Textbook Question
Book Icon
Chapter 4, Problem 13P

Determine over-and underbillings for a company with the following information:

Job Number: 311

Job Name: Smith Remodel

Current Contract Amount: $22,530

Total Estimated Cost at Completion: $17,264

Actual Costs to Date: $16,538

Total Billed: $21,000

Job Number: 316

Job Name: Redd Remodel

Current Contract Amount: $35,624

Total Estimated Cost at Completion: $28,221

Actual Costs to Date: $22,345

Total Billed: $28,500

Job Number: 318

Job Name Winter Remodel

Current Contract Amount $17,954

Total Estimated Cost a: Completion. $14,567

Actual Costs to Date: $4,562

Total Billed: $6,000

Job Number: 322

Job Name Richardson Remodel

Current Contract Amount $3,213

Total Estimated Cost at Completion: $3,721

Actual Costs to Date: $1,956

Total Billed: $0

Blurred answer
Students have asked these similar questions
Hillcrest Publishing Co. established the following cost pools for 2018 support costs: Cost Pool Machine setup Amount $25,000 $22,000 $18,000 $16,000 Cost Driver Setup hours Number of inspections Number 900 Inspection Maintenance 400 Machine hours 9,800 200 Materials handling Number of moves The following data pertains to two jobs performed during 2018: Job #60 1,450 $11,510 $8,220 Job #70 1,060 $8,890 $6,780 Item Number of units Direct materials cost Direct labor cost Machine hours 750 610 Direct labor hours 595 475 Number of material moves 44 17 Number of setup hours Number of inspections 72 39 36 21 Determine the unit cost of Job #70 using activity based costing: $
Hillcrest Publishing Co. established the following cost pools for 2018 support costs: Cost Pool Machine setup Amount $25,000 $22,000 $18,000 $16,000 Cost Driver Setup hours Number of inspections Number 900 Inspection Maintenance 400 Machine hours 9,800 Materials handling Number of moves 200 The following data pertains to two jobs performed during 2018: Job #60 1,450 $11,510 $8,220 Job #70 1,060 $8,890 $6,780 610 Item Number of units Direct materials cost Direct labor cost Machine hours 750 Direct labor hours 595 475 Number of material moves Number of setup hours Number of inspections 44 17 72 39 36 21 (1) Determine the unit cost of Job #60 using machine hrs. to allocate all support costs: $
Determine over and underbilling's for a company with the following information: • Job Number: 311 Job Name: Smith Remodel Current Contract Amount: $22,530 o Total Estimated Cost at Completion: $17, 264 Actual Costs to Date: $16, 538 Total Billed: $21,000 • Job Number: 316 Job Name: Redd Remodel Current Contract Amount: $35, 624 o Total Estimated Cost at Completion: $28, 221 Actual Costs to Date: $22,345 Total Billed: $28, 500
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Text book image
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
What is Cost Allocation? Definition & Process; Author: FloQast;https://www.youtube.com/watch?v=hLhvvHvZ3JM;License: Standard Youtube License