Borges Machine Shop, Inc., has a 1-year contract for the production of 75,000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow: Annual contracted units Annual fixed cost Per unit variable cost General-Purpose Equipment (GPE) 75,000 $100,000 $15.00 Flexible Manufacturing System (FMS) 75,000 $225,000 $14.75 Dedicated Machine (DM) 75,000 $500,000 $13.00 Based on the total cost, the process that is best suited for the current contracted volume is Suppose the contracted volume changes to 275,000 gear housings. Based on the total cost, the process that is best suited for the new

Marketing
20th Edition
ISBN:9780357033791
Author:Pride, William M
Publisher:Pride, William M
Chapter19: Pricing Concepts
Section: Chapter Questions
Problem 6DRQ
icon
Related questions
Question
K
Borges Machine Shop, Inc., has a 1-year contract for the production of 75,000 gear housings for a new off-road vehicle. Owner Luis Borges
hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are
general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost
data follow:
Annual contracted units
Annual fixed cost
Per unit variable cost
General-Purpose
Equipment (GPE)
75,000
$100,000
$15.00
Flexible Manufacturing
System (FMS)
75,000
$225,000
$14.75
Dedicated
Machine (DM)
75,000
$500,000
$13.00
Based on the total cost, the process that is best suited for the current contracted volume is
Suppose the contracted volume changes to 275,000 gear housings. Based on the total cost, the process that is best suited for the new
volumo in
Transcribed Image Text:K Borges Machine Shop, Inc., has a 1-year contract for the production of 75,000 gear housings for a new off-road vehicle. Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow: Annual contracted units Annual fixed cost Per unit variable cost General-Purpose Equipment (GPE) 75,000 $100,000 $15.00 Flexible Manufacturing System (FMS) 75,000 $225,000 $14.75 Dedicated Machine (DM) 75,000 $500,000 $13.00 Based on the total cost, the process that is best suited for the current contracted volume is Suppose the contracted volume changes to 275,000 gear housings. Based on the total cost, the process that is best suited for the new volumo in
K
Annual contracted units
Annual fixed cost
Per unit variable cost
General-Purpose
Equipment (GPE)
75,000
$100,000
$15.00
Flexible Manufacturing
System (FMS)
75,000
$225,000
$14.75
Based on the total cost, the process that is best suited for the current contracted volume is
Dedicated
Machine (DM)
75,000
$500,000
$13.00
Suppose the contracted volume changes to 275,000 gear housings. Based on the total cost, the process that is best suited for the new
volume is
Suppose the contracted volume changes to 375,000 gear housings. Based on the total cost, the process that is best suited for the new
volume is
Transcribed Image Text:K Annual contracted units Annual fixed cost Per unit variable cost General-Purpose Equipment (GPE) 75,000 $100,000 $15.00 Flexible Manufacturing System (FMS) 75,000 $225,000 $14.75 Based on the total cost, the process that is best suited for the current contracted volume is Dedicated Machine (DM) 75,000 $500,000 $13.00 Suppose the contracted volume changes to 275,000 gear housings. Based on the total cost, the process that is best suited for the new volume is Suppose the contracted volume changes to 375,000 gear housings. Based on the total cost, the process that is best suited for the new volume is
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L