Thrasher Construction Co. was contracted to construct a building for $1,045,000. The building is owned by the customer throughout the contract period. The contract provides for progress payments. Thrasher's accounting year ends 31 December. Work began under the contract on 1 July 20X5, and was completed on 30 September 20X7. Construction activities are summarized below by year: 20x5 Construction costs incurred during the year, $192,600; estimated costs to complete, $674,100; progress billings during the year, $163,500; and collections, $149,800. 20x6 Construction costs incurred during the year, $481,500; estimated costs to complete, $203,300; progress billing during the year, $409,100; and collections, $406,600. 20X7 Construction costs incurred during the year, $209,000. Because the contract was completed, the remaining balance was billed and later collected in full per the contract. Required: 1. Prepare Thrasher's journal entries to record these events. Assume that percentage of completion is measured by the ratio of costs incurred to date divided by total estimated construction costs. (If no entry is required for a transaction/event, select "No journal entry required" in the first account field. Do not round intermediate calculations. Round your final answers to the nearest whole dollar.) View transaction list Journal entry worksheet 1 2 3 4 5 Record the construction costs incurred. >

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 18RE
icon
Related questions
Question

Ab. 129.

Thrasher Construction Co. was contracted to construct a building for $1,045,000. The building is owned by the customer throughout
the contract period. The contract provides for progress payments. Thrasher's accounting year ends 31 December. Work began under
the contract on 1 July 20X5, and was completed on 30 September 20X7. Construction activities are summarized below by year:
$674,100; progress
20x6 Construction costs
20x5 Construction costs incurred during the year, $192,600; estimated costs to complete,
billings during the year, $163,500; and collections, $149,800.
incurred during the year, $481,500; estimated costs to complete,
$203,300; progress billing during the year, $409,100; and collections, $406,600.
20X7 Construction costs incurred during the year, $209,000. Because the contract was
completed, the remaining balance was billed and later collected in full per the
contract.
Required:
1. Prepare Thrasher's journal entries to record these events. Assume that percentage of completion is measured by the ratio of costs
incurred to date divided by total estimated construction costs. (If no entry is required for a transaction/event, select "No journal
entry required" in the first account field. Do not round intermediate calculations. Round your final answers to the nearest whole
dollar.)
View transaction list
Journal entry worksheet
<
1
2
3
Date
20X5
Note: Enter debits before credits.
Record the construction costs incurred.
4
5
Statement of Financial Position:
Current assets:
Accounts receivable
Contract asset
Income Statement:
Income on construction (net)
General Journal
Debit
2. Provide the balances that would be shown on the SCI and SFP for this contract for each year. (Do not round intermediate
calculations. Round your final answers to the nearest whole dollar.)
20X5
Credit
20X6
>
20X7
Transcribed Image Text:Thrasher Construction Co. was contracted to construct a building for $1,045,000. The building is owned by the customer throughout the contract period. The contract provides for progress payments. Thrasher's accounting year ends 31 December. Work began under the contract on 1 July 20X5, and was completed on 30 September 20X7. Construction activities are summarized below by year: $674,100; progress 20x6 Construction costs 20x5 Construction costs incurred during the year, $192,600; estimated costs to complete, billings during the year, $163,500; and collections, $149,800. incurred during the year, $481,500; estimated costs to complete, $203,300; progress billing during the year, $409,100; and collections, $406,600. 20X7 Construction costs incurred during the year, $209,000. Because the contract was completed, the remaining balance was billed and later collected in full per the contract. Required: 1. Prepare Thrasher's journal entries to record these events. Assume that percentage of completion is measured by the ratio of costs incurred to date divided by total estimated construction costs. (If no entry is required for a transaction/event, select "No journal entry required" in the first account field. Do not round intermediate calculations. Round your final answers to the nearest whole dollar.) View transaction list Journal entry worksheet < 1 2 3 Date 20X5 Note: Enter debits before credits. Record the construction costs incurred. 4 5 Statement of Financial Position: Current assets: Accounts receivable Contract asset Income Statement: Income on construction (net) General Journal Debit 2. Provide the balances that would be shown on the SCI and SFP for this contract for each year. (Do not round intermediate calculations. Round your final answers to the nearest whole dollar.) 20X5 Credit 20X6 > 20X7
Expert Solution
steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Revenue Recognition
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage