, which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost? Assuming no other paths become critical, how much can this project be shortened at what total added cost?