Use the following scenario and data for all questions The following is the Bill of Material (BOM) of a simple product. E(2) Item A B D(2) с CDEFO B(2) G G(1) E(4) Assume the firm has made a commitment to ship 200 units of the final product (A) to one of its customers in the 9th week. Based on the partial information given in the following table, complete the material requirement planning for this order. Lead Time (Week) 2 The correct MRP table for item A should be E(2) On Hand 0 0 50 100 200 250 0 C(4) E(3) E(2) G(2) Scheduled Receipt No 100 in week 1 50 in week 2 No No 200 in week 3 No

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
What is the correct MRP table for item A through G (respectively)?
 
QUESTION 1
Use the following scenario and data for all questions
The following is the Bill of Material (BOM) of a simple product.
E(2)
D(2)
B(2)
Item
A
B
с
D
E
F
G
G(1)
E(4)
Lead Time
(Week)
2
3
2
2
1
3
Assume the firm has made a commitment to ship 200 units of the final product (A) to one of its customers in the 9th week. Based on the partial
information given in the following table, complete the material requirement planning for this order.
The correct MRP table for item A should be
E(2)
On Hand
0
0
50
100
200
250
0
C(4)
E(3)
F(2)
G(2)
Scheduled Receipt
No
100 in week 1
50 in week 2
No
No
200 in week 3
No
Click Save and Submit to save and submit. Click Save All Answers to save all answers.
Save All Answers
Transcribed Image Text:QUESTION 1 Use the following scenario and data for all questions The following is the Bill of Material (BOM) of a simple product. E(2) D(2) B(2) Item A B с D E F G G(1) E(4) Lead Time (Week) 2 3 2 2 1 3 Assume the firm has made a commitment to ship 200 units of the final product (A) to one of its customers in the 9th week. Based on the partial information given in the following table, complete the material requirement planning for this order. The correct MRP table for item A should be E(2) On Hand 0 0 50 100 200 250 0 C(4) E(3) F(2) G(2) Scheduled Receipt No 100 in week 1 50 in week 2 No No 200 in week 3 No Click Save and Submit to save and submit. Click Save All Answers to save all answers. Save All Answers
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 7 steps with 11 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.