Your options for shipping $96,970 of machine parts from Baltimore to Kuala Lumpur, Malaysia, are (1) use a ship that will take 32 days at a cost of $3,370, or (2) truck the parts to Los Angeles an then ship at a total cost of $5,180. The second option will take only 20 days. You are paid via a letter of credit the day the parts arrive. Your holding cost is estimated at 30% of the value per year. If you have a third option and it costs only $4,440 and also takes 20 days, what is your most economical plan? The daily holding cost of Alternative 1 is $ 79.70. (Enter your response rounded to two decimal places.) The daily cost of faster shipping with Alternative 2 is $ 150.83. (Enter your response rounded to two decimal places.) The daily cost of faster shipping with Alternative 3 is $ (Enter your response rounded to two decimal places.)

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Chapter16: Lean Supply Chain Management
Section: Chapter Questions
Problem 10DQ: The chapter presented various approaches for the control of inventory investment. Discuss three...
icon
Related questions
Question
Your options for shipping $96,970 of machine parts from Baltimore to Kuala Lumpur, Malaysia, are (1) use a ship that will take 32 days at a cost of $3,370, or (2) truck the parts to Los Angeles and
then ship at a total cost of $5,180. The second option will take only 20 days. You are paid via a letter of credit the day the parts arrive. Your holding cost is estimated at 30% of the value per year.
If you have a third option and it costs only $4,440 and also takes 20 days, what is your most economical plan?
The daily holding cost of Alternative 1 is $ 79.70 . (Enter your response rounded to two decimal places.)
The daily cost of faster shipping with Alternative 2 is $ 150.83. (Enter your response rounded to two decimal places.)
The daily cost of faster shipping with Alternative 3 is $
(Enter your response rounded to two decimal places.)
Transcribed Image Text:Your options for shipping $96,970 of machine parts from Baltimore to Kuala Lumpur, Malaysia, are (1) use a ship that will take 32 days at a cost of $3,370, or (2) truck the parts to Los Angeles and then ship at a total cost of $5,180. The second option will take only 20 days. You are paid via a letter of credit the day the parts arrive. Your holding cost is estimated at 30% of the value per year. If you have a third option and it costs only $4,440 and also takes 20 days, what is your most economical plan? The daily holding cost of Alternative 1 is $ 79.70 . (Enter your response rounded to two decimal places.) The daily cost of faster shipping with Alternative 2 is $ 150.83. (Enter your response rounded to two decimal places.) The daily cost of faster shipping with Alternative 3 is $ (Enter your response rounded to two decimal places.)
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning