Wally's Widget Warehouse takes orders from 7 A.M. to 7 PM. The manager wants to analyze the process and has provided the following process flow diagram. There are three steps required to ship a customer order. The first step is to take the order from a customer. The second step is to pick the order for the customer, and then they have to pack the order to ready it for shipping. The order-taking step works at a maximum rate of 110 customer orders per hour. Order picking works at a maximum of 80 per hour, and packing works at 75 per hour. Customery Picked Pick Orden HAVY Onders Onder Taker 110 Customer/ Customer Orden 80 Customers hour Pack units per day Onders 75 Customers/ hour Wilt for Shippy Wally wants to figure out the following a. What is the current maximum daily output of the process assuming that no one works overtime? (.e., meaning all three operations work a 12-hour shift) Current maximum output

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
Wally's Widget Warehouse takes orders from 7 A.M. to 7 PM. The manager wants to analyze the process and has provided the
following process flow diagram. There are three steps required to ship a customer order. The first step is to take the order from a
customer. The second step is to pick the order for the customer, and then they have to pack the order to ready it for shipping. The
order-taking step works at a maximum rate of 110 customer orders per hour. Order picking works at a maximum of 80 per hour, and
packing works at 75 per hour.
Customery
Order
Taker
110 Customers/
hour
Customer
Orden
Current maximum output
Pick
Orders
80 Customer
hour
Picked
Orden
units per day
Pack
Orders
75 Customers
hour
Wally wants to figure out the following.
a. What is the current maximum daily output of the process assuming that no one works overtime? (.e., meaning all three operations
work a 12-hour shift)
Wait for
Shippe
Transcribed Image Text:Wally's Widget Warehouse takes orders from 7 A.M. to 7 PM. The manager wants to analyze the process and has provided the following process flow diagram. There are three steps required to ship a customer order. The first step is to take the order from a customer. The second step is to pick the order for the customer, and then they have to pack the order to ready it for shipping. The order-taking step works at a maximum rate of 110 customer orders per hour. Order picking works at a maximum of 80 per hour, and packing works at 75 per hour. Customery Order Taker 110 Customers/ hour Customer Orden Current maximum output Pick Orders 80 Customer hour Picked Orden units per day Pack Orders 75 Customers hour Wally wants to figure out the following. a. What is the current maximum daily output of the process assuming that no one works overtime? (.e., meaning all three operations work a 12-hour shift) Wait for Shippe
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,