13.39 Activity A is worth $500, is complete, and actually cost $500. Activity B is worth $1.000, is 50% complete, and has actually cost $700 so far. Activity C is worth $100, is 75% complete, and has actually cost $90 so far. What is the total earned value for the project?
Q: Task 3: 100 trailers of a specific model are required by Sask Trailers to meet the demand at the beg...
A: A Small Introduction about Requirement Plan A prerequisite: the board plan is an archive that is no...
Q: Kent State University students services department is concerned about the lack of healthy food optio...
A: given, 650 bar per week allocate 3workers for 7.5 hr each
Q: A plant has four operators to be assigned to four machines. The time (minutes) required by each work...
A: When workers are assigned to certain duties based on cost, the Hungarian algorithm is beneficial for...
Q: Togo makes riding lawn mowers and tractors. The company's expected quarterly demand is given below i...
A: Given- Production cost per unit = $210Inventory carrying cost = $30Hiring cost per worker = $400Fi...
Q: What role does collaborative forecasting play in a supply chain of a build to order manufacturer suc...
A: The bullwhip effect in businesses disturb the supply chain at many production and operational level...
Q: When crashing a project, the general guideline is to concentrate on the path with? a. The least expe...
A: A project crashing is the process of reducing the total duration of the project completion based on ...
Q: Please outline or bold the answer
A: X1 = Number of one person boats X2 = Number of two persons boats X3 = Number of four-person boats
Q: A manufacturer's average WIP inventory for Part #2934 is 900 parts. The workstation produces parts a...
A: Little's law states lead time (aka flow time) = Work in progress / Thorughput this can also be wri...
Q: Demonstrate how concentration at work gives the dynamic leader power and passion to succeed.
A: Strong leadership is when individual can inspire, motivate, inspire & challenge the team to prod...
Q: Given the Exponential Smoothing Method, Actual Demand alpha = .25 and Forecast Demand alpha = 0.75, ...
A: The formula for forecast using the exponential smoothening method.
Q: a. Use the sales forecaster's prediction to describe a normal probability distribution that can be u...
A: Note: As per the Bartleby guidelines, only the first three parts have been answered.
Q: The XYZ Company produces small plastic toys in its Burbuli manufacturing plant. The company is curre...
A: Information given hereTotal units attempted=6000000Goods unit manufactured=4800000Processing time=80...
Q: You've just been appointed as the new regional manager at a supermarket, and your first task is to d...
A: Inventory cost comprises the amount to order and holds stock or inventory, along with governing of t...
Q: List & define the steps in the new product development process and the major considerations in manag...
A: A Small Introduction about Product Development Item improvement alludes to the total course of ta...
Q: The standard time fixed for the worker is 20 hours to complete a job. If a worker completes the job ...
A: Given data The standard time fixed for employees = 20 hours Time taken by a worker in job completi...
Q: 1) Who are/is the responsible decision makers? 2) What are the rights of the skatemakers? 3) What...
A: The legal issues that occur when companies monitor their workers' activities are covered under workp...
Q: Activity Duration(days) Construct the network and find critical path. 1-2 1-3 2-4 3-4 3-5 4-9 5-6 5-...
A: A project network diagram is formed with the help of boxes and arrows. It shows the analytical relat...
Q: What is Project Closure?
A: Project closure is the last phase of the project management lifecycle. In this phase, all the activi...
Q: Explain what a SWOT analysis is and what it isn't.
A: SWOT analysis is an analytical technique to determine strengths, weaknesses, opportunities, and thre...
Q: Problem 2: A large aerospace manufacturer is planning to propose a sophisticated drone for induction...
A: Based on the time estimate and the predecessor relationships given, we prepare a project network dia...
Q: Please try to solve in 30 minute Electricians are trained in a process with two resources. The first...
A: Given, Capacity of first resource = 0.026 per hour Number of workers for first resource = 2 Capacity...
Q: Item SKU A3378 has a demand that is normally distributed during the lead time, with a mean of 360 un...
A: ITEM SKUA3378 Average demand during lead time, μ=360 Standard deviation during lead time, σ =12 Prob...
Q: Question 1 B A company produces 2 (two) different grades of gasoline – regular and premium from 3(t...
A: Table 1: Table 2:
Q: A campus deli serves 300 customers over its busy lunch period from 11:30 am to 1:30 pm. A quick coun...
A: A queuing system refers to the system that has service facility where the customers arrive for servi...
Q: The obverse of “Some brands of gin are not suitable for making martinis” is: a. Some brands of gin ...
A: obverse is the opposite of some thing. That means a word that has an exact opposite meaning of anoth...
Q: The operations manager using a combination of methods has forecast sales of Lomi Cup Orders at the l...
A: Given data is
Q: ve money a
A: Small companies and startups typically cut corners because of expenses, but customer relationship ma...
Q: (a) What is Agency Theory? (b) Pros & Cons of Agency Theory (c) Importance of Agency Theory
A: Note - Hi! Thank you for the question, As per the honour code, we are allowed to answer three sub-pa...
Q: (c) A company manufactures two products: X and Y. Product X costs $8 per unit and contains 2 units o...
A: Objective Functions and Constraints: Based on the given details, the objective funct...
Q: List and discuss potential supply chain modeling pitfalls to avoid.
A: The supply chain is the system in which people, resources, equipment, processes, and other factors a...
Q: Strategic Planning process, CEO wants to assign the budget to each business function for functional ...
A: A Small Introduction about Planning Process Arranging includes choosing missions and targets and ...
Q: The Department and Board may remove a license limitation as soon as the next license cycle begins. i...
A: A person who has had a limitation placed on a license, a certificate of registration, or the renewal...
Q: АСTIVITY PREDECESSOR DURATION (days) A1 3 A2 A1 4 АЗ A1 A4 A2 5 A5 АЗ 1 Аб АЗ 2 A7 A4,A5 Аб,А7 4 A8 ...
A: Find the Given details below: Activity Predecessor Duration(Days) A1 - 3 A2 A1 4 A3 A1 2 ...
Q: a) b) c) d) e) f) g) h) i) What is the optimal solution (in words? An additional 4 hours of shaper t...
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(a, b, ...
Q: Alabama llc collected sales dara for four months, janurary through april. the data is janurary-17, f...
A: Note- Hi! Thank you for the question As per the honour code, We’ll answer the first question since t...
Q: To illustrate these different approaches to Production Planning, identify to most appropriate Produc...
A: The manufacturing sector has gotten more competitive as the range and variety of goods and services ...
Q: Describe the factors influencing effective capacity.
A: Facilities, product and service, process, people, policy, operational, supply chain, and external va...
Q: You have just started a project for a manufacturer. Project team members report they are 30 percent ...
A: Earned value (EV) is indicating the value of actually completed work according to the date of measur...
Q: current year. Formulate an LP model whose solution will tell John how to maximize the total profit f...
A: Here, first I would formulate the LP, then I would solve this LP using the Ms Excel solver tool, In...
Q: Given the Exponential Smoothing Method, Actual Demand alpha = .25 and Forecast Demand alpha = 0.75, ...
A: Forecasting is a method that uses past data as inputs to make informed estimations that are predicti...
Q: In operations management logistics does past performance guarantee future performance?
A: Operations management is the management in which the production process is controlled and designed s...
Q: What is a cost baseline in project management? How can it be applied to monitor and control a projec...
A: When a project is initiated there are some basic factors that are predefined like scope, budget, and...
Q: Supervisor Kenneth Peterson wants to determine the percent of time a machine in his area is idle. He...
A: The detailed solution of this question is given in Step 2.
Q: How is lean ux used in continuous exploration?
A: In the process of continuous exploration, we would put major emphasis on understanding the needs and...
Q: Callers are helped in a process with two resources. The first resource has a capacity of 1.7 callers...
A: Given, First resource capacity = 1.7 callers per minute Number of workers for first resource = 1 wor...
Q: 1- What may be the main factors considered in such layout from your study of layout principles 2- I...
A: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and s...
Q: A schematic technique to discover possible causes of quality problems in an overall process is a: O ...
A: Quality is the ability to manufacture the products and services as set standards and increase custom...
Q: Soledad Bautista, the engineering manager, delegates tasks as a good manager should. However, Mark ...
A: given, Soledad Bautista, the engineering manager,delegates tasks as a good manager should. However,...
Q: Identifies the common Production Planning methods that companies can use to control purchasing, manu...
A: Production planning is described as the process of developing a guide through which a service or a p...
Q: Solve the questions: Tony and his team identified some risks during the first month of the Recreatio...
A: given, : Tony and his team identified some risks during the first month of the Recreation and Wellne...
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
- 13.42 Activity A is worth $100, is complete, and actually cost $150 Activity B is worth $500, is 75% complete, and has actually cost $400 so far Activity C is worth $500, is 25% complete, and has actually cost $200 so far. What is the estimated cost to completion for the project?please help, project management 1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach? Make sure to document any cited references.please help, project management 1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach?
- Given the following information for a one-year project, answer the following questions. Recall that PVis the planned value, EV is the earned value, AC is the actual cost, and BAC is budget at completion.PV = $22,000EV = $20,000AC = $25,000BAC = $120,000a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performanceindex (SPI) for the projectb. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or overbudget?c. Use the CPI to calculate at estimate at completion (EAC) for this project. Is the project performingbetter or worse than planned?d. Use the SPI to estimate how long it will take to finish this project.e. Sketch the earned value chart for this project.Explain the following project situations using just the following schedule and cost information: a. PV = $10,000, AC = $12,000, EV = $10,500b. PV = $10,000, AC = $10,000, EV = $10,000c. PV = $10,000, AC = $9,000, EV = $10,000a. PV = $10,000, AC = $10,000, EV = $9,000given the following information for a 1-year project, answer the following questions. Assume you have actual and earned value data at the end of the second month. Recall that PV is the plan value, Evie is the earned value, AC is the actual cost, and BAC is the budget at completion.pv =$ 23,000ev = 20,000ac= 25,000bac = 130,000a. what is the cost variance, schedule variance, cost performance index CPI and schedule performance index SPI for the project?B. how is the project progressing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?C. use the CPI to calculate the estimate at completion EAC for this project.d. use the SPI to estimate how long it will take to finish this project.e. sketch the earned value chart for this project, use the figure below as a guide. Assume the data for month one is half of the values given for Pv, Ev and ac at the end of month 2
- A project with total budget cost of 30 cr. is scheduled to be completed in 80 weeks. A periodic review was carried out at end of 60 weeks and results are as given: Budgeted cost of work performed = 17 cr. Actual Cost of work performed = 19 cr. Budgeted cost of work scheduled = 21 cr. What is the cost performance index? A.0.895 B.0.81 C.0.90 D.1.12A project is set to be completed in 12 months with an estimated budget cost of $520,000. 6 months have passed, and expenses were $240,000. The completion of work is set to be $270,000 What is the planned value PV of the project? What is the actual cost AC of the project? What is the earned value EV of the project? Find the SPI and CPI of the project. Is the project ahead or behind schedule? Is the project under or over budget? What is the estimated cost to complete the project?After the first month of a project, the Actual Cost was $400 and the planned cost for the first month was $500. Currently, only 50% of the work have been completed. Based on this information, calculate the following: a.Cost Performance Index b.
- Project Typhoon has a net present value of $10,000 and a profitability index of 1.01. Project Cyclone has a net present value of $10,000 and a profitability index of 1.10. Project SurfsUp has a net present value of $10,000 and a profitability index of 1.05. If only one project could be undertaken, what should the oraganiztion select?After the first month of a project, the Actual Cost was $400 and the planned cost for the first month was $500. Currently, only 50% of the work have been completed. Based on this information, calculate the following: a.Cost Performance Index b.Estimate to Complete c.Estimate at CompletionAfter the first month of a project, the Actual Cost was $400 and the planned cost for the first month was $500. Currently, only 50% of the work have been completed. Based on this information, calculate the following: a.Earned Value b.Cost Variance c.Schedule Variance