a) Draw a schedule showing the work package critical path and duration.  b) Assume the wor kpackage has to be completed within 44 weeks.Calculate the most cost effective way of completing the work package within this time, giving the cost increase associated with this crash sequence.  c) Discuss the main factors likely to be considered by the project manager when considering time– cost trade-offs and time–quality trade-offs as ways of reducing the overall time required to complete a project or work package

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

a) Draw a schedule showing the work package critical path and duration. 
b) Assume the wor kpackage has to be completed within 44 weeks.Calculate the most cost
effective way of completing the work package within this time, giving the cost
increase associated with this crash sequence. 
c) Discuss the main factors likely to be considered by the project manager when
considering time– cost trade-offs and time–quality trade-offs as ways of reducing
the overall time required to complete a project or work package. 

Question 1
Table 1: Activity normal and crash durations and costs
Activity Normal dura- Crash duration Normal cost (£) Crash cost (£)
tion (weeks)
A-B
B-C
B-D
B-E
C-F
C-K
D-G
E-H
F-G
FI
F-K
F-L
F-N
G-L
H-K
H
J-O
K-N
L-M
M-O
N-O
4
3
2
6
3
3
2
10
3
3
2
2
2
2
10
238
4
2
12
(weeks)
2
3
I
5
2
2
I
8
2
2
I
I
7
2
I
10
300 000
100 000
50 000
150 000
30 000
20 000
000
60 000
160 000
350
000
170 000
330
000
250 000
60 000
100 000
10000
30 000
50 000
40 000
5 000
200 000
300
420 000
100 000
55 000
200 000
150 000
25 000
350 000
140 000
260 000
500 000
270 000
440 000
500 000
65 000
110 000
20 000
35 000
80 000
50 000
6 000
240 000
Note: The crash duration represents the minimum duration where an activity is speeded up as much
as possible. The crash cost represents the increased cost of the activity after it has been speeded up
as much as possible.
Transcribed Image Text:Question 1 Table 1: Activity normal and crash durations and costs Activity Normal dura- Crash duration Normal cost (£) Crash cost (£) tion (weeks) A-B B-C B-D B-E C-F C-K D-G E-H F-G FI F-K F-L F-N G-L H-K H J-O K-N L-M M-O N-O 4 3 2 6 3 3 2 10 3 3 2 2 2 2 10 238 4 2 12 (weeks) 2 3 I 5 2 2 I 8 2 2 I I 7 2 I 10 300 000 100 000 50 000 150 000 30 000 20 000 000 60 000 160 000 350 000 170 000 330 000 250 000 60 000 100 000 10000 30 000 50 000 40 000 5 000 200 000 300 420 000 100 000 55 000 200 000 150 000 25 000 350 000 140 000 260 000 500 000 270 000 440 000 500 000 65 000 110 000 20 000 35 000 80 000 50 000 6 000 240 000 Note: The crash duration represents the minimum duration where an activity is speeded up as much as possible. The crash cost represents the increased cost of the activity after it has been speeded up as much as possible.
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.