With the data attached: 1. Draw a project network. 2. What is the critical path 3. What is the normal project cost? 4. What would be the total cost of this project if need to crash it by 1 week?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
With the data attached: 1. Draw a project network. 2. What is the critical path 3. What is the normal project cost? 4. What would be the total cost of this project if need to crash it by 1 week?
Activity
A
B
C
D
E
F
G
H
I
Predecessor(s)
---
A
A
--
B,D,C
D
D
E
F,G,H
Normal Time
(Wks)
5
8
7
6
8
3
3
4
6
Crash Time (Wks)
4
6
6
5
6
2
2
3
5
Normal Cost
$400
1600
800
600
1200
800
500
400
900
C
Crash Cost
$750
2200
1100
1000
2200
1000
650
600
1300
I
ZOOM
Transcribed Image Text:Activity A B C D E F G H I Predecessor(s) --- A A -- B,D,C D D E F,G,H Normal Time (Wks) 5 8 7 6 8 3 3 4 6 Crash Time (Wks) 4 6 6 5 6 2 2 3 5 Normal Cost $400 1600 800 600 1200 800 500 400 900 C Crash Cost $750 2200 1100 1000 2200 1000 650 600 1300 I ZOOM
Expert Solution
Step 1

The critical path can be defined as the longest path in the project and should be completed for the project to be completed and Normal Duration and Cost mean the amount of absolute cost of the normal duration activities in the project changed by the year in accordance with the appropriate penalty or reward associated with the completion of the project.

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.