Chapter 9, Problem 52P
(a)
To determine
The benefit-cost ratio for Alternative X
(b)
To determine
The best alternative based on payback period.
(c)
To determine
The preferred alternative based on incremental benefit cost analysis.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Determine the process to compare alternatives on an equal basis and select the alternative that is wisest from an economic standpoint?
You have been asked to perform an economic evaluation of two projects and recommend one of
them for implementation. The project parameters are as follows:
Project A
Project B
Discount
Rate
4.0%
4.0%
Your analysis concludes that:
Project Cost
$1,000,000
$750,000
Project Life
(yrs)
10
15
Elec. Savings Elec. Cost
(kWh/yr)
($/kWh)
800,000
600,000
O Project A is preferable, but Project B also has attractive performance.
O Project B is preferable, but Project A also has attractive performance.
O Project B is preferable and Project A results in a net loss.
O Project A is preferable and Project B results in a net loss.
$0.12
$0.12
Annual Cost
Escalation Rate
1.5%
1.5%
Alternatives B and C are replaced at the end of their useful lives with identical
replacements.
Find the best alternative using MARR = 10%.
Data
Initial Cost
Uniform Annual Benefit
Useful Life
a) Benefit to Cost ratio analysis
b) Payback Period Analysis
Alt. A
$6,00
$150
20
Alt. B
$900
$300
5
Alt. C
$1,800
$450
10
Chapter 9 Solutions
ENGR.ECONOMIC ANALYSIS
Ch. 9 - Prob. 2QTCCh. 9 - Prob. 3QTCCh. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Prob. 3PCh. 9 - Prob. 4PCh. 9 - Prob. 5PCh. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8P
Ch. 9 - Prob. 9PCh. 9 - Prob. 10PCh. 9 - Prob. 11PCh. 9 - Prob. 12PCh. 9 - Prob. 13PCh. 9 - Prob. 14PCh. 9 - Prob. 15PCh. 9 - Prob. 16PCh. 9 - Prob. 17PCh. 9 - Prob. 18PCh. 9 - Prob. 19PCh. 9 - Prob. 20PCh. 9 - Prob. 21PCh. 9 - Prob. 22PCh. 9 - Prob. 23PCh. 9 - Prob. 24PCh. 9 - Prob. 25PCh. 9 - Prob. 27PCh. 9 - Prob. 28PCh. 9 - Prob. 29PCh. 9 - Prob. 30PCh. 9 - Prob. 31PCh. 9 - Prob. 32PCh. 9 - Prob. 33PCh. 9 - Prob. 34PCh. 9 - Prob. 35PCh. 9 - Prob. 36PCh. 9 - Prob. 37PCh. 9 - Prob. 38PCh. 9 - Prob. 39PCh. 9 - Prob. 40PCh. 9 - Prob. 41PCh. 9 - Prob. 42PCh. 9 - Prob. 43PCh. 9 - Prob. 44PCh. 9 - Prob. 45PCh. 9 - Prob. 46PCh. 9 - Prob. 47PCh. 9 - Prob. 48PCh. 9 - Prob. 49PCh. 9 - Prob. 50PCh. 9 - Prob. 51PCh. 9 - Prob. 52PCh. 9 - Prob. 53PCh. 9 - Prob. 54PCh. 9 - Prob. 55PCh. 9 - Prob. 56PCh. 9 - Prob. 57PCh. 9 - Prob. 58PCh. 9 - Prob. 59PCh. 9 - Prob. 60PCh. 9 - Prob. 61PCh. 9 - Prob. 62PCh. 9 - Prob. 63PCh. 9 - Prob. 64PCh. 9 - Prob. 65PCh. 9 - Prob. 66PCh. 9 - Prob. 67PCh. 9 - Prob. 68PCh. 9 - Prob. 69PCh. 9 - Prob. 70PCh. 9 - Prob. 71PCh. 9 - Prob. 72PCh. 9 - Prob. 73PCh. 9 - Prob. 74PCh. 9 - Prob. 75PCh. 9 - Prob. 77PCh. 9 - Prob. 78PCh. 9 - Prob. 79PCh. 9 - Prob. 80PCh. 9 - Prob. 81PCh. 9 - Prob. 83PCh. 9 - Prob. 84PCh. 9 - Prob. 85PCh. 9 - Prob. 86PCh. 9 - Prob. 87PCh. 9 - Prob. 88P
Knowledge Booster
Similar questions
- b) National Homebuilders, Inc., plans to purchase new cut-and-finish equipment. The details of the 2 alternative options are summarized in the table below. The interest rate is 10% per year. First Cost, S Annual Operating Cost, S Salvage Value, S Equipment Life (years) Consider only machine A now. Alternative A 15,000 3,500 1,000 4 Alternative B 18,000 3,100 2,000 8 a) Calculate the AW of Machine A for one life cycle. b) Calculate the AW of Machine A for LCM = 8 years (2 life cycles). c) Demonstrate the equivalence of AW over 2 life cycles and AW over one life cycle.arrow_forward12% per year. For the cash flows shown, use an annual worth comparison and an interest rate of First cost, $ Annual cost$, per year Overhaul cost every 5 years,$ Salvage value, $ Life, years X Y -100,000 -250,000 -40,000 -30,000 0 2,000 30,000 10,000 5 10 Z -500,000 -10,000 5,000 ∞ a) Determine the alternative that is economically best. b) Determine the first cost required for each of the two alternatives not selected in part a) so thatarrow_forwardThe ore of a gold mine in the province contains, on average, 0.5 ounce of gold per ton. Method A ofprocessing costs 150Php/ton and recovers 93% of the gold, while Method B costs only 120Php/tonand recovers 81% of the gold. If gold can be sold at 1,200/ounce, which method is better and by howmuch?a. Method A, by 43Phpb. Method A, by 42Phpc. Method B, by 42Phpd. Method B, by 43Phparrow_forward
- How do we compare alternatives on an equal basis and select the alternativethat is wisest from an economic standpoint?arrow_forward(a) Q1: Examine the data in the Table below and determine the lifetimecosts of this hybrid vehicle. b) As logistics manager, you’re considering the following alternativevehicle for your fleet. What are its lifetime costs in comparison withthe hybrid vehicle? c) Calculate the indifference point between the two vehicle designsand the expected age of the vehicles at this point. d) Which car should you choose if you intend to own it for longer thanthis time?arrow_forwardIn the design of a jet engine part, the designer has a choice ofspecifying either an aluminium alloy casting or a steel casting. Either materialwill provide equal service, but the aluminium casting will weigh 1.2 kg ascompared with 1.35 kg for the steel casting.The aluminium can be cast for $. 80.00 per kg. and the steel one for$ 35.00 per kg. The cost of machining per unit is $. 150.00 for aluminiumand $. 170.00 for steel. Every kilogram of excess weight is associated witha penalty of $. 1,300 due to increased fuel consumption. Cost of using aluminium metal for the jet engine part?arrow_forward
- "Four alternatives for the manufacture of construction materials, called "Barboncito"", have been identified with the following annual benefits and costs: Alternative Annual Benefits Annual Costs AP 15,000,000 P8,000,000.00 B 14,000,000 7,000,000.00 9,000,000 3,000,000.00 D 11,000,000 3,500,000.00 What is the best alternative?" "Alternative A 'Alternative D"" 'Alternative C"" "Alternative B'arrow_forwardEvaluate the two alternatives A and B and decide the economic justified alternative using: Present worth method Annual worth method Future worth method I.R.R method E.R.R Method E.R.R.R method M.A.R.R = 15% the details of alternatives are shown in the table below Alternatives A Investments $6,000 $7,500 Useful life (years) 10 Annual disbursements $2,500 $3,500 Annual revenues $4,500 $6,000 Salvage values $500 $1,000arrow_forwardDecision making in the engineering economy is concerned with choosing the best 1. Alternative with the longest life 2. Alternative with the least cost 3. Alternative with highest revenue 4. An alternative that is the most cost-effective O 1arrow_forward
- Marmara Processing Technologies Company wants to buy milling cutters in order to meet its increasing production needs. As a result of the studies, the data in the table below were found. According to these data, what will be the current cost of the annual operating expense parameter of alternative B? A Purchase Cost 10.000 12.000 Annual Operating Expense 1.500 1.700 Scrap Values 2.000 3.000 Economic Life 4 4 Capital Cost 10% 10%arrow_forwardHero expert pro Hand written solution is not allowed.arrow_forwardNational homebuilders Inc plans to purchase new rain gutter forming equipment. Two manufacturers offered the following estimates, First Cost, $ Annual Operating Cost, $/year Salvage Value, $ Life, years Vendor A 15,000 3500 1000 6 Vendor B 18,000 3100 2000 9 a. Determine which vendor should be selected on the basis of a PW comparison, if the MARR is 15% per year. b. National Homebuilders has a standard practice of evaluating all options over a 5-year period. If a study period of 5 years is used and the salvage values are not expected to change, which vendor should be selected?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Economics: Applications, Strategies an...EconomicsISBN:9781305506381Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. HarrisPublisher:Cengage Learning
Managerial Economics: Applications, Strategies an...
Economics
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:Cengage Learning