Cost Code Variance 03-3100M ($25,000) Description Concrete Material Budget $150,000 Committed $175,000 Cost to Date $135,000 The current project schedule update tells us that the concrete scope of work is 72% poured/placed. What percent of cost have we expended? A. 90% B. 77% C. 72% D. 23%

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter12: Balanced Scorecard And Other Performance Measures
Section: Chapter Questions
Problem 11MC: Dixon Construction Materials has collected this information: Based on this Information, what is the...
icon
Related questions
Question
Cost Code
Variance
03-3100M
($25,000)
Description
Concrete Material
Budget
- $150,000
Committed
$175,000
- Cost to Date
$135,000
The current project schedule update tells us that the concrete scope of work is 72% poured/placed.
What percent of cost have we expended?
A. 90%
B. 77%
C. 72%
D. 23%
Transcribed Image Text:Cost Code Variance 03-3100M ($25,000) Description Concrete Material Budget - $150,000 Committed $175,000 - Cost to Date $135,000 The current project schedule update tells us that the concrete scope of work is 72% poured/placed. What percent of cost have we expended? A. 90% B. 77% C. 72% D. 23%
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College