The manufacturing cycle efficiency for NUBD Company when the processing time is nine hours and inspection, waiting, and move time are one hour each is: (round-off to 2 decimal places)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question

The manufacturing cycle efficiency for NUBD Company when the processing time is nine hours and inspection, waiting, and move time are one hour each is: (round-off to 2 decimal places)