gure 1 shows a cross-section through an excavation in a deep sand deposit. The site engineer termined that the exaction is too deep for a cantilever sheet pile to perform as an economical tion and recommended to prop a smaller thickness sheet pile wall by using wooden struts that e spaced 3 m along the length of the wall. You are the office design engineer and are given the etch below and asked to determine the following: i. The distribution of the lateral pressure over the wall height. The total force that the retaining wall must resist. i. i. The loads (in kN) carried by the individual upper and lower props. q = 12 kPa 1.5 m Props 1.5 m Sand y= 17.5 kN/m³ d' = 34° Sand 7 sat= Figure 1 V = 19.5 kN/m² d' = 34° 3.0 m 7.0 m

Principles of Foundation Engineering (MindTap Course List)
9th Edition
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter18: Sheet-pile Walls
Section: Chapter Questions
Problem 18.6P
icon
Related questions
Question

Figure 1 shows a cross-section through an excavation in a deep sand deposit. The site engineer determined that the exaction is too deep for a cantilever sheet pile to perform as an economical option and recommended to prop a smaller thickness sheet pile wall by using wooden struts that are spaced 3 m along the length of the wall. You are the office design engineer and are given the sketch below and asked to determine the following:

  1. The distribution of the lateral pressure over the wall height.
  2. The total force that the retaining wall must resist.
  3. The loads (in kN) carried by the individual upper and lower props.
Figure 1 shows a cross-section through an excavation in a deep sand deposit. The site engineer
determined that the exaction is too deep for a cantilever sheet pile to perform as an economical
option and recommended to prop a smaller thickness sheet pile wall by using wooden struts that
are spaced 3 m along the length of the wall. You are the office design engineer and are given the
sketch below and asked to determine the following:
i.
ii.
iii.
The distribution of the lateral pressure over the wall height.
The total force that the retaining wall must resist.
The loads (in kN) carried by the individual upper and lower props.
q = 12 kPa
1.5 m
Props
1.5 m
Sand
7= 17.5 kN/m³
$' = 34°
Figure 1
▼
Sand 7 sat = 19.5 kN/m²
d' = 34°
3.0 m
7.0 m
Transcribed Image Text:Figure 1 shows a cross-section through an excavation in a deep sand deposit. The site engineer determined that the exaction is too deep for a cantilever sheet pile to perform as an economical option and recommended to prop a smaller thickness sheet pile wall by using wooden struts that are spaced 3 m along the length of the wall. You are the office design engineer and are given the sketch below and asked to determine the following: i. ii. iii. The distribution of the lateral pressure over the wall height. The total force that the retaining wall must resist. The loads (in kN) carried by the individual upper and lower props. q = 12 kPa 1.5 m Props 1.5 m Sand 7= 17.5 kN/m³ $' = 34° Figure 1 ▼ Sand 7 sat = 19.5 kN/m² d' = 34° 3.0 m 7.0 m
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 7 steps with 6 images

Blurred answer
Knowledge Booster
Braced cuts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning