2. Assume the following project data given in Table 2. It is required to crash the project duration from its original duration. Assume Indirect (overhead) costs are $120 per day. a) Draw the network diagram by using AON method b) Calculate the normal duration and Normal project cost c) Least-cost and optimum point/durations for the project. d) Show the relationship between time and cost Graphically. Activity Preceded Duration (days) Cost (Birr) by Normal Crash Normal Crash A 5 4 500 600 B A 7 350 500 A 8. 5 800 920 D A 11 7 1200 1400 B,C 6. 4 600 700 F C 4 4 500 500 G D,F 7 700 1000 E,F 300 420

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Show all steps
2. Assume the following project data given in Table 2. It is required to crash the
project duration from its original duration. Assume Indirect (overhead) costs are $120
per day.
a) Draw the network diagram by using AON method
b) Calculate the normal duration and Normal project cost
c) Least-cost and optimum point/durations for the project.
d) Show the relationship between time and cost Graphically.
Activity Preceded Duration (days) Cost (Birr)
by
Normal Crash
Normal Crash
A
5
4
500
600
B
A
7
350
500
C
A
8
800
920
D
A
11
7
1200
1400
E
B,C
6.
4
600
700
F
C
4
4
500
500
G
D,F
7
700
1000
H
E,F
6.
300
420
Transcribed Image Text:2. Assume the following project data given in Table 2. It is required to crash the project duration from its original duration. Assume Indirect (overhead) costs are $120 per day. a) Draw the network diagram by using AON method b) Calculate the normal duration and Normal project cost c) Least-cost and optimum point/durations for the project. d) Show the relationship between time and cost Graphically. Activity Preceded Duration (days) Cost (Birr) by Normal Crash Normal Crash A 5 4 500 600 B A 7 350 500 C A 8 800 920 D A 11 7 1200 1400 E B,C 6. 4 600 700 F C 4 4 500 500 G D,F 7 700 1000 H E,F 6. 300 420
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Knowledge Booster
Organizational strategy
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.