5. New York Building Corporation uses the critical path method to monitor construction jobs. The company is currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty. Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal completion time of 22 weeks. The following activities can be crashed. Activities BC DE EF Cost to Crash 1 Week P.8.000 10,000 8,800 Cost to Crash 2 Weeks P15,000 19,600 19,500 REQUIRED: a New York Building desires to reduce the normal completion time Job # 181 and, at the same time, report the highest possible income for the year. New York Building should crash c. Activity EF 2 weeks a. Activity BC 1 week and activity EF 1 week b. Activity DE 1 week and activity BC 1 week d. Activity DE 1 week and activity EF 1 week b. Compute for the cost to crash of the activities.

Elements Of Electromagnetics
7th Edition
ISBN:9780190698614
Author:Sadiku, Matthew N. O.
Publisher:Sadiku, Matthew N. O.
ChapterMA: Math Assessment
Section: Chapter Questions
Problem 1.1MA
icon
Related questions
Question

New York Building Corporation uses the critical path method to monitor construction jobs. The company is currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty.

Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal completion time of 22 weeks. The following activities can be crashed.

 

             Activities                         Cost to Crash 1 Week                 Cost to Crash 2 Weeks

                   BC                                     P  8,000                                          P15,000

                   DE                                       10,000                                            19,600

                   EF                                         8,800                                             19,500

 

      REQUIRED:

1. New York Building desires to reduce the normal completion time Job #181 and, at the same time, report the highest possible income for the year. New York Building should crash

a. Activity BC 1 week and activity EF 1 week

b. Activity DE 1 week and activity BC 1 week

c. Activity EF 2 weeks

d. Activity DE 1 week and activity EF 1 week

       

2. Compute for the cost to crash of the activities.

5. New York Building Corporation uses the critical path method to monitor construction jobs. The company is
currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty.
Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal
completion time of 22 weeks. The following activities can be crashed.
Activities
Cost to Crash 1 Week
Cost to Crash 2 Weeks
P 8.000
10,000
8,800
BC
P15,000
19,600
19,500
DE
EF
REQUIRED:
a New York Building desires to reduce the normal completion time Job #181 and, at the same time, report
the highest possible income for the year. New York Building should crash
a. Activity BC 1 week and activity EF 1 week
b. Activity DE 1 week and activity BC 1 week
c. Activity EF 2 weeks
d. Activity DE 1 week and activity EF 1 week
b. Compute for the cost to crash of the activities.
Transcribed Image Text:5. New York Building Corporation uses the critical path method to monitor construction jobs. The company is currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty. Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal completion time of 22 weeks. The following activities can be crashed. Activities Cost to Crash 1 Week Cost to Crash 2 Weeks P 8.000 10,000 8,800 BC P15,000 19,600 19,500 DE EF REQUIRED: a New York Building desires to reduce the normal completion time Job #181 and, at the same time, report the highest possible income for the year. New York Building should crash a. Activity BC 1 week and activity EF 1 week b. Activity DE 1 week and activity BC 1 week c. Activity EF 2 weeks d. Activity DE 1 week and activity EF 1 week b. Compute for the cost to crash of the activities.
Expert Solution
steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Knowledge Booster
Project Management Techniques
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Elements Of Electromagnetics
Elements Of Electromagnetics
Mechanical Engineering
ISBN:
9780190698614
Author:
Sadiku, Matthew N. O.
Publisher:
Oxford University Press
Mechanics of Materials (10th Edition)
Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:
9780134319650
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Thermodynamics: An Engineering Approach
Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:
9781259822674
Author:
Yunus A. Cengel Dr., Michael A. Boles
Publisher:
McGraw-Hill Education
Control Systems Engineering
Control Systems Engineering
Mechanical Engineering
ISBN:
9781118170519
Author:
Norman S. Nise
Publisher:
WILEY
Mechanics of Materials (MindTap Course List)
Mechanics of Materials (MindTap Course List)
Mechanical Engineering
ISBN:
9781337093347
Author:
Barry J. Goodno, James M. Gere
Publisher:
Cengage Learning
Engineering Mechanics: Statics
Engineering Mechanics: Statics
Mechanical Engineering
ISBN:
9781118807330
Author:
James L. Meriam, L. G. Kraige, J. N. Bolton
Publisher:
WILEY