a. Construct the project network b. Determine the critical path c. Find the completion time of the project d. Make a Gantt chart of the activities
Q: A plumber has decided to use the techniques of project management in order to plan a job. He knew…
A: The critical path method in project management is the longest set of activities that must be…
Q: a. Construct a CPM network for the design project. b. Compute the EF, LF, and slack for each…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: a. Construct the network diagram for this project. b. Determine the earliest and latest start times…
A: Below is the solution:-
Q: Which of the following activities is not part of defining a project?a. The project triangleb. The…
A: An organization has numerous projects running at a time and numerous projects in the pipeline to be…
Q: 3.1 Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers…
A: Critical path examination is an undertaking arranging technique that spotlights on recognizing…
Q: As the pandemic waned, an educational institution was faced with the imperative of refurbishing and…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: Discuss the ethical considerations associated with completting a project in the shortest possible…
A: Three things that drive ethical conduct are responsibility, honesty, and respect, which has been…
Q: a. Draw a project network b. Identify the critical path c. Develop the activity schedule for the…
A: A project schedule network diagram shows the tasks that are to be performed in the defined sequence.…
Q: The conditions and pert times for constructing a network diagram are given below. -Creation…
A: Given data is
Q: Explain how you will employ scope management to a new project you have been tasked to manage.
A: Project scope is a task or work that needs to be completed in order to deliver the product within…
Q: a) Draw an ACON diagram of the project, including activity durations. b) Define the critical path,…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 11. Building a backyard swimming pool consists of nine major activities. The activities and their…
A: As you have posted multiple questions, we will provide the answers to the first question. Kindly…
Q: (c) Compute the earliest start, earliest finish, latest start and latest finish time and the slack…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: 1- Calculate the total project time and floats 2- Identify activities on the critical path
A: In this question table data, we have activity information, for each activity, we have been given…
Q: Solve the following project by hand and submit your notes: Activity Normal Time Crash Time Normal…
A: Please find the attached network diagram below-
Q: (1) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical connection between tasks in a…
Q: Discuss the ethical considerations associated with completing a project in the shortest possible…
A: The ultimate goal of project management is to achieve all the project objectives within the given…
Q: Solve the following project by hand and submit your notes: Activity Normal Time (weeks) Crash…
A: NOTE: AS PER GUIDELINES, WE ARE ONLY ALLOWED TO DO THREE SUB-PARTS AT A TIME. PLEASE POST THE REST…
Q: lease complete the ES, EF, LS, LF, and slack for the project below. Activity Description
A: Early start (ES) indicates the earliest time of the beginning of the activity. Early finish (EF)…
Q: Task Duration (Weeks) Follows A 3 B 7 A C 9 A D 3 C E 11 B, D F 3 E G 2 F H 3 C F I 5…
A: We use the forward and backward methods to calculate the critical path.
Q: The estimated times and immediate predecessors for the activities in a project at George Kyparis's…
A: Activity Imm Pred a m b Expected timee = (a+4m+b)/6 SD(b - a) / 6 Variance A 9 10 11 10 0.333…
Q: According to the PMBOK Guides, every project must pass through several phases, from start to…
A: The project life cycle comprises of the characterized project stages which are normally…
Q: Two international banks are integrating two financial processing software systems as a result of…
A: Activity Immediate Predecessors Activity Time A - 3 B A 1 C A 2 D…
Q: Explain the ethical considerations associated with completing a project in the shortest possible…
A: The ultimate goal of project management is to complete all project objectives within the constraints…
Q: PERT analysis computes the variance of the total projectcompletion time as:a) the sum of the…
A: Leadership style is the approach of providing direction, plans implementation, and motivating…
Q: scüšslon 1. Discuss the differences between project work and normal operations, and the role of a…
A: Project Management Project management is the use of techniques, procedures, capabilities,…
Q: ) Construct an AON diagram using the above the Project Management table. ) What is the Critical Path…
A: The answer is as below:
Q: a) Determine the expected completion time and variance for each activity. b) Determine the total…
A: To calculate the Mean or Expected completion time for each activity is- [tA+4(tM)+tB]/6 Similarly,…
Q: a. Draw a CPM network for the project. b. Provide an overview for the project by computing the…
A: The project network is the diagram that shows the order of completion of project network activities…
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: For each activity, we have immediate predecessor data and Time in days, using the above table,…
Q: a. Develop a network diagram for the project using AON convention. b. Determine the project…
A: Here, in the question, we have the activity id, a description of each activity, immediate…
Q: i. Calculate the expected time for each activity ii. Draw a Gantt Chart from the same information…
A: As per Bartleby guidelines we can only solve first 3 sub par Below is the solution:-
Q: a) Develop a network diagram for the project. Identify the critical path. b) If the company would…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: a) Construct a network for this project b) Find a project schedule to minimize the completion time…
A: Given data is
Q: From the following information, develop an AON project network. Complete the forward and backward…
A: Given Information:
Q: Schedule the following activities using CPM: Activity Immediate Predecessor Time (weeks) A - 1…
A: a)
Q: Use the Program Evaluation and Review Technique to represent the project in an activity network. In…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: The following table contains a list of activities, with precedence requirements and crash costs. All…
A: Based on the table data,specifically Data like activity ID, Normal time and predecessor data, we…
Q: (i) Construct a Network Diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: Project ALPHA has 6 activities from A to Fas follows: Activity Duration Preceded By B A D Legend:…
A: Given data is
Q: The fo llowing is a table of activities associated with a project at Rafay lshfaq's software firm in…
A: Note: As per the Bartleby guidelines only the first three parts have been answered. AOA ( Arrow to…
Q: “Critical activities determine the project completion time”. Justify the statement.
A: The Project Management Body of Knowledge (PMBOK) defines the Critical Path Method as follows: The…
Q: Find the project's total duration, and described the completion of the project activities after the…
A: ANSWER IS AS BELOW:
Q: Compare and contrast the Project Evaluation and Review Technique (PERT) with the Critical Path…
A: Project management is managing different aspects of the project. It includes planning, organizing,…
Q: The following is NOT one of the advantages of CPM and PERT: a) Straightforward concept and not…
A: Option A is incorrect Project management and review techniques often called the PERT approach and…
Q: a. Determine the expected activity completion times b. Identify the critical path. c. If activity…
A: Given data is
Q: ws with all parties involved resulted in the following project information. The “systems integration…
A: Activity Immediate Predecessors Duration A - 3 B A 1 C A 2 D B,C 3 E C 5 F C 3 G E 7…
Solve the following attached problem using PERT or CPM.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- Explain all parts Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity Description ImmediatePredecessor Time(weeks) A Survey building site 5 B Develop initial design 9 C Obtain board approval A, B 13 D Select architect C 3 E Establish budget C 5 F Finalize design D, E 14 G Obtain financing E 11 H Hire contractor F, G 9 A) Draw a project network. (Submit a file with a maximum size of 1 MB.) B) Identify the critical path. (Enter your answers as a comma-separated list.) C) Develop the activity schedule for the project. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F G…The expected times and variances for the activities for a project for Test Marketers, Inc. are given below. (Assume time is provided in days.) ID 12345678 Description Pilot production Select channels of distrib. Develop mktg. program Test market Patent Full production Ad promotion Release Predecessor None None None 1 1 4 3 2,5,6,7 t₂ 6 7 4 4 10 16 3 2 Varlance [(b-a)/6]² 34225221 102.0 Give an example of Critical Path Analysis of one (1) Method.
- In 2017, Aurecon was appointed by the City of Ekurhuleni to design and construct rail lineunderpasses that are attractive, safe and user-friendly for pedestrians and cyclists, together withthe associated safety infrastructure. The project was completed in February 2019 at a cost of R50 million with over 5,000 resourcesinvolved over the 2-year project.Q.1.1 Based on the above project information, discuss any Five (5) project constraints. Q.1.2 Projects are different from operations, state any Five (5) project attributes.Imagine that you are a project manager for a construction company. You must create a WBS for the Site Preparation phase of this project. Here is a list of tasks. Task Title Predecessors Duration A Contract Approval -- 5 B Site Survey A 5 C Permit Application A 4 D Grading B,C 5 E Sewer Lines B 7 F Base Paving D 3 G City Approval C,F 6 H Final Paving E,G 8The following table shows the various activities of the development of a new product in your organization. Activity Event Immediate 1 2345 6 7 8 9 10 A B с D E F G H I J Questions: Predecessor( Optimistic s) A A B B C D E,F,G H Estimates of Activity Duration (Weeks) Most Likely Pessimisti (Tm) c (Tp) 4 ? I (To) 2 1 1 ? 3 2 ? 3 3 2 3 2 ? 5 ? 3 2 4 ? 1 4 6 5 ? 4 6 5 3 Averag e (Te) ? 2 2.2 a. Calculate ALL the missing (?) data points b. Draw the PERT network from the given data. c. Determine ALL the paths, the critical path and its total duration in days 5 4 3 2.2 ? 4 ?
- W AutoSave Off H PGDPM AA Calendar JULY 2022 Final No Label ✓ File Home Insert Draw Design Layout References 2 X U Undo Page 26 of 32 ▬ Paste Clipboard Arial Q Search BIU 25 of 5110 words U ab 12 ab x₂ A A Aa A X x ADA А Font Mailings QUESTION THREE 3.1 3.2 Search QUESTION FOUR Review View Help Paragraph Styles 2.1 Evaluate the significance of project stakeholder needs to project risk managers. 2.3 Using an example, discuss the meaning of the term risk assessment matrix. 16-16-15 ← 三三三三 2↓¶ 17° Normal Describe the relationship between uncertainty and project risk management. Discuss the use of time planning as a project risk management tool. Read the case study below and answer the questions that follow: Internal and external risks in project management English (South Africa) Text Predictions: On Accessibility: Unavailable No Spacing W Heading 1 The most critical phase in the project life cycle is the conceptual phase or bidding process, since only scarce information is available, and…3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: a) DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team. b) Find the critical path. c) What is the project completion time? • • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede: ACTIVITY DURATION (WEEKS) PRECEDES A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 — ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A — 2 B — 5 C — 1 D B…Explain the difference between the service projects and revenue projects ?
- 2. Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Immediate Time Activity Predecessor (Weeks) Description Survey Building Site Develop Initial Design Obtain Board Approval Selct Architect Establish Budget Finaliza Design Obtain Financing Hire Contractor A 6. C А, В 12 D 4 E 6 F D, E 15 E 12 H F, G 8 a. Draw the project network. b. Identify the critical path. c. In your assessment, is it reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? Explain your answer.Customer Identification and market share for a project Rotary car parking system. a) Show tables and charts for Customer identification. b) Market share for Rotary parking system globally?Why construct? Mapping a project in the absence of architecture. Product influence.