Three critical path activities from the same critical path are candidates for crashing on a CPM network. What is the crash cost per unit time for activity A? What is the crash cost per unit time for activity B? Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? Assuming no other paths become critical, which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost? Assuming no other paths become critical, how much can this project be shortened at what total added cost?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Three critical path activities from the same critical path are candidates for crashing on a CPM network.

  1. What is the crash cost per unit time for activity A?
  2. What is the crash cost per unit time for activity B?
  3. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
  4. Assuming no other paths become critical, which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?

Assuming no other paths become critical, how much can this project be shortened at what total added cost?

Activity Normal Time Normal Cost
Crash
Duration
Crash Cost
A
9 days
$8,000
5 days
$12,000
B
5 days
$9,200
4 days
$10,000
C
12 days
$9,000
11 days
$12,000
Transcribed Image Text:Activity Normal Time Normal Cost Crash Duration Crash Cost A 9 days $8,000 5 days $12,000 B 5 days $9,200 4 days $10,000 C 12 days $9,000 11 days $12,000
Expert Solution
steps

Step by step

Solved in 7 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.