Principles Of Operations Management
Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 14, Problem 16P

a)

Summary Introduction

To determine: The change in the items due to the change in the lead time of item G.

Introduction:

Net requirements plan:

The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the Scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.

a)

Expert Solution
Check Mark

Answer to Problem 16P

The change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.

Explanation of Solution

Given information:

  • 10 units for service and production department for B and F.
  • 10 units of A at week 8.
  • Lead time of G has been changed to 4 weeks.
Part A B C D E F G H
On hand 0 2 10 5 4 5 1 10

Product structure:

Principles Of Operations Management, Chapter 14, Problem 16P , additional homework tip  1

Net requirements plan:

Item A:

Week
Item A 1 2 3 4 5 6 7 8
Gross requirements 10
Scheduled receipt
On-hand (0) 0
Net requirement 10
Planned order receipt 10
Planned order release 10

Week 8:

The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.

Item B:

Week
Item B 1 2 3 4 5 6 7 8
Gross requirements 10 10
Scheduled receipt
On-hand (2) 2 0
Net requirement 8 10
Planned order receipt 8 10
Planned order release 8 10

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the planned order release will be 8 in week 5 which will be the planned order receipt in week 6.

Week 7:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the planned order release will be 10 in week 6 which will be the planned order receipt in week 7.

Item F:

Week
Item F 1 2 3 4 5 6 7 8
Gross requirements 10 10
Scheduled receipt
On-hand (5) 5 0
Net requirement 5 10
Planned order receipt 5 10
Planned order release 5 10

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.

Week 7:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.

Item D:

Week
Item D 1 2 3 4 5 6 7 8
Gross requirements 8 10
Scheduled receipt
On-hand (5) 5 0
Net requirement 3 10
Planned order receipt 3 10
Planned order release 3 10

Week 5:

The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.

Item G (Lead Time = 3):

Week
Item G 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (1) 1 0
Net requirement 4 10
Planned order receipt 4 10
Planned order release 4  10

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.

Item G (Lead Time = 4):

Week
Item G 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (1) 1 0
Net requirement 4 10
Planned order receipt 4 10
Planned order release 4 10

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.

Item H:

Week
Item H 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (10) 10 5
Net requirement 5
Planned order receipt 5
Planned order release 5

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.

Item C:

Week
Item C 1 2 3 4 5 6 7 8
Gross requirements 13 10
Scheduled receipt
On-hand (10) 10 0
Net requirement 3 10
Planned order receipt 3 10
Planned order release 3 10

Week 5:

The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.

 Item E:

Week
Item E 1 2 3 4 5 6 7 8
Gross requirements 3 15
Scheduled receipt
On-hand (4) 4 1
Net requirement 14
Planned order receipt 14
Planned order release 14

Week 4:

The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.

Week 5:

The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.

Hence, the change will take place only with item G because it has no children. The Lead time of 4 weeks will preempt the Planned order release by 1 one week.

b)

Summary Introduction

To determine: The implications of the production plan because of change in the lead time of item G.

Introduction:

Net requirements plan:

The Net requirements plan is the plan which is established on the Gross requirements plan formed by deducting the stock on and the Scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.

b)

Expert Solution
Check Mark

Answer to Problem 16P

The production plan will be altered such that item F and four units of A will be delayed by 1 week.

Explanation of Solution

Given information:

  • 10 units for service and production department for B and F.
  • 10 units of A at week 8.
  • Lead time of G has been changed to 4 weeks.
Part A B C D E F G H
On Hand 0 2 10 5 4 5 1 10

Product structure:

Principles Of Operations Management, Chapter 14, Problem 16P , additional homework tip  2

Net requirements plan:

Item A:

Week
Item A 1 2 3 4 5 6 7 8
Gross requirements 10
Scheduled receipt
On-hand (0) 0
Net requirement 10
Planned order receipt 10
Planned order release 10

Week 8:

The gross requirement is 10 (1 assembly). The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 7 which will be the Planned order receipt in week 8.

Item B:

Week
Item B 1 2 3 4 5 6 7 8
Gross requirements 10 10
Scheduled receipt
On-hand (2) 2 0
Net requirement 8 10
Planned order receipt 8 10
Planned order release 8 10

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 2. Hence, the Net requirement is 8. The lead time is 1 week. Therefore, the Planned order release will be 8 in week 5 which will be the Planned order receipt in week 6.

Week 7:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.

Item F:

Week
Item F 1 2 3 4 5 6 7 8
Gross requirements 10 10
Scheduled receipt
On-hand (5) 5 0
Net requirement 5 10
Planned order receipt 5 10
Planned order release 5 10

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.

Week 7:

The gross requirement is 10 (1 assembly) derived from the Planned order release of A. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 6 which will be the Planned order receipt in week 7.

Item D:

Week
Item D 1 2 3 4 5 6 7 8
Gross requirements 8 10
Scheduled receipt
On-hand (5) 5 0
Net requirement 3 10
Planned order receipt 3 10
Planned order release 3 10

Week 5:

The gross requirement is 8 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 5. Hence, the Net requirement is 3. The lead time is 1 week. Therefore, the Planned order release will be 3 in week 4 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of B. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 1 week. Therefore, the Planned order release will be 10 in week 5 which will be the Planned order receipt in week 6.

Item G (Lead Time = 3):

Week
Item G 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (1) 1 0
Net requirement 4 10
Planned order receipt 4 10
Planned order release 4  10

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 3 weeks. Therefore, the Planned order release will be 4 in week 2 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 3 weeks. Therefore, the Planned order release will be 10 in week 3 which will be the Planned order receipt in week 6.

Item G (Lead Time = 4):

Week
Item G 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (1) 1 0
Net requirement 4 10
Planned order receipt 4 10
Planned order release 4 10

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 1. Hence, the Net requirement is 4. The lead time is 4 weeks. Therefore, the Planned order release will be 4 in week 1 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 4 weeks. Therefore, the Planned order release will be 10 in week 2 which will be the Planned order receipt in week 6.

Item H:

Week
Item H 1 2 3 4 5 6 7 8
Gross requirements 5 10
Scheduled receipt
On-hand (10) 10 5
Net requirement 5
Planned order receipt 5
Planned order release 5

Week 5:

The gross requirement is 5 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 10. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 6.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of F. The on-hand inventory is 5. Hence, the Net requirement is 5. The lead time is 1 week. Therefore, the Planned order release will be 5 in week 5 which will be the Planned order receipt in week 6.

Item C:

Week
Item C 1 2 3 4 5 6 7 8
Gross requirements 13 10
Scheduled receipt
On-hand (10) 10 0
Net requirement 3 10
Planned order receipt 3 10
Planned order release 3 10

Week 5:

The gross requirement is 13 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 10. Hence, the Net requirement is 3. The lead time is 2 weeks. Therefore, the Planned order release will be 3 in week 3 which will be the Planned order receipt in week 5.

Week 6:

The gross requirement is 10 (1 assembly) derived from the Planned order release of B and H. The on-hand inventory is 0. Hence, the Net requirement is 10. The lead time is 2 weeks. Therefore, the Planned order release will be 10 in week 4 which will be the Planned order receipt in week 6.

 Item E:

Week
Item E 1 2 3 4 5 6 7 8
Gross requirements 3 15
Scheduled receipt
On-hand (4) 4 1
Net requirement 14
Planned order receipt 14
Planned order release 14

Week 4:

The gross requirement is 3 (1 assembly) derived from the Planned order release of D. The on-hand inventory is 4. Hence, the Net requirement is 0. Therefore, there will be no Planned order release. The excess inventory will be available in week 5.

Week 5:

The gross requirement is 15 (1 assembly) derived from the Planned order release of H. The on-hand inventory is 1. Hence, the Net requirement is 14. The lead time is 1 week. Therefore, the Planned order release will be 14 in week 4 which will be the Planned order receipt in week 5.

If this week is week 1 of the production plan, the increase in the lead time will make that only 1 assembly of G will be available for F in week 5. Hence, item F and consequently 4 units of item A will be delayed by a time of 1 week.

c)

Summary Introduction

To determine: The options the production manager has to manage these changes.

c)

Expert Solution
Check Mark

Explanation of Solution

Options the production manager has to manage these changes:

The production manager can do the following. They are:

  • The production manager can inform the customer in advance that the 4 units will be delayed by a time of 1 week.
  • The production manager can ask the supplier of item G to expedite the production or the delivery.
  • The production manager can reduce the time take for production of item F or A.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
You are working in the planning team of a food factory in Malaysia, producing Lipton. Tomorrow is the deadline for shipping deliveries to Giant supermarkets ready for a new Lipton promotion. The promotion has featured an extensive social media campaign to drive sales. You have just been informed that the delivery of raw materials has broken down. There is a risk that the tight manufacturing schedule will not be feasible in the time remaining. So in this case, 1. What is the potential impact on the retailer and consumer of failing to meet the delivery schedule? 2. What steps could you take to solve this problem? 3. Who dod you need to keep informed? 4. What method of communication would you choose for each?
You’re working in the planning team of a foods factory in Malaysia, producing Magnum. The deadline for shipping deliveries to Giant Supermarkets ready for a new Magnum promotion is in four weeks. The promotion has featured an extensive social media campaign to drive sales. You’ve just been informed that the delivery of raw materials has broken down. There is a risk that the tight manufacturing schedule will not be feasible in the time remaining. What is the potential impact on the retailer, consumer and our brand of failing to meet the delivery schedule? What steps could you take to solve this problem? Who do you need to keep informed, and what method of communication would you choose for each? What steps would you take to prevent this situation from happening again? What data/insights would you gather to support with this?
Discuss how is CVP analysis used to calculate the break even point for multiple products?

Chapter 14 Solutions

Principles Of Operations Management

Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1CSCh. 14 - Prob. 2CSCh. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - Prob. 2.1VCCh. 14 - Prob. 2.2VCCh. 14 - Prob. 2.3VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY