a- Which site should the contractor select? b- When do the costs of two sites are equals (After how many months of work the costs are similar)?
Q: ABC Company produces two main products and a by-product out of a joint process. The ratio of output…
A: Joint Costs are the costs incurred in the production process while manufacturing more than one…
Q: A. Company E constructs its own building and incurs the following costs: Direct Material |Direct…
A: a. Calculate the cost of building: Hence, the cost of building is $165,000.
Q: The annual cost and an effectiveness measure of items salvaged per year for four mutually exclusive,…
A: Computation of CER is shown below: The formula snip for computing the above value as follows:
Q: Which example is NOT a step cost?
A: Cost are the expenses which are incurred by the company due to fact that certain activities has been…
Q: In connection with surfacing a new highway, a contractor has a choice of two sites on which to set…
A: Fixed cost is the cost which do not change with the change in the production level. Conversely,…
Q: MEGA BRIDGE SDN BHD has been offered by government to construct a bridge. Based on PROJECT X AND…
A: Cost of Project: It is total amount required to finish the project and consists of a Direct Cost…
Q: ABC Company produces two main products and a by-product out of a joint process. The ratio of output…
A: Joint cost can be referred to as the cost incurred for the production of two or more than two…
Q: A metal plating company is considering four different methods for recovering by-product heavy metals…
A: Calculation of Net Present Values of the company: Excel spreadsheet:
Q: Cost: Salary of marketing manager Decision: Project discontinuance: manager to be…
A: Relevant cost means that cost which helps for decision making. conditions :1. It should be future…
Q: Consider the two air conditioning systems detailed below. Use AW analysis to determine the…
A:
Q: Your company is an established engineering contractor for TNB. Your job is to install an underground…
A: "Since you have asked a question with multiple sub-parts, we will solve the first three sub-parts…
Q: Rie the actvities with their precedence sequence and expected time (days) are listed for a project…
A: The critical path of a network is the longest time path through the network.
Q: The table below shows a subcontracting work having 3 work activities. DIRECT COST BALANCED BID…
A: The question is based on the concept of profit calculation in different situation of subcontracting…
Q: Which of the following documents is most likely to be used in the expenditure cycle. Select one: O…
A: Expenditure cycle: Expenditure cycle refers to the repetitive business activities that deals with…
Q: Required: a. Calculate the cost per equivalent unit for direct materials and conversion costs. b.…
A:
Q: A finance manager has to select one of the four different suppliers of raw materials. The total cost…
A: A finance manager has to select one of the four different suppliers of raw materials.there are total…
Q: When determining the cost of a manufactured good under an operation-costing system, a company would:…
A: as per operating costing system cost of goods manufactured is computed by taking direct material…
Q: Question # 3 A Report a Problem Revisit Choose the best option ll these statements are true for…
A: Step 1 Contract costing is the accounting of costs associated with a specific contract with a…
Q: percentage of completion can be measured in a number of ways, in
A: Percentage of completion is the method to compute the level of production completed which ascertains…
Q: Which of the following would be the most appropriate basis for allocating the costs of plant…
A: Definition: Property, plant, and equipment: These assets are long-lived economic resources which are…
Q: The project director had queried the concrete work for the first floor and had asked you to rerify…
A: When the actual costs are more than the budgeted costs, we say an unfavorable variance is generated.…
Q: Requirements: A. What is the total Equivalent production for Materials? B. What is the total…
A: Since you have posted a question with multiple sub-parts, we will solve first three subparts for…
Q: please answer accordingly
A: Given Information Lathe A LatheB First Cost 40,000 56,000 Salvage Value 5,000 7,000…
Q: 2. Based on your response in part (1), determine the total costs allocated from each support…
A: Part 1: b and personal department.
Q: For a project, an estimated normal time with an associated normal cost is given for each activity.…
A:
Q: 21. if the direct method of allocation is used, how much of the equipment maintenance costs would be…
A: The overhead rate is calculated with the help of following formula Overhead Rate = Manufacturing…
Q: If the Maintenance Department's total costs to be allocated is P24,000, Department A under the…
A: Overhead allocation under all 3 parts are computed. The overhead allocation of service departments…
Q: 2. Equivalent units of production (A) will always be greater than or equal to the physical units (B)…
A: "Since you have asked multiple questions, we will solve only first question for you. If you want any…
Q: You have been asked by management to classify the costs associated with the start-up of this new…
A: SOLUTION- CLASSIFICATION OF COST- IT MEANS SEPARATION OF EXPENSES IN THE DIFFERENT SECTORS AS LIKE…
Q: Which of the following costs is a mixed cost? a.straight-line depreciation on factory equipment…
A: Mixed cost means cost that includes both fixed and variable cost. Based on the activity levels cost…
Q: In trying to decide whether or not to replace a sorting/baling machine in a solid waste recycling…
A: The Defender is the currently owned (in place) item and Challenger is the new possible replacement…
Q: A civil engineer has 2 alternative designs for a house. Both designs involve the acquisition of a…
A: The total salary expense for each design will be calculated by multiplying the wage rate per day by…
Q: The production schedule is: A. The expected demand for the firm’s finished goods for a given…
A: Production is the process of converting raw material into finished goods which can be consumed by…
Q: Which of the following activity bases would be appropriate to use for materials handling? A.…
A: Activity-based costing (ABC) method: The costing method which allocates overheads to the products…
Q: Which one of the following costing methods is most likely to be used by a company invloved in the…
A: Solution : Which one of the following costing methods is most likely to be used by a company…
Q: A metal plating company is considering four different methods for recovering by-product heavy…
A: The rate which makes the total discounted worth of cash flows equal to zero is called IRR or…
Q: The equivalent units for the FIFO unit cost represent: a. work done during the current period. b.…
A: Equivalent units of products concept came in to existence when some units are not fully completed at…
Q: what lump-sum price should the contractor bid?
A: Lump-sum price is the price which is the total of all costs which will be incurred on the contract…
Q: Herme, the quarry supervisor for Espinosa Stone, wants to select the more economical of two…
A: Annual worth distributes present worth into equivalent uniform value over its useful life.
Q: Which of the following are examples of a mixed cost? I - A building that is used for both…
A: The costs incurred in the production, can be classified as variable cost, fixed cost and mixed…
Q: Required a. Determine the avoidable cost per unit of making the bike frames, assuming that Sturdy is…
A: Avoidable cost refers to those cost of the company which is eliminated or not incurred when a…
Q: Identify the following as elements of first cost or annual operating cost: (a) direct materials, (b)…
A: Cost: It can be defined as the total amount that is spent by a business in manufacturing a product.
Q: 3. There are three resource types available for a certain project. One unit of each resource type is…
A: Project resource management is a technique in which the resources are allocated towards various work…
Q: : An engineer determined the payback period of the project lowing table presents the project contact…
A: Given information : Initial cost 15000000 Annual cost 3000000 Salvage 5000000 The…
Q: If the 300 defective bolts(normal spoilage) were repaired and management wanted to be sure the…
A: The rework costs are incurred to rectify the spoiled product so that it can be sold in the market.
Q: A manufacturing process can be designed for varying degrees of automation. The following is relevant…
A: Present Value- The current value of a sum of future money with a specific interest rate is referred…
Step by step
Solved in 2 steps
- In order to carry a new investment project, company A has to purchase a machine for OMR 400,000. Company A staff have enough capacity to carry out the production, no one new will need to be hired, they are currently paid OMR 20,000. Calculate the relevant cost? a. OMR 20,000 Ob. OMR 380,000 O c. OMR 400,000 d. OMR 420,000Three alternatives have the following cost data associated with them: Data Alt. 1 Alt. 2 Alt. 3 Useful Life, Years 10 10 10 First Cost $1,325,000 $1,980,000 $1,650,000 Annual Benefit 265,000 589,000 435,000 Annual M&O Costs 95,000 97,000 91,000 Annual M&O Gradient 2,300 2,100 1,980 Salvage Value 145,000 205,000 178,000 Loan Payment 150,946 225,565 187,971 The loan payments are calculated using an interest rate of 10%, a life equal to the life of the machine, and a down payment of 30%. Use a MARR of 12% and determine which machine, if any, should be purchased. Use incremental analysis.Three alternatives have the following cost data associated with them: Data Alt. 1 Alt. 2 Alt. 3 Useful Life, Years 10 10 10 First Cost $1,125,000 $1,980,000 $1,650,000 Annual Benefit 265,000 589,000 435,000 Annual M&O Costs 95,000 97,000 91,000 Salvage Value 145,000 205,000 178,000 Determine whích machine is better to purchase, if i = 10%. 1. Use a B/C 2. Use a Payback Period
- Reference: Case Study S Dunn Manufacturing is considering the following two alternatives. The cost information for the two proposals for replacing an equipment are provided are in table below. Initial cost Benefits/year Machine X $120,000 $20,000 for the first 10 years and $9,000 for the next 10 years Life Salvage value $40,000 MARR 5.2. The NPW of machine X is A) $35,158 B) $48,192 C) $50,752 Machine Y $96,000 $12,000 per year for 20 years. 20 years 8% $20,000Should WMM lease or construct their own production facility Option 1: Construct Costs to incur: Actual expenditure towards buying land, construct building and getting ready for use $ 500,000Taxes, insurance, and repairs (per year) $ 20,000Intended years of use 18Projected market value in 18 years $ 1,000,000 Budgeted maximum expenditure towards buying land, construction of building and getting ready for use. $ 500,000Remainder in four payments of; $ 175,000Option 2: LeaseIntended years of use 18First lease payment due now $ 100,000Rest of the lease payments…Problem 2: Alternatives for constructing a new facility which are mutually exclusive are being considered. The annual equivalènt costs and estimated benefits of the alternatives are as follows: Alternative Cost Benefits $1,050,000 $900,000 $1,230,000 $1,350,000 $990,000 $1,110,000 $810,000 $1,390,000 $1,500,000 $1,140,000 A C D E Using the B-C ratio, which alternative, if any, should be adopted for investment?
- heavy equipment for a certain project and the details are as follows: ITEM: MACHINE A: MACHINE B: First Cost P2,000,000.00 P3,000,000.00 Annual operating P325,000.00 P250,000.00 cost Annual labor cost Insurance and taxes Payroll taxes Estimated life P500,000.00 P320,000.00 4% 10% 12 yrs. 4% 10% 12 yrs. If the minimum ROR is 25%, What is the annual cost of Machine A & B using present worth method?Given the two machines’ data Machine A Machine B First Cost P8,000.00 P14,000.00 Salvage value 0 2,000.00 Annual operation 3,000.00 2,400.00 Annual maintenance 1,200.00 1,000.00 Taxes and insurance 3% 3% Life, years 10 15 Money is worth at least 16% Using equivalent uniform annual cost method, determine the value of alternative A and alternative B:Calculate for the cost of site clean-up if the total duration of the project is 18 months. The estimated number of trips per week is 3 truck loads of site rubbish and debris with a cost of Php 3,200.00 per trip. Php 9,600.00 Php 19,200.00 Php 345,000 Php 691,200.00
- RLC Manufacturing is planning to purchase a cutting equipment. Information are as follows: Equipment 1 Equipment 2 First Cost P 12,000 P 18,000 Salvage Value P 600 P 2,000 Annual Operation P 3,200 P 2,500 Annual Maintenance P 1,200 P 1,000 Taxes & Insurance 3% 3% Life, years 10 15 Money is worth at least 16%. Which equipment should be selected? Use: Annual Cost MethodTwo alternatives, code-named X and Y, are under consideration at Afalava Corporation. Costs associated with the alternatives are listed below. Alternative N Alternative Y $37,000 $37,000 Materials costs............ Processing costs. $38,000 $53,000 Equipment rental. $12,000 $26,000 Occupancy costs......... $16,000 $26,000 Are the materials costs and processing costs relevant in the choice between alternatives X and Y? (Ignore the equipment rental and occupancy costs in this question.) Select one: a. Only materials costs are relevant b. Only processing costs are relevant C. Both materials costs and processing costs are relevant d. Neither materials costs nor processing costs are relevantGiven the two machines' data Machine A Machine B First Cost P8,000.00 P14,000.00 Salvage value Annual operation 2,000.00 3,000.00 2,400.00 Annual maintenance 1,200.00 1,000.00 Taxes and insurance 3% 3% Life, years 10 15 Money is worth at least 16% Using equivalent uniform annual cost method, determine the value of alternative A and alternative B: ANSWER for ALTERNATIVE A: Blank 1 ANSWER for ALTERNATIVE B: Blank 2