6- The total grace period (TF) for events is
Q: A plumber has decided to use the techniques of project management in order to plan a job. He knew…
A: The critical path method in project management is the longest set of activities that must be…
Q: Define the term Slack-Time?
A: Project management can be termed as the application of knowledge, techniques, tools, skills, and…
Q: example of cost control for project
A: Cost Control A tool which is used by the organization’s management in controlling and regulating the…
Q: Discussion on reasons of lowering productivity Conclusion In PROJECT MANAGEMENT
A: Productivity is defined as the ratio between the output volume and the volume of inputs. It measures…
Q: What is the critical path
A: A critical path is a path which indicating the highest duration from all available paths. A critical…
Q: The following represents a project with known activity times. All times are in weeks. Activity…
A: Given that: Activity Immediate Predecessors Duration A - 4 B - 3 C A 2 D B 7 E C, D 4…
Q: Explain phase-to-phase relationships in a typical project lifecycle...
A: ANSWER IS AS BELOW:
Q: i. What is the project completion date? ii. What is the total cost required for completing this…
A: Total cost is the cost that includes fixed cost and variable cost of goods and services.
Q: 2- Find the completion time (TE).
A: TE stands for the expected duration. It means the expected time duration that each activity will…
Q: activity predecessor optimistic time(days) Most likely time(days) Pessimistic time(days) A - 4 8 24…
A: Find the Given details below: Activity Predecessors Optimistic Time(To) a(Days) Pessimistic…
Q: Q1- The schedule for one of the projects was as in Table No. (1), answer the following- 1- Draw the…
A: Below is the solution:-
Q: a) Prepare a PERT network diagram to aid the coordination of the activities. Calculation of…
A: a.PERT DIAGRAM:
Q: Explain : Activity time, Gantt chart, Critical path, Slack time, Crashing.
A: PART A: - Activity period may be a noun that represents the particular amount of your time that…
Q: Question 37 How much slack is there in task A? Your Answer: Your Answer Question 38 If the crash…
A: Slack is the available time in a activity for delaying the project without affecting the total…
Q: The FWO has just made the winning bid of 54 million Rs. to construct a new Building. Company has…
A: Master Working Sheet as mentioned-
Q: What is the relationship between the earliest start time (EST) of an activity and the earliest…
A: EST is early start time. It refers to earliest possible time to start an activity. ECT is early…
Q: d. How long the program is expected to finish? e. Determine the slack time for each activity using…
A: given,
Q: 7-Partial grace period (FF) for events is
A:
Q: SESSION 2: Tutorial Homework Activity Duration Additional Information (days) The project starts with…
A: 1. Activity Immediate Predecessors Duration A - 5 B A 3 C - 1 D…
Q: Consider the project crashing information presented in Figure 8-4. What is the cost to complete this…
A: Project duration is the total time taken to complete the project successfully measurable in days or…
Q: The FWO has just made the winning bid of 54 million Rs. to construct a new Building. Company has…
A: Note: - Since we can answer only up to 3 subparts we will answer 1, 2, and 3 for your question.…
Q: Table 7.8 contains data for the installation of new equipment in a manufacturing process at Excello…
A:
Q: How does the Work Breakdown Structure differ from the project network?
A: Work Breakdown structure is the clear breakdown of the entire working processes of the project into…
Q: days. Carl's team should be able to complete the project in
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: Time Task Precedence Tasks Task (sec (s ЕЗ D6 D7 D8 J2 D9 J3 C1 K4, K9 K9, J1 B3 B5 J2 B7 25
A: Calculate the cycle time based on the goal is to produce 1000 bicycles per standard 40hour week…
Q: a. Find the critical path.
A: A network diagram is a visual representation of a project which identifying the activity…
Q: Using the beta distribution rule, what is your estimated duration for activity A in days? Round your…
A: Given, Optimistic production rate per crew: 21 sf/hour Most likely production rate per crew: 17…
Q: Part 1: For the activities, duration, and sequence shown in the table below, prepare a Gantt chart…
A: A Gantt chart is a project management device that illustrates a project plan. It typically includes…
Q: Activity Normal_time Crash_time Normal_cost Crash_cost Slack A. 31 17 4800 6200 B 14 14 5500 5500 34…
A: Given- Activity Name Normal Time Crash Time Normal Cost Crash Cost SLACK A 31 17 4800 6200 0…
Q: Question 3: The following bar chart shows the activities to complete a project in 6 months (each…
A: Planned value (PV), Earned value (EV) and Actual costs are different values which helps to identify…
Q: What is the significance of the critical path?
A: The critical path method often called CPM is nothing but the assets utilization algorithm for…
Q: a. Draw a precedence diagram using AOA , AON and Gantt chart. b. Find the critical path using CPM.…
A: Below is the solution:-
Q: 3- The value of the variance of the critical path in the project is
A: Variance = square of sum standard deviations of critical activities Standard deviation = (b-a)/6
Q: No. Activity Duration Successor Relationship Lag (week) (week) В, С, D A-B (S-S) A-C (F-S) A-D (F-S)…
A: The question is related to Crtical Path. The Path having the longest duration is the Criticial Path.…
Q: Why might a person wish to be involved with a critical path activity? What are some of the…
A: A critical path activity is an activity that is deciding the duration of the project It is…
Q: Task ID Task Predecessor Original Duration Original Cost Crashed Duration Crashed Cost 1 2…
A: Find the Given details below: Task ID Activity Predecessor Original duration (NT) (Days) Original…
Q: Create Gantt chart and estimate critical path
A: Below is the solution:-
Q: Power Builders Inc. is planning for an upcoming job with a large client. They have listed the…
A: Given data is
Q: partment Transportati project section of interstate highway near Wahington, DC. The project includes…
A: Project scheduling with uncertain activity times (Optimistic, Most likely, Pessimistic) a - 1 2 2…
Q: Task ID Duration Dependency A 3 B 14 C.F A 2
A: Activity Immediate Predecessors Duration A - 3 B A 4 C B 3 D C,F 5 E A 6 F E 2
Q: Question 2…
A: We know in Project Management, Variance may be a measure of a deviation from the projected value.…
Q: Question 30 State the duration of the critical path.
A: A project network diagram displays the sequential and analytical connection between tasks in a…
Q: What would a project manager have to do to crash an activity?
A: Project crashing is the point at which you abbreviate the term of a venture by diminishing the hour…
Q: (i) The backward pass in project network calculations determines the A. Latest time's activities can…
A: network diagram helps in scheduling the activities of project management. It helps in analysing the…
Step by step
Solved in 4 steps with 3 images
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity D. Activity B is connected to activity E. Activity C is connected to activity F. Activity D is…[Project Management] Because a housing project is running late, the developer will need to complete and deliver the houses as quickly as possible. You and your management team are responsible for mitigating the situation by including a time-cost trade-off analysis into the project. You will need to include the following: Normal crash Activity Prior Days cost, RM Days cost, RM A 7,000 7,000 B A 8,000 9 8,000 B 14 6,000 12 11,000 D B 18 5,000 11 8,500 E C,D 12 8,000 12 8,000 E 20 6,000 16 12,000 E 7,000 7,000 E 11 11,000 7 15,000 G, H 10 15,000 21,000 7 I, F 6 9,000 6 9,000 Construct a network diagram (PDM), including activity early start, late start, early finish, late finish and float.Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a). Develop a project network. (b) Develop an activity schedule. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F (c) What are the critical activities? (Enter your answers as…
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity C. Activity B is connected to activity E. Activity C is connected to activity D. Activity D is…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop an activity schedule. What are the critical activities? (Enter your answers as a comma-separated list.) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (d) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost? (A, B, C, D, E) = (e) Develop an activity schedule for the crashed project. Activity EarliestStart LatestStart…
- B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4Problem Statement: Project Control and Monitoring You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project. Required: Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?How to Plan, direct and coordinate IT projects to ensure effectiveproject control including scope changes and project risks?
- Q6:write briefly but relevant answer a) PERT and CPM b) Risk Management and its types.Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost 1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks. Show breakdown of workOpp l +O 90% 10:31 33,19 K/s UNIVERSITY OF GHANA 35 Part 1 of 1- Question 1 of 100 . refers to how the project is expected to work and solve the stated problem in project or proposal writing. A. Project Portfolio B. Portfolio of Activities C. Plan of Activities D. Project Activities Reset Selection [1] Question Progress