9.A Sample of EARNED VALUE ANALYSIS The following project is at the end of its 5 week.Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Duration Budget ($) 300 Actual Cost % Activity Predecessor (s) ($) 400 (week) Complete A 100 В 200 180 40 250 300 A 6 50 А, В 4 600 400 100 E А,В 2 400 200 100 F C 4 150 180 60 G D,F 100 200 75 H E,G 3 500 350 25

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Project Management

9.A Sample of EARNED VALUE ANALYSIS
The following project is at the end of its 5 week.Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC
and EAC for the project.
Budget
($)
Duration
Actual Cost
Activity
Predecessor (s)
(week)
($)
400
Complete
A
4
300
100
В
200
180
40
A
6
250
300
50
D
А,В
4
600
400
100
400
200
E
А, В
2
100
F
4
150
180
60
G
D,F
100
200
75
500
350
Е,G
3
25
Transcribed Image Text:9.A Sample of EARNED VALUE ANALYSIS The following project is at the end of its 5 week.Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Budget ($) Duration Actual Cost Activity Predecessor (s) (week) ($) 400 Complete A 4 300 100 В 200 180 40 A 6 250 300 50 D А,В 4 600 400 100 400 200 E А, В 2 100 F 4 150 180 60 G D,F 100 200 75 500 350 Е,G 3 25
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.