Required: (i) (ii) (iii) Draw a network and identify the critical path. What are the normal project duration and associated cost? Find out total float for each activity.
Q: Explore the ethical considerations and decision-making processes involved in prioritizing recovery…
A: In times of crisis, organizations must prioritize their recovery efforts to minimize disruption,…
Q: What is the significance of a stakeholder analysis matrix in identifying and prioritizing project…
A: A stakeholder analysis matrix is a strategic tool in project management that is used to identify,…
Q: Level II should be changed to General Field Administration, Earthwork, Concrete Work, Masonry Work,…
A: WBS is the work breakdown structure which is used to breakdown the process into different parts or…
Q: You are creating a customer database for the Hillsboro Hops minor league baseball team. Given the…
A: Critical path method is project management tool (others e.g WBS, PERT). It uses flow chart of…
Q: One product line at Spearman Fishing Industries has 19 turns per year and an annual sales volume (at…
A: The average inventory is the typical quantity of items or products held in stock by a business…
Q: Three point estimates and bottom up estimating are used in developing: (select one correct answer)…
A: Planning and project cost estimation are crucial components of project management. They entail…
Q: Assume you are the manager in an organisation, discuss the purpose of planning for newly recruited…
A: Management is an integral part of an organization. It helps in coordinating the efforts of various…
Q: A frolic is a small scale deviation from normal business practices and an employer typica…
A: The terms "detour" and "frolic" are crucial in employment law. Employers ought to be aware of these…
Q: 1. What is the value proposition for Paramount+ service? Focus on offerings for customers in the…
A: A value proposition is a brief statement that describes the distinct benefits and advantages that a…
Q: What are some important domestic demographic changes currently affecting HRM? How does HRM…
A: Human resource management is crucial for an organization because it includes managing the workforce…
Q: A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the…
A: Total time available = 400 minsOutput units = 200
Q: Transportation Problem (Solve using excel): Acme Block Company has orders for 80 tons of…
A: A specific kind of linear programming problem is the "linear programming transportation problem,"…
Q: BION Food, A food company wants to produce brownies, bread and martabak dough to sell to other…
A: For this question, I will formulate the LP, Then, I will prepare the spreadsheet model, This model…
Q: A discount store is experiencing an unacceptable number of dissatisfied customers leaving from the…
A: A Pareto chart is a type of chart that contains both bars and a line graph, where individual values…
Q: Week 1 LC% 2 3 4 5 6 30% 60% 70% 80% 90% 100% A new equipment was installed, and we estimate this…
A: Learning new skills and acquiring knowledge enhances individual as well as organizational…
Q: What is the total slack on D? What is the total slack on E? What is the FREE slack on B? What is the…
A: To find the start and end dates of each work in a project, as well as the total project time,…
Q: North Dakota Electric Company estimates its demand trend line (in millions of kilowatt hours) to be:…
A: The concept used here is forecasting using linear trends and seasonal relatives.
Q: Lillian Fok is president of Lakefront Manufacturing, a producer of bicycle tires. Fok makes 1,200…
A: Find the Given details below:
Q: Draw a decision tree and solve it
A:
Q: Brew Master Part Metal frame Plug / cord Coffee pot Brew Mini Part Plastic frame Plug / cord Coffee…
A: Production management is the concept of operations management wherein the production has to be…
Q: an organisation can organise its purchasing function choosing among centralisation, decentralisation…
A: Each purchasing function has specific advantages and disadvantages, first, I will discuss each…
Q: What are Likeablity Bias, Performance Bias, Attribution Bias, and Affinity Bias in the workplace?
A: Bias in the workplace refers to unfair or special treatment and injustice to specific individuals…
Q: Discuss briefly the historical development of strategic management.
A: In the contemporary era, strategic management has evolved into a multidimensional and dynamic field.…
Q: An institution has 7 departments. The closeness chart is given in the following table. 1. Material…
A: The layout plan is the aspect of the organization that is concerned with deciding the best and…
Q: esource based view theory, transcation cost theory, theory X and Y, human capital theory,…
A: Artificial intelligence is the aspect of the technology or computer-based system that includes…
Q: What is the significance of IT project management in the successful implementation of technology…
A: An essential discipline for the effective implementation of technology projects in businesses is IT…
Q: Consider the data below for the sales of widgets: 1. Using seasonal percentages or seasonal indexes,…
A: Here, for the year 4, the annual widgets sales are 1500I will determine the seasonal index for each…
Q: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine.…
A:
Q: 0 1 2 3 02 1 4 03 1 5 1 6 сл 2 4 6 2 3 Legend ES ID EF SL SL LS DUR LF Resource
A: Here, in the question, I am given the network diagram, This network diagram is to be completed,…
Q: Year 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Advertising Expenditure $ 000 51 58 62…
A: Note: Since you have posted a question with multiple sub parts, we will provide the…
Q: Describe the process of model identification and system parameter estimation and its significance in…
A: Model identification and system parameter estimation are crucial steps in various fields, including…
Q: Hello from the case study here are the questions 1. Question One Using the information in the…
A: Environmental analysis is the aspect or area of business that is utilized as a strategic tool for…
Q: Min Z = Subject to: 4x1 + 3x2 > 200 (constraint 1) 2x₁ + x2 ≥ 70 (constraint 2) > X1, X₂ ≥ 0 O 35…
A: Objective function:Min 7x1 + 5x2Constraints:C1 = 4x1 + 3x2 ≥ 200C2 = 2x1 + x2 ≥ 70x1, x2 ≥ 0The…
Q: Calculate the process capability
A: UCL = 1.01LCL= 0.99Standard deviation = 0.003
Q: why is Project Management crucial to Strategic Planning of an organization
A: Management is an integral part of an organization. It helps in coordinating the efforts of various…
Q: How does the Internet contribute to the globalization of e-commerce and digital business models?…
A: The globalisation of e-commerce and digital business models has been made possible by the Internet,…
Q: Burger Prince buys top-grade ground beef for $1.00 per pound. A large sign over the entrance…
A: Burger price = 60 cents each = $0.60 Cost per Burger = 50 cents = $0.50 Cost price of beef = $1.00…
Q: Within a workplace, a worker describes how his co-workers leave business documents on the reception…
A: When co-workers leave business documents on the reception desk and belongings within the conference…
Q: Southeastern Oklahoma State University's business program has the facilities and faculty to handle…
A: Efficiency and utilization are paramount parts of resource management and procedure optimization.…
Q: discuss , , What are the key components or fundamental elements of a strategic management framework?
A: The art and science of directing an organisation towards long-term success is known as strategic…
Q: Refer to the table below. Assume that the company Involved now finds that the learning rate is 70…
A: Time taken to produce 1st unit = 100 hoursLearning Curve Percent = 70%Learning Rate coefficient =…
Q: For the given sample size, the control limits for 3-sigma x chart are: Upper Control Limit (UCL) =…
A: There are many types of process charts. One of the process charts is an X-bar chart. It is the mean…
Q: Plot the scattergraph for the data. (ii) Use the data, to develop a regression equation…
A: NOTE: We are allowed to do first three sub-parts only. YEAR ADVERTISING EXPENDITURE…
Q: In the program evaluation and review technique below, how many activities are there for this 7 month…
A: Program Evaluation and Review Technique is referred to as PERT. This statistical tool is employed in…
Q: Evaluate the impact of geopolitical factors, such as trade restrictions and global alliances, on the…
A: Supply chain management plays a pivotal role in coordinating the movement of goods and services,…
Q: From the Research Topic and questions kindly provide a draft for a proposed seminar presentation as…
A: Topic"An Analysis of the factors influencing Recruitment, Selection and Retention of Public Sector…
Q: Explain what is the use of work contour in MS project? What are the different types of contour you…
A: In Microsoft Project, a work contour is a tool that helps you define how work on a task is…
Q: (b) Johnson and Johnson Ltd has four plants each of which can manufacture any one of the four…
A: A linear objective function and a collection of linear constraints form the conventional linear…
Q: Potter Machine Company expects total sales of $60,000. The price per unit is $10. The firm estimates…
A: The optimal order size of inventory means the absolute amount of inventory a business should have at…
Q: The school board is trying to evaluate a new math program introduced to second-graders in five…
A: SchoolNo. of test Errors A45B24C38D41E45Sum193
Step by step
Solved in 5 steps with 3 images
- 1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He has identified the activities and their durations for each stage of operation. Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D I 4 F J 3 F K 5 C,J L 8 H,E,I,K M 4 CJ Draw a network diagram (AOA) for this road construction project. Which are the critical activities? How long the project will take?Table 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT) Activity Preceded 1 Order review 2 Order vendor parts 3 Produce standard parts 4 Design custom parts Software development 5 6 Manufacture custom parts 7 Assemble 8 Test Duration 5 15 20 13 18 10 10 5 1 1 1 4 2,3,6 2,5 Resources Ryan Carly Ryan Lauren Connor Ryan Dawn Test Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air Control Project: Time Plan without Resources), USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of your programming process (indicate technical dependency with resources imposed).Normal Time Problem 1 You are the manager of a project to improve a billing process at your firm. The following table contains the data you will need to conduct crashing of the project duration. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after Week 12. Activity Immediate Predecessor(s) Crash Time (weeks) Normal (Direct) Cost Crash Cost (weeks) ($) ($) A 4 1 5,000 8,000 B 5 2 8,000 11,000 C A 1 1 4,000 4,000 Ꭰ B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F Ꭰ 7 6 4,000 7,000 What is the optimum choice for project duration?
- Time Immediate Time Activity (weeks) Predecessor(s) Activity (weeks) 5 6 9 7 ABCD 5622 A A Dave's earliest start (ES) and earliest finish (EF) are: Activity A B ооши G H Dave's latest start (LS) and latest finish (LF) are: Activity H ES 0 0 5 5 6 6 11 12 LS 13 EFGH EF 5 6 7 7 11 12 20 19 LF Immediate Predecessor(s) B B C, E D, FActivity A B CDEFG 3. You have been appointed as the project leader of a project to be undertaken by your company. You have identified the following tasks and made the time estimates for each task as listed in the table below: с Preceding "from" activity A A A B,C C,D,E F Succeeding "to" activity B,C,D E E F F G Estimated duration work days) 3 5 3 10 8 14 7 a) Use the above table to construct a project network diagram. b) Determine the critical path for the project and its duration.What is the importance of variance analysis to project managers? Give 2 examples.
- The detail of the direct cost for project XYZ are given in Table 1. Table 1 Details for Project XYZ Normal Direct Cost 100 150 Activity Predecessor Maximum Slope Time (day) crash time A 100 50 A 3 A 4 200 1 200 200 D B 3 1 60 E C 4 2 D.E 70 90 F 3 150 1 The indirect cost is listed in Table 2. i. If the project needs to be crashed from its initial time, T1 to T5, list the step-by-step changes in activity and the direct cost to crash the project in Table 2,. ii. Identify the project's lowest cost possible within T1-T5 duration Table 2 Project Duration Activity crashed Step Total Direct Indirect Total Cost Cost Cost 1 Initial time T1 900 New time T2 800 New time T3 600 4 New time T4 550 New time T5 50021. The following table provides the information necessary to construct a project network and project crash data: Activity (i, j) Activity Predecessor Activity Time (weeks) Normal Crash Activity Cost Normal Crash a (1,2) --- 16 8 $2000 $4400 b (1,3) --- 14 9 1000 1800 c (2,4) a 8 6 500 700 d (2,5) a 5 4 600 1300 e (3,5) b 4 2 1500 3000 f (3,6) b 6 4 800 1600 g (4,6) c 10 7 3000 4500 h (5,6) d, e 15 10 5000 8000 a. Construct the project network b. Manually crash the network to 28 weeks Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.Consider the following project network and activity times (in days). E Start Finish D F G Activity | A B C D EF G Time 3 5 6 .2 The crashing data for this project are as follows: Time (days) Cost ($) Activity Normal Crash Normal Crash 800 1,200 2,000 A 2 1,400 В 2 1 1,900 3 2,800 1,500 1,800 2,300 E 6 4 2,800 1,000 1,000 F 2 1 600 G 2 1 500 a. Find the critical path and the expected project completion time. b. What is the total project cost using the normal times? Assume that management desires a 12-day project completion time. c. Formulate a linear programming model that can be used to assist with the crashing decisions. d. What activities should be crashed? e. What is the total project cost for the 12-day completion time? 2.
- O O D 40 4 22:31 photo_2021-02-2... O By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A В CDEF GHIJ Duration 8 28 4 6. 4 5 6 (days) Following C,DEFGH Activity * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? 7. 5,A Social Project manager is faced with a project with the following activities: Activity-ID Description Duration 1-2 Social Work Team to live in Village 5 Weeks 1-3 Social Research Team to do survey 12 Weeks 3-4 Analyse results of survey 5 Weeks 2-4 Establish Mother & Child Health Program 14 Weeks 3-5 Establish Rural Credit Programme 15 Weeks 4-5 carry out Immunisation of under Fives 4 Weeks Draw the arrow diagram, using the helpful numbering of the activities, which suggests the…Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Immediate Predecessor(s) Activity ABCDEFG This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B A, D C E, F Time (days) 4 5 3 10 4 6 10