d. How long the program is expected to finish? e. Determine the slack time for each activity using either LS & ES or LF and EF. f. What is the probability of finishing in 75 days
Q: Draw an Activity on Arrow 2. Show all paths
A: A network diagram indicating a visual representation of a project which specifying the activities…
Q: What are hammock activities and when should they be used
A: A hammock activity can be defined as a schedule or project planning term for a gathering of…
Q: Explain the risks associated with leveling resources, compressing or crashing projects, and imposed…
A: Leveling resources indicates that in cases where demand changes greatly over the project's life…
Q: 1- ES for Activity C, E, G. J 2- E.F for Activity B. H 3- L.S for Activity A. J
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: The project manager serves as an expert on the theory and application of statistical techniques.…
A: A project manager is a management head who carries out the work of planning and implementation of…
Q: What project scheduling tool expands and contracts to share the right information to the right…
A: Schedule Variance An Schedule Variance denotes how much ahead or behind schedule a project is. By…
Q: Duration of Dummy activity is always constant IS Select one: O True O False
A: Dummy activity does not consume time and resource. Duration of dummy activity is not always…
Q: To obtain reasonable assurance about the completion of the project within the timeline, the best…
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: Activity time: 20 minutes Instruction to the student: The students have to discuss and write at…
A: We can say that here are 5 creative products and their innovative features 1. Skylock – We can say…
Q: Ann decided to hired Dionne Richards to be her assistant given the exigencies of this particular…
A: Given: identified resources=10 Kimberley Sharpe who would continue the set of activities started by…
Q: Why is it important for project managers to resist changes to the project baseline? Under what…
A: Project baseline is the timeline of the project that is scheduled and agreed by stakeholders of the…
Q: A, B, and C, activities are the immediate predecessors for Y activity. If the earliest finish times…
A: THE ANSWER IS AS BELOW:
Q: You are managing a project where you work with 7 other team members and two sponsors. How many lines…
A: This is a simple application of the lines of communication formula: # lines = n x (n - 1) / 2. Don’t…
Q: Briefly describe 'Parkinson's Law' and 'Murphy's Law'. One sentence each. Then briefly in 3-6…
A: A project plan is the series of tasks that are supposed to control the project execution and…
Q: 11-27 General Foundry’s project crashing data are shown in Table 11.9. Crash this project to 13…
A: Given data is
Q: (a) With the use of a diagram, show (illustrate) the typical levels of uncertainty or project risks…
A: A Small Introduction about Project Life Cycle The undertaking life cycle incorporates the means…
Q: 1. What is the earliest time that activity 1 will be finished? A) Week 15 B) Week 10 c) Week 1 D)…
A: Below is the solution:-
Q: Computer and photocopying paper, brochures, envelopes, cleaning materials, lubricants are called as:…
A: Consumables are products utilized by people and organizations that should be supplanted routinely in…
Q: Identify the order in which a Project manager does his job a. Planning, Organizing,…
A: A project manager is the responsible person for the whole project and is the person who makes proper…
Q: 1.Estimating the type and quantities of resources required to perform each schedule activity…
A: “Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: Find the total cost associated with the project as Data is given in Table 1)
A: Given that: Activity Expected Time Standard deviation Cost A 3 0.3 $2,000 B 2 0.5 $3,000…
Q: What is the definition of the latest completion time (LCT) of a project activity?a. LCT(Ai) =…
A: The latest completion time is referred to as the possible completion time of any activity such that…
Q: Evaluate the below statement according to the estimation of activity duration tools, write the…
A: 1) Makes use of group intelligence to determine the activity duration, scaling up or down the…
Q: Activity times with the greatest uncertainty are activities D, E, and H. Describe conceptually how…
A: Activity times with the greatest level of uncertainties are D,E and H. This could be modeled in…
Q: Activity time estimates for a production line design & implementation project at the CBA factory are…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: Under what conditions would the top-down approach to estimating project times and costs be the best…
A: For any company, strategy plays a crucial role and strategic decision-making is defined as the…
Q: here are four project baselines. Scope baseline Schedule baseline Cost baseline Performance…
A: A baseline in project management is a project starting plan and it acts as a project reference point…
Q: 1. Organize the information above in an activity precedence table. 2. Draw an Activity-On-Arrow…
A: Below is the solution:-
Q: of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=9. A. the critical…
A: 1) Correct answer is (B) Critical Path = D-E-F duration 16 2) Correct answer is (D) A firm produces…
Q: Issues in project management include a. level of effort. b. period of performance. c.…
A: Budgeting issues Most managers think about monetary issues as probably the greatest obstacle in…
Q: You are in charge of a project at the local community center. The center needs to remodel one of the…
A: For the first part, let us calculate the early finish and early start time for each of the…
Q: You are managing a software project with an initial budget estimate of 5 million USD. During interim…
A:
Q: On the job, the telephone numbers of doctors, hospitals, and ambulances must be: a. conspicuously…
A: Amassing data and info on job-related accidents, ailments, or damages, can assist in decreasing the…
Q: Explain the difference between a project that has a fixed delivery day and one that has a fixed…
A: A project (or program) is any endeavor, done independently or cooperatively and possibly including…
Q: The WBS is a. a Gantt chart. b. a chart showing the hierarchical listing of all the tasks…
A: A work breakdown structure (WBS) is a visual, hierarchical and deliverable-arranged deconstruction…
Q: Kelly Melford and her team are working on redesigning a client's home. The client requested Kelly…
A:
Q: Explain the difference between a project that has a fixed delivery day and one that has a fixed…
A: Fixed delivery date Fixed limit on resource usage It can be vary from the resource level which is…
Q: If Activity C has an expected time estimate of 8 days, which of the following statements is TRUE? *…
A: The formula for expected time can be given as:- TE = (O + 4T + P) 6
Q: A potential conflict on projects is work scope; conflict can arise from differences of opinion on…
A: Project management is the management in which different types of knowledge and skills are required…
Q: What is the latest that activity B can start if A lasts 35 days, B lasts 5, days C lasts 6 days, and…
A: Given data is
Q: You are working as a project manager. Your Company wants to develop a project. You are also involved…
A: Project management is broadly defined as the process of planning and successful execution of…
Q: In Risk Management Plan, when a new risk is identified, as a Project Manager, you should: a. Bypass…
A: Risk refers to a degree of uncertainty or potential for loss that might appear in the course of…
Q: A. If activity B were delayed by 2 days, how long can activity G be delayed without delaying the…
A: Given data is
Q: An organization plans to have a manufacturing unit after eight years and two new offices after nine…
A: The process of determining a company's purpose for existence, setting goals aimed at achieving…
Q: Given an activity's optimistic, most likely, and pessimistic time estimates of 6,7 and 14 days…
A: Energetic movement – The performing of an assignment, recorded when taken to do as such and the…
Q: Mr. Ali being an enthusiast player wants to remain in good relation with his employer, Mr. Mohamed.…
A: 1. No, Mr. Ali's action is not acceptable within an organization's climate as an employee should…
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
Step by step
Solved in 6 steps with 5 images
- Cousins Jeri Lynn DeBose, Tish Hoover, and Josephine (Joey) Parks looked forward to meeting up during the Christmas holidays to compare notes on the results of midyear teacher evaluations. All were public school teachers in districts scattered over the state. In the pressured search for new levels of teacher accountability demanded by legislators, the state department of education joined 16 other States in implementing a new teacher evaluation system. The goal is to hold teachers account-able for student learning progress in the classroom. Under the guidance of the National Council for Teacher Quality, criteria varies by State, but in most cases, 40 percent of each teacher's accountability score would be based on the principal's evaluation and ranking based on personal observation, 30 percent would be based on personal observation by a master teacher from outside the district, and the Other 30 percent would be based on student test score gains. The state department of education would set a performance goal each school district, and the principal would set a performance goal for each teacher. In preparation, the State conducted intensive training sessions for principals and designated master teachers who would conduct the evaluations based on four class observations per teacher. Officials used standardized achievement tests to derive value-added scores that measure student learning over the year. Teacher ratings were 1-5, with I am being the lowest and 5 representing near perfection. The publication of the first year's evaluations stirred interest and controversy, particularly among teachers who worried about the possible long-term effects on job retention and tenure. Now, with the first-year evaluations in hand, the three cousins pored over their experiences. The three represented different types of school systems within the state. Jeri Lynn worked for a metropolitan system in the state capital. The system included many low-income students whose first language was nor English, and several schools within the system were teetering on the brink of State takeover if improvement in student scores didn't materialize this school year. Tish worked in a county System dominated by upper-income residents, and Joey taught in the rural community in which all three grew up. The rural community had high unemployment, and a low percentage of graduates went on to college. As a result, the cousins came to the table with differing teaching experiences. "The numbers are all over the place," Jeri Lynn remarked as she studied the pages. "The whole system is flawed, and they need to make changes," Joey said. " It's too subjective. The principal and master teacher observations are subjective because there are personal factors that affect a true outcome." "Yeah, look at the numbers from your upper-income district," Jeri Lynn said to Tish. " How can 60 percent of the teachers score 5s?" Tish chuckled. "Yeah, lucky us. Our schools are overflowing with children from wealthy families. These are the kids who will apply to Ivy League schools. I can tell you that the principals are going to avoid confrontation on all fronts. No principal is going to give any indication that their students are receiving an education that's less than perfect, and that means cramming the rankings with 5s. They claim a higher level of motivation for students, and thus the selection of an elite team of educators. So with those pressures, I don't think we get personal feedback that IS accurate." "At the other end of the spectrum, we have my rural district," Joey said. "The big problem is that the principals know everyone and have longstanding relationships with everyone in the county, so I think scores are based on personal history. We could almost predict who would get high or low scores before the observations. For principals, it can go back as far as 'his daddy and my daddy hated each other in high school, and now I get to evaluate his daughter." "I think that in many cases, principals feel pressure to align scores with state expectations. The stare expected my district to have high scores and expected rural schools such as yours to be lower," Tish said. "But isn't that partially offset by lower goals for the rural school distracts responded Joey. "The key to the accountability system is the principal in each school," Jeri Lynn suggested. "With several of the schools in Metro teetering on the edge of state takeover by the end of the year, we had lots of strict principals who wanted to hold our feet to the fire with lower scores." "I thought the whole idea was to provide the teachers With feedback so that we would know the areas where we need improvement," Tish said. "The principals were supposed to conduct two observations in the fall and two more in the spring," Jeri Lynn said. think that's asking too much of them when they already have so much on their plates. I think a lot of them are skimping on their visits. know I only had one observation last semester, and I'm sure Mr. Talley just faked the second set of numbers. The master teachers make only two observations a year, which may be more objective but counts for less." "I'm wondering, too, how a principal measure performance in a course area outside his area of expertise, such as math," Joey said. "If the guy has a phobia about math, anything the teacher says or does is going to 100k brilliant—thus a 5." Tish and Jeri Lynn looked at each other and laughed. Maybe we picked the wrong subjects," Tish said. "My question is one of perception," Jeri Lynn said. "A large percentage of my students are ELL. That affects their scores. How do you measure a 3 in my situation against a 5 for Tish? At the end of the school year, little Carlos is thrilled that his reading in English has improved, but there's no Big Bang here. a slow steady improvement that may not actually show up in big strides for a couple of years." "So, the question is how do they create a system that is fair?" Tish asked. "And accurate," added Jeri Lynn. Is a 1-5 grading System by principals and master teachers a valuable part of a feedback control system for teachers? Why?Cousins Jeri Lynn DeBose, Tish Hoover, and Josephine (Joey) Parks looked forward to meeting up during the Christmas holidays to compare notes on the results of midyear teacher evaluations. All were public school teachers in districts scattered over the state. In the pressured search for new levels of teacher accountability demanded by legislators, the state department of education joined 16 other States in implementing a new teacher evaluation system. The goal is to hold teachers account-able for student learning progress in the classroom. Under the guidance of the National Council for Teacher Quality, criteria varies by State, but in most cases, 40 percent of each teacher's accountability score would be based on the principal's evaluation and ranking based on personal observation, 30 percent would be based on personal observation by a master teacher from outside the district, and the Other 30 percent would be based on student test score gains. The state department of education would set a performance goal each school district, and the principal would set a performance goal for each teacher. In preparation, the State conducted intensive training sessions for principals and designated master teachers who would conduct the evaluations based on four class observations per teacher. Officials used standardized achievement tests to derive value-added scores that measure student learning over the year. Teacher ratings were I —5, with I am being the lowest and 5 representing near perfection. The publication of the first year's evaluations stirred interest and controversy, particularly among teachers who worried about the possible long-term effects on job retention and tenure. Now, with the first-year evaluations in hand, the three cousins pored over their experiences. The three represented different types of school systems within the state. Jeri Lynn worked for a metropolitan system in the state capital. The system included many low-income students whose first language was nor English, and several schools within the system were teetering on the brink of State takeover if improvement in student scores didn't materialize this school year. Tish worked in a county System dominated by upper-income residents, and Joey taught in the rural community in which all three grew up. The rural community had high unemployment, and a low percentage of graduates went on to college. As a result, the cousins came to the table with differing teaching experiences. "The numbers are all over the place," Jeri Lynn remarked as she studied the pages. "The whole system is flawed, and they need to make changes," Joey said. " It's too subjective. The principal and master teacher observations are subjective because there are personal factors that affect a true outcome." "Yeah, look at the numbers from your upper-income district," Jeri Lynn said to Tish. "How can 60 percent of the teachers score 5s?" Tish chuckled. "Yeah, lucky us. Our schools are overflowing with children from wealthy families. These are the kids who will apply to Ivy League schools. I can tell you that the principals are going to avoid confrontation on all fronts. No principal is going to give any indication that their students are receiving an education that's less than perfect, and that means cramming the rankings with 5s. They claim a higher level of motivation for students, and thus the selection of an elite team of educators. So with those pressures, I don't think we get personal feedback that IS accurate." "At the other end of the spectrum, we have my rural district," Joey said. "The big problem is that the principals know everyone and have longstanding relationships with everyone in the county, so I think scores are based on personal history. We could almost predict who would get high or low scores before the observations. For principals, it can go back as far as his daddy and my daddy hated each other in high school, and now I get to evaluate his daughter "I think that in many cases, principals feel pressure to align scores with state expectations. The stare expected my district to have high scores and expected rural schools such as yours to be lower," Tish said. "But isn't that partially offset by lower goals for the rural school distracts responded Joey. "The key to the accountability system is the principal in each school," Jeri Lynn suggested. "With several of the schools in Metro teetering on the edge of state takeover by the end of the year, we had lots of strict principals who wanted to hold our feet to the fire with lower scores." "l thought the whole idea was to provide the teachers With feedback so that we would know the areas where we need improvement," Tish said. "The principals were supposed to conduct two observations in the fall and two more in the spring," Jeri Lynn said. think that's asking too much of them when they already have so much on their plates. I think a lot of them are skimping on their visits. know I only had one observation last semester, and I'm sure Mr. Talley just faked the second set of numbers. The master teachers make only two observations a year, which may be more objective but counts for less." "I'm wondering, too, how a principal measure performance in a course area outside his area of expertise, such as math," Joey said. "If the guy has a phobia about math, anything the teacher says or does is going to 100k brilliant—thus a 5." Tish and Jeri Lynn looked at each other and laughed. Maybe we picked the wrong subjects," Tish said. "My question is one of perception," Jeri Lynn said. "A large percentage of my students are ELL. That affects their scores. How do you measure a 3 in my situation against a 5 for Tish? At the end of the school year, little Carlos is thrilled that his reading in English has improved, but there's no Big Bang here. a slow steady improvement that may not actually show up in big strides for a couple of years: "So, the question is how do they create a system that is fair?" Tish asked. "And accurate," added Jeri Lynn. What do you see as the major strengths and flaws in the feedback control system used in the schools in this scenario? What changes do you recommend to overcome the flaws?The HRM (Human Resource Management) Department of an organization administers a behavioralprofile test to measure the capabilities of individuals under consideration for employment. The testresults were analyzed manually by experts appropriate for the positions to be filled. Results aredivided into three categories: candidate style, candidate values and candidate thought preferences.Due to the large number of applicants, the many locations of the company and the high level ofexpertise required for the analysis, it was very difficult to execute a quality analysis in a timelymanner. To overcome these problems an expert system was developed which includes elevenknowledge bases.The basic objective of the system is to assess the candidate’s directional initiative, potentialperformance problems, and supervision effectiveness. Analysis of an average applicant, which takesan hour when it is done manually, can be performed in about five minutes when supported by anexpert system. The system is…
- Identify the problem of the caseState the objectivesSWOT AnalysisConclusion/RecommendationAdditional questions:1. How should an employee behave if he/she is a holder of confidential information?2. Why should a company protect trade secrets and proprietary information?3. Bibi is the manager of Arts beauty salon. One day it was suggested to her by the supervisor that she should implement a performance appraisal in the business. In Order to do so she started to do some research, but she needs more information. You are therefore required to provide Bibi with the Following information. Create a sample form for her to use.Suppose that in a telecommunications company, the manager wants to do a study to determine which customers are potential to receive a 30% discount on a new product. Name one quantitative variable and one qualitative variable that you would use to conduct this study. a. Existing client (qualitative) and Profession (quantitative) b. SSN (quantitative) and Existing Client (qualitative) c. Date of Birth (quantitative) and SSN (qualitative) d. Annual Income (quantitative) Profession (qualitative)
- E FA/IBM536/FEB2022 O Final Assessment Test Declaratic x • Download file | iLovePDF o docs.google.com/forms/d/e/1FA/PQLSCUK7M_XQAbSDhnv-0qsBCBvKgmkwb0Q1I13Vx4wkihZP6TOA/formResponse French and German managers tend to use work-centered and approach to leadership. * Authoritarian Autocratic Paternalistic Participative None of the above Which of the following statements about third-country nationals are false? * ntdoox 6 Final Assessment.docx a Final Assessment_..pdf a Final Assessment...pdf O Final Assessment.docx3. you are working as an HR manager in a reputed company, as a part of salary developmentprocedure of the employees, management asked you to develop a salary survey questionnaire which can besupportive to do their task successfully. You are required to identify and discuss the various aspects of datato be collected in salary survey and develop an effective salary survey questionnaire based on the samedetail. (Note: The questionnaire should include Minimum 10 and Maximum 20 items which is related tovarious aspects of employees’ compensation.). Prepare a scatter diagram for each of these data sets and then express in words the apparent relationship between the two variables. Put the first variable on the horizontal axis and the secondvariable on the vertical axis.a. Age 24 30 22 25 33 27 36 58 37 47 54 28 42 55Absenteeism rate 6 5 7 6 4 5 4 1 3 2 2 5 3 1
- 17-6 Hiring The HR department is trying to fill a vacant position for a job with a small talent pool. Valid applications arrive every week or so, and the appicants all seem to bring differnt levels of expertise. For each applicant, the HR manager gathers information by trying to verify various claims on resumes, but some doubt about fit always lingers when a decisions to hire or not is to be made. What are the type I and II decision error cost? Which decision error is more likely to be discovered by the CEO? How does this affect the HR manager's hiring decisions?Cick on The x C blever | Portal Freckle Student Dashboard Dashboard 6 BigBlueButton Independern x udent.freckled Clever | Portal clever.com Probability -1r You can earn'S coins Eunice selected a random sample of Seattle residents and polled them about traffic solutions. Which population could Eunice draw conclusions about? A) entire Seattle population B) Seattle homeowners C) Seattle residents who own a car D) Seattle residents who take the bus A B Submit rch9 A survey can provide insight about why a certain demographic makes a particular decision. True False