What is the shortest path and what is the shortest possible time to travel from A to Z? (Round yo number.) Shortest path Shortest duration
Q: A project consisting of eight activities satisfies the following precedence constraints: a.…
A:
Q: A network consists of the activities in the following list. Times are given in weeks. Activity…
A: ESActivityEFLSTimeLFES=maximum (EF of all immediate predecessor)EF=ES+durationLF=minimum (LS of all…
Q: a. Construct an arrow diagram for this problem b. Determine the critical path and compute the…
A: ANSWER IS AS BELOW:
Q: d) If the time to complete path A-C is normally distributed, what is the probability that this path…
A: Probability of competing a path indicating the proportion between the difference in line duration…
Q: 2- Find the completion time (TE).
A: TE stands for the expected duration. It means the expected time duration that each activity will…
Q: D) Using the precedence table given, construct the precedence matrix and draw an activity-on-node…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: activity predecessor optimistic time(days) Most likely time(days) Pessimistic time(days) A - 4 8 24…
A: Find the Given details below: Activity Predecessors Optimistic Time(To) a(Days) Pessimistic…
Q: Any solution to critical section problem must satisfy all the following except: A. Progress B.…
A: Process synchronization is an activity of coordinating and executing the processes in a way that no…
Q: a) Prepare a PERT network diagram to aid the coordination of the activities. Calculation of…
A: a.PERT DIAGRAM:
Q: Duration 49 52 75 63 94 56 57 What is the shortest path and what is the shortest possible time to…
A: Below is the solution:-
Q: Identify critical path and total time (i.c. number of hours) required to complete the path). Find…
A: A network diagram representing a project in visual model using arrows and nodes. A critical path is…
Q: d. How long the program is expected to finish? e. Determine the slack time for each activity using…
A: given,
Q: A Project has been defined to contain the following list of activities along with their required…
A: a) The network diagram based on the given information is as follows: Note: EF = Early Finish Time…
Q: SESSION 2: Tutorial Homework Activity Duration Additional Information (days) The project starts with…
A: 1. Activity Immediate Predecessors Duration A - 5 B A 3 C - 1 D…
Q: Project ALPHA has 6 Acivities from A to F as follows: Activity Duration Preceded By A 3 A A F The…
A: The question is to find a number of the critical paths. In the project of the executives, the…
Q: The total cost required for completing this project on normal time = $ %3D
A: THE ANSWER IS AS BELOW:
Q: 2IA Five tasks to be completed in three places A, B and C and the work sequence is A and then C, B…
A: Find solution of Processing 3 Jobs Through 5 Machines Problem Job A B C Machine-1 4…
Q: Statement for both assignment One and Two Kwazulu –Natal, a coastal South African province, is known…
A: Target marketing focuses on defined group of people who are likely the most profitable customers of…
Q: Schedules and activities of some projects are shown below Draw the network diagram Activity…
A: I will be drawing the network diagrams for the 2 projects. Please post it again for other projects'…
Q: Table 7.8 contains data for the installation of new equipment in a manufacturing process at Excello…
A:
Q: 5. For the following problem, draw a network Activity A B C D E F G H IJ Immediate B А,В A,B B D,E,F…
A: Activity Immediate Predecessors A - B - C B D A,B E A,B F B G D,E,F H D,E I E,F…
Q: Activity Q on a project has exactly 4 successors E, F, G, and H whose late start days are 20, 12,…
A: Below is the solution:-
Q: Sushant and his team of frenco Ltd. Want to ascertain the expected time and variance for an Activity…
A: Given : Optimistic Time (a) - 2 weeks Pessimistic time (b) - 8 weeks Most likely time (m) - 3 weeks…
Q: (d) Suppose you want to shorten the completion time as much as possible and you have the option of…
A: Activity Activity time Immediate Predecessor(s) A 4 - B 2 A C 4 A D 3 C E 5 B,D F 6 D…
Q: a) Identify each path and path duration b) Identifying due time of the critical path c) Compute for…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Example - Draw Activity on Node Diagram Activity Predecessor Duration A B A 3 B E F G C,F 5 H G 4 G…
A: Activity Immediate Predecessors Duration A - 5 B A 3 C B 4 D - 5 E D 7 F E 2 G C,F 5…
Q: Construct a CPM network based on activity on node method with the details given below and find the…
A: Given information, Activity Immediate Predecessor Duration A 1 B A 4 C A 2 D A 2 E…
Q: What is the definition of a assignment matrix in project management?
A: A Responsibility Assignment Matrix establishes the extent to which numerous organisations, persons,…
Q: cts to implement in project man
A: To be a good project manager, one must have a wide range of abilities. It requires a variety of…
Q: Noted that a facility used by activity C and D is scarce and limited. Based on that statement, to…
A: As per guidelines, we are only allowed to do first three sub-parts at a time. Please post rest parts…
Q: snip
A: PERT assumes that path lengths through a network can be modeled with Normal distribution.
Q: Develop a project network for this problem. b. Determine the ES, EF, LS, LF, and slack time for…
A: The critical path tells the shortest possible duration to complete the project. Slack tells the time…
Q: When crashing a project, the general guideline is to concentrate on the path with? a. The least…
A: A project crashing is the process of reducing the total duration of the project completion based on…
Q: Identify the term being described for each of the following: b. The longest time sequence of…
A: b. The critical path is the longest time sequence of activities in a project.
Q: What is the shortest path and what is the shortest possible time to travel from A to Z? (Round your…
A: A network diagram is the graphical representation of activities with their duration to complete the…
Q: Please help me answer parts 3. and 4. of this question if not all of them. Thank you
A: Forward Pass:Early Start = Maximum (or Highest) EF value from immediate Predecessor(s)Early Finish =…
Q: Week 9-10 ACTIVITY Directions Read and analyze the case below. Identify and discuss the reasons…
A: The skills and experience of individual C helped him in starting his own business venture. He had a…
Q: partment Transportati project section of interstate highway near Wahington, DC. The project includes…
A: Project scheduling with uncertain activity times (Optimistic, Most likely, Pessimistic) a - 1 2 2…
Q: (b) Identify all of the paths on the network diagram and note how long they are, using Figure 6- 8…
A:
Q: Project ALPHA has 6 activities from A to F as follows: Activity Duration Preceded By A A A B E F E…
A: Answer: A as A is the merged activity of the correct network diagram.
Q: Students are sometimes confused by the concept of critical path, and want to believe that it is the…
A: The critical path method is a project management tool. Critical Path forms the most extended…
Q: What is the least expensive method of halting some tasks in order to keep the project's (estimated)…
A: Project crashing would be a method in which fit indices are utilized to reduce the time of a project…
Q: Slack time for each of the activities is? (Activity A-G)
A: Find the given details below: Given Details: Activity Immediate Predecessor(s) Time (days) A…
Q: . Determine the optimal sequence. b. Determine the completion time.
A: The sequence is defined as an order to move the operation with a fixed procedure. It defines the…
Q: snip
A: PERT stands for Program Evaluation and Review Technique. It is a strategy used to look at the…
Q: What would a project manager have to do to crash an activity?
A: Project crashing is the point at which you abbreviate the term of a venture by diminishing the hour…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- The shortest-route technique wouldbest be used to: plan the routes for avacation driving tour.plan the route for a school bus.determine the path for a truck making frequent runsfrom a factory to a warehouse.All of the aboveNone of the aboveRoss Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Activity a m b Immediate Predecessor(s) Activity a m b Immediate Predecessor(s)A 6 8 12 - G 2 3 4 C, EB 1 9 24 A H 2 2 2 FC 8 14 16 A I 7 7 7 FD 4 7 10 A J 6 7 12 D, G, HE 1 2 4 B K 1 1 4 I, JF 6 9 20 C, E a) The expected (estimated) time for activity C is 13.33weeks. (Round your response to two decimal places.) b) The variance for activity C is 1.78weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is A - C - F - H - J - K . d) The estimated time for the critical path is [ ? ] enter your response here weeks. (Round your response to two…The shortest-route technique would best be used to a.plan the route for a school bus. b.determine the path for a truck making frequent runs from a factory to a warehouse. c.plan the routes for a vacation driving tour. d.none of the answers presented apply. e.all of the answers presented apply.
- . New York Building Corporation uses the critical path method to monitor construction jobs. The company is currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty. Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal completion time of 22 weeks. The following activities can be crashed. Activities Cost to Crash 1 Week Cost to Crash 2 Weeks BC P 8,000 P15,000 DE 10,000 19,600 EF 8,800 19,500 REQUIRED: New York Building desires to reduce the normal completion time Job #181 and, at the same time, report…A commercial company has a main branch located in Beirut with around 35 employees. The company is looking to expand its activities by opening 3 new branches in Lebanon. To facilitate information and data sharing, the company decided to implement a network in each branch, then to connect all the branches into a single network. Also, the new network will be based on giving employees the facility to use their laptops and smartphones in most of their operations. On the other hand, the company has a major problem with organizing its data. The human resource, finance, sales, and customer service departments have all developed separately their own systems and data files, which created a lot of redundancy and poor security. Managers can't have access to timely, accurate, or relevant information for analysis because the data have been poorly organized and maintained in separated files. The main concern for the company, regarding this problem, is to discover new and hidden patterns of customers'…Good day. Can you please assist on the following question below Lorraine has received a lump sum of R500 000.00 from her retirement fund. She intends to use these funds to start a student accommodation business. In order to start this business, Lorraine would need approximately R1 million, funds are needed for building the students accommodationapartments and to register with various regulatory bodies. She has to source additional funding in order to realise this dream. In the business plan, Lorraine has outlined the following:• Accommodation will be offered ONLY to students in Cape Town, Johannesburg, Mpumalanga and Polokwane.• ONLY females will be approved to reside in these houses, between the age of 18 - 35.• Marketing of the business will be done on community Radio stations only at the four mentioned cities.• It is going to be a family business, Friends and relatives are in support of the idea but are not able to support the business financially. Q.1. Discuss ANY TWO labour…
- Good day. Can you please assist on the following question below Lorraine has received a lump sum of R500 000.00 from her retirement fund. She intends to use these funds to start a student accommodation business. In order to start this business, Lorraine would need approximately R1 million, funds are needed for building the students accommodationapartments and to register with various regulatory bodies. She has to source additional funding in order to realise this dream. In the business plan, Lorraine has outlined the following:• Accommodation will be offered ONLY to students in Cape Town, Johannesburg, Mpumalanga and Polokwane.• ONLY females will be approved to reside in these houses, between the age of 18 - 35.• Marketing of the business will be done on community Radio stations only at the four mentioned cities.• It is going to be a family business, Friends and relatives are in support of the idea but are not able to support the business financially. Q.1. Discuss ANY TWO labour…Good day. Can you please assist on the following question below Lorraine has received a lump sum of R500 000.00 from her retirement fund. She intends to use these funds to start a student accommodation business. In order to start this business, Lorraine would need approximately R1 million, funds are needed for building the students accommodationapartments and to register with various regulatory bodies. She has to source additional funding in order to realise this dream. In the business plan, Lorraine has outlined the following:• Accommodation will be offered ONLY to students in Cape Town, Johannesburg, Mpumalanga and Polokwane.• ONLY females will be approved to reside in these houses, between the age of 18 - 35.• Marketing of the business will be done on community Radio stations only at the four mentioned cities.• It is going to be a family business, Friends and relatives are in support of the idea but are not able to support the business financially. Q.4.1 Identify the TWO basis or…Travelling Salesman Problem (TSP); Given the following distance matrix, use the nearest neighbor (NN) heuristic to find a route that starts from the warehouse (W), visits each customer only once, and finishes at the warehouse to minimize the distance traveled. What is the route and the corresponding distance? Distances W 1 2 3 4 in miles 18 57 27 50 18 0 65 29 61 57 65 0 36 99 3 27 29 36 0 76 4 50 61 99 76 Route=W-1-3-2-4, Distance=182 miles Route=W-3-1-2-4-W, Distance=270 miles Route = W-3-1-2-4, Distance=220 miles Route=W-1-3-2-4-W, Distance=232 miles Route=W-1-3-4-2, Distance=272 miles 1, 2.
- Required information The Childfair Company has three plants producing child push chairs that are to be shipped to four distribution centers. Plants 1, 2, and 3 produce 12, 17, and 11 shipments per month, respec- tively. Each distribution center heeds to receive 10 shipments per month. The distance from each plant to the respective distributing centers is given below: Distance Plant 1 2 3 1 1450 1750 1250 Distribution Center 3 1050 1250 1450 Obtain an optimal solution, and determine the total cost. Total Cost = $ 2 1950 2050 1850 The freight cost for each shipment is $100 plus 50 cents per mile. 4 1350 1650 1550By Monday April 16th the following towns will need the numbers of coal cars listed: coal valley 30 Coaltown 45 Coal Junction 25 Coalsburg 20 Using a railway city to city distance chart, the dispatcher constructs a mileage table on this page. Minimizing total miles over which cars are moved to new locations, compute the best shipment of coal cars.RBL’s directors are looking to expand into a new suite of services. Although they are doing quite well in their existing lines of business, analysts have identified some new areas for development. One of these is expansion into manufacturing prefabricated homes. However, this venture requires a large amount of funding. To raise additional funds to finance this new project, the company is considering issuing a new bond.Required: Prepare a short report which supports the case for issuing a corporate bond. In your report:a.Explain what a corporate bond is,b.Outline the characteristics of the bond market,c. Explain the benefits of issuing bonds to raise financing.