Consider the following table and answer the following questions. All duration estimates or estimated times are in days, and the network proceeds from Node 1 to Node 9. 1. Draw an AOA network diagram representing the project. 2. Prepare a Gantt Chart considering the start date of the project as 1" November. Make necessary assumptions where required. 3. Identify all of the paths on the network diagram and note how long they are, using Figure 6-8 as guide for how to represent each path. 4. What is the critical path for this project and how long is it? 5. What is the shortest possible time needed to complete this project? Activity Intial Node Final Node Estimated Duration

Computer Networking: A Top-Down Approach (7th Edition)
7th Edition
ISBN:9780133594140
Author:James Kurose, Keith Ross
Publisher:James Kurose, Keith Ross
Chapter1: Computer Networks And The Internet
Section: Chapter Questions
Problem R1RQ: What is the difference between a host and an end system? List several different types of end...
icon
Related questions
Question
Consider the following table and answer the following questions. All duration estimates
or estimated times are in days, and the network proceeds from Node 1 to Node 9.
1. Draw an AOA network diagram representing the project.
2. Prepare a Gantt Chart considering the start date of the project as 1s" November.
Make necessary assumptions where required.
3. Identify all of the paths on the network diagram and note how long they are, using
Figure 6-8 as guide for how to represent each path.
4. What is the critical path for this project and how long is it?
5. What is the shortest possible time needed to complete this project?
Activity
Initial Node
Final Node
Estimated
Duration
A
1
2
2
в
2
3
2
2
4
D.
4
E
3
6
F
4
6.
3.
G
7.
6.
6.
6.
5.
7
K
Transcribed Image Text:Consider the following table and answer the following questions. All duration estimates or estimated times are in days, and the network proceeds from Node 1 to Node 9. 1. Draw an AOA network diagram representing the project. 2. Prepare a Gantt Chart considering the start date of the project as 1s" November. Make necessary assumptions where required. 3. Identify all of the paths on the network diagram and note how long they are, using Figure 6-8 as guide for how to represent each path. 4. What is the critical path for this project and how long is it? 5. What is the shortest possible time needed to complete this project? Activity Initial Node Final Node Estimated Duration A 1 2 2 в 2 3 2 2 4 D. 4 E 3 6 F 4 6. 3. G 7. 6. 6. 6. 5. 7 K
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Recommended textbooks for you
Computer Networking: A Top-Down Approach (7th Edi…
Computer Networking: A Top-Down Approach (7th Edi…
Computer Engineering
ISBN:
9780133594140
Author:
James Kurose, Keith Ross
Publisher:
PEARSON
Computer Organization and Design MIPS Edition, Fi…
Computer Organization and Design MIPS Edition, Fi…
Computer Engineering
ISBN:
9780124077263
Author:
David A. Patterson, John L. Hennessy
Publisher:
Elsevier Science
Network+ Guide to Networks (MindTap Course List)
Network+ Guide to Networks (MindTap Course List)
Computer Engineering
ISBN:
9781337569330
Author:
Jill West, Tamara Dean, Jean Andrews
Publisher:
Cengage Learning
Concepts of Database Management
Concepts of Database Management
Computer Engineering
ISBN:
9781337093422
Author:
Joy L. Starks, Philip J. Pratt, Mary Z. Last
Publisher:
Cengage Learning
Prelude to Programming
Prelude to Programming
Computer Engineering
ISBN:
9780133750423
Author:
VENIT, Stewart
Publisher:
Pearson Education
Sc Business Data Communications and Networking, T…
Sc Business Data Communications and Networking, T…
Computer Engineering
ISBN:
9781119368830
Author:
FITZGERALD
Publisher:
WILEY