The table below shows a schedule. Activity Duration Predecessor Cost of crashing Max. days it can be crashed (per day) A 7 200 B A 100 8 B 220 D 9. 300 3 5 500 F 4 D. E 100 Calculate the cost of crashing the schedule by 4 days 2. 2. 3. C. 9,
Q: Q1) The project schedule has the following characteristics: Activity Time (weeks) Activity…
A: Given information, Activity Predecessors Durations A 10 B 7 C B 5 D B 6 E A 9…
Q: 4. Schedules and activities of a project are shown below. Answer the questions. Activity…
A: A) The CPM chart is as follows: The critical path is: A-D-E-H-I-L
Q: For the small project with the relationships shown below. Activity IPA's Duration (Day) A 5 B 7 4 D…
A: An activity-on-node diagram is a visual representation of the network of an entire project schedule.…
Q: Conduct a forward and backwards pass for the activity network diagram that you have constructed…
A: THE ANSWER IS AS BELOW:
Q: Optical Disk Preinstallation Project 18. The optical disk project team has started gathering the…
A: Given data, Activity Description Duration Predecessor 1 Define Scope 6 None 2 Define…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Note: - As we can answer only three subparts, the first three(a, b, and c) will be answered. If…
Q: (9):- A construction project of (61), the operations that occur in the construction sequence are…
A: Given information, Activity Depend on Duration (D) Rate A 4 6 B 2 10 C A & B 2…
Q: 01) The utility data for a network are given below: Activity Duration (Days) 0-1 1-2 8 1 -3 10 2-4…
A: Note: - Since we can answer only up to 3 subparts we will answer subparts 1, 2, and 3 for your…
Q: Give data of a project. Project manager checks the project at the end of week 10th Manpowers/ weeks…
A: Cost Variance (CV = EV - AC) Cost Performance Index (CPI = EV/AC) Schedule Variance (SV = EV -…
Q: A Project has been defined to contain the following list of activities along with their required…
A: a) The network diagram based on the given information is as follows: Note: EF = Early Finish Time…
Q: An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and…
A: We have, Optimistic, To = 2 Most likely, Tm = 3 Pessimistic, Tp = 6
Q: please answer ASAP Table 1 Activity Immediate Predecessor Time (day) ES EF LS LF A - 2…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: 1) Find out the CP by drawing the Network diagram (need to show ES, Duration.EF, LS, LF, Slack) 2)…
A: Below is the solution:-
Q: b) Herlich's project manager, Ruby, believes that for the new product to succeed, it must be…
A: Find the Given details below: Activity Predecessors Duration Cost (RM) Crashed duration Crash…
Q: A plant start-up is based on the following network :a. Draw a network for this project.b. What is…
A:
Q: 12. Given the following network project where the times are in days: Task Normal Crash Normal Crash…
A: Given data: TASK NORMAL TIME CRASH TIME NORMAL COST CRASH COST IP A 2 1 200 300 - B 3 1 100…
Q: Based on project information on kitchen space renovation as prepared below, in the time estimates .…
A: Given- Activity Predecessor Optimistic (O) Most likely (4M) Pessimistic (P) A - 9 10 11 B - 8…
Q: 5. For the following problem, draw a network Activity A B C D E F G H IJ Immediate B А,В A,B B D,E,F…
A: Activity Immediate Predecessors A - B - C B D A,B E A,B F B G D,E,F H D,E I E,F…
Q: The information in the table below is available for a large fund-raising project. Activity…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: 6. A Project network is shown below. Use forward and backward pass to determine th critical path and…
A: PERT is very useful techniques which are common among organizations to reduce cost and to represent…
Q: 1.2 A planned project contains the activities shown in the table below, along with their reqi…
A: A Gantt chart, which is widely used in project management, is one of the most popular and practical…
Q: Activity 3: Scenarios of a project activities (tables given below) and their required times to be…
A: Note: Since you have posted a question with multiple subparts, we will solve the first three…
Q: Activity Times (days) Activity Cost ($) Immediate Activity Predecessor 100 None 150 None 125 А D 175…
A: given,
Q: Example - Draw Activity on Node Diagram Activity Predecessor Duration A B A 3 B E F G C,F 5 H G 4 G…
A: Activity Immediate Predecessors Duration A - 5 B A 3 C B 4 D - 5 E D 7 F E 2 G C,F 5…
Q: 3. Information relating to"RUHUNA X" project is given below. Estimated cost per Activity predecessor…
A: Activity Predecessors Duration A - 2 B A 10 C A 4 D A 5 E…
Q: Preceding Activity Duration Activity (weeks) C, D 3 2 F What is the project's critical path? B -D-G…
A: Activity Immediate Predecessors Duration A - 5 B - 4 C A 2 D B 1 E B 5 F B 5 G C,D 4…
Q: bläi 8 Q2/ By using PERT Method, Solve the ? following Q2/ For the project described in table below,…
A: Given data is
Q: Activity Preceding Activity Expected Completion Time (in Weeks) A None B A 2 A D B 12 E D 10 F 9 D H…
A: Activity Immediate Predecessors Duration A - 5 B A 2 C A 6 D B…
Q: Decide on Menu Hre Caterer Decide on Event Detal A 15 4. Decide on Date Send Out Invites Hold Event…
A: ES = maximum (EF of all immediate predecessor) EF = ES + duration Minimum project duration = largest…
Q: 5. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each…
A: The project network is the visual representation of the project activities and their durations to…
Q: 7. The project information for the custom order project of the Air Control Comp presented here. Draw…
A:
Q: Given the activities of a project; their optimistic (t.), most likely (t_) and pessimistic (t) time…
A: Note: - Since we can answer only up to 3 questions we will answer questions 1, 2, and 3 for your…
Q: 1. A project has been defined to contain the following list of activities along with their required…
A: Note: You have posted multiple questions with multiple subparts, we can solve only one question per…
Q: The following project is reported to be at the end of its 8 week. Find the cost and schedule…
A: From the network diagram, we can see that C-G-I-J is the critical path with duration = 15 weeks
Q: PROJECT PLANNING & SCHEDULING WITH PERT/CPM Given the activities of a project; their optimistic…
A: Given data is
Q: Instructions: 1. Make the project network diagram 2. Find the project duration 3. Solve for 4.…
A: For each non-critical activity, the total float, free float, and independent float calculations are…
Q: Project completion time is * 24.5 weeks 32 weeks 22 weeks O 20 weeks Expected times of activities C…
A: Expected activity duration for each activity could be determined by using the formula, (Pessimistic…
Q: Schedules and activities of some projects are shown below Draw the network diagram Activity…
A: Note: - Since we can answer only up to 3 sub-parts we will answer questions 1, 2, and 3 from the…
Q: Predecessors C, F 9. Activity A B. H, I None (Start) B, J D D. C. H. G\ Construct a CPM network for…
A: Edge Node1 → Node2 D 1→2 C 2→3 F 2→4 d 3→4 G 3→6 H 3→7 A 4→5 J 5→8 I 6→7 B 7→8…
Q: Instructions: 1. Make the project network diagram 2. Find the project duration 3. Solve for…
A: Note: - Since we can answer only up to three subparts we will answer only the first three subparts…
Q: Immediate Activity Predecessor Time (days) 8 в 20 33 18 D E 20 F B B.C 10 H D EF G, H, I 4 (End) a)…
A: A network diagram is a visual representation of a project which helps to identify the project…
Q: Q2,A project network diagram with activities and their durations (days) is given below. A H 2 10…
A: In assembly line balancing, each task is assigned to a workstation in order to meet the specified…
Q: What is the slack time for Activity F and the late start for Activity H?
A: Below is the solution:-
Q: A student club plans on holding a campus-wide event at the end of the semester. The activities that…
A: Given that: Duration Immediate Activity (weeks) Predecessor A 2 -- B 3 A C 1 A D 3…
Q: Find the activity duration (t), latest start (LS) and latest finish (LF) times for activity A.
A: Given: Early start (ES) = 5 Early finish (EF) = 16
Q: Q1: A project consisting of the following activities: ML KTJIH GFE D CB A K J HE GF D.C D.C D.C A BB…
A:
Q: 7. The project information for the custom order project of the Air Control Company is presented…
A: Activity and Slack TimeThe AON project network is a project network with activities being…
Give me right solution
Step by step
Solved in 2 steps with 1 images
- M Inbox (102) - kellyca6@miamioh. X M Inbox (14) - christopher 10kelly@x ✰ miamioh.instructure.com/courses/190424/assignments/2380311 Proj 1 - Prj Mgt-1.docx 5 B Assignments Project #1 Project #1 Activity A B с D E F G H I J K L M N O P Q R X A group of developers is building a new shopping center. A consultant for the developers has developed the following table of activities, durations and predecessors. Determine the earliest start times and finish times, latest start and finish times, activity slack, critical path and duration for the project. There is a Bonus for finishing the project at 90% of the projected date. The bonus for early completion is $50,000. Which activities should be crashed, if the cost for 1 week reduction, for any activity, is $3500 per week, and what is the total cost of crashing? And, Net Bonus, if any. Description Award Kick-off Contract for Crew/Mach Purchase Material Excavation Build Foundation Electrical - Outside Paving Lighting - Exterior Electrical -…↓ ← M Gmail UNILUS | E X ChatGPT X YouTube GBS 660_A X Maps GE News C + File C:/Users/nemet/Desktop/UNILUS/2024/GBS%20660_Assignment%20Distance%20January%202024%20(1).pdf Translate GBS 660_Assignment Distance January 2024 (1).pdf Production X Lusaka Times-Zamb... R Browse Map | Rulac Item cost per Unit Setup cost 4 / 4 2 80 6-Hour D X Inventory carrying cost per year Weekly Net Requirement 1 105 3 130 QUESTION 2: The determination of lot sizes in an MRP system is a complicated and difficult problem. Lot sizes are the part quantities issued in the scheduled receipt and planned-order release sections of an MRP schedule. For parts produced in-house, lot sizes are the production quantities of batch sizes. For purchased parts, these are the quantities ordered from the supplier. Consider the following data relevant to an MRP lot-sizing problem: 4 50 Membersh X b Answered: X G The detern X 100% + # $25 $100 20.8% 5 Building a Better Re... 0 6 200 Get involved in hum... 7 125 8 100 Use the…Hardware departm 8. Decision Tree A wine maker must decide whether to harvest grapes now or in four weeks. Harvesting now will yield 100,000 bottles of wine, netting P 2 per bottle. If the wine maker waits for four weeks and weather turns cold (probability: 20%), the yield will be cut in half but net P 3 per bottle. If the weather does not turn cold, the yield depends on rain. With rain (probability: 50%), a full yield netting P 4 per bottle will result. Without rain, there will still be a full 100,000-bottle yield, but the net amount will be P 3 per bottle only. REQUIRED: Determine the optimal expected value. D NOW LATER (4 weeks) COLD ( ): NOT COLD Decision Alternative Stock 0 unit Stock 1 unit Stock 2 units ( RAIN ( NO RAIN ): 9. Decision (Payoff) Table ESA Dealers, Inc. is contemplating on how many units of cars to order to meet the customer demands for the month based on the following projection: ): Demand 0 unit 1 unit 2 units The profit for each unit sold is P 200,000 while the…
- Student Portal | Main BUS-660 Topic 1 DQ 1 /ilm/takeAssignment/takeAssignmentMain.do?invoker=&takeAssignmentSessionLocator=&inprogress=false eBook X X State of Nature Decision Alternative Strong Demand S₁ Weak Demand S₂ Small complex, d₁ 7 6 Medium complex, d₂ 12 6 Large complex, d3 19 -9 CengageNOWv2 | Online teachin X MindTap-Cengage Learning Problem 4-11 (Algorithmic) Following is the payoff table for the Pittsburgh Development Corporation (PDC) Condominium Project. Amounts are in millions of dollars. x + A million, the large complex remains the best decision. 30 G Suppose PDC is optimistic about the potential for the luxury high-rise condominium complex and that this optimism leads to an initial subjective probability assessment of 0.8 that demand will be strong (S₁) and a corresponding probability of 0.2 that demand will be weak (S₂). Assume the decision alternative to build the large condominium complex was found to be optimal using the expected value approach. Also, a…Decision Table with Conditional Values for Happy Company: Product Market Condition and Payoff (RM) Favourable Stable Unfavourable 8,000 5,000 7,000 6,000 3,000 6,000 -5,000 -1,200 -1,000 A В C Do Nothing Probability 0.4 0.3 0.3 Opportunity loss table for Happy Company.: MARKET CONDITION AND PAYOFF (RM) MAXIMUM IN PRODUCT FAVOURABLE STABLE UNFAVOURABLE A ROW (RM) 5,000 5,000 3,000 A 3,000 3,000 1,200 1,000 8,000 1,000 1,000 Do Nothing Probability 8,000 6,000 0.3 0.4 0.3 Based on the above data answer the following questions: (a) Construct the expected opportunity loss table for Happy Sdn. Bhd. (b) State the best decision (value and product) under EOL method.W AutoSave Off H 2.0 = PDPMT_PQM102_08 June 2023_1 - Read-Only No Label ✓ Layout References Mailings A A Aa A D x² A✓ ✓ A. А File Home Insert Draw Design X Paste Clipboard F Page 6 of 7 ■ Arial B I U U 1599 words Q Search V ✓11 ab ab X₂ X Font English (South Africa) 13° A EE¹F✓ 1.5 5 Text Predictions: On ■ Review View Help E = T 4 Paragraph 5 Accessibility: Unavailable Search W Normal Discuss the benefits of quality in relation to project performance. No Spacing e Styles Heading 1 R A Thembi Mdepa TM Editing Focus Comments Editing Dictate Sensitivity Editor Voice Sensitivity Editor ENG US Share Reuse Files Reuse Files + 09:36 2023/06/08 100%
- B. Match between column A and column B (14 Marks) A Breakeven point method Indirect cost PERT Calculate schedule Classification by Variability Depreciation and administrative expenses Project Planning/Scheduling Total float Provides contingency Difficult to establish and maintain for a large project Probability of completion before a specified date slack time СРМ Gantt ChartSubject: Logistic Management Q#6) What is Porters Power Model explain with example? Q#7) What is risk management & mitigation explain with example?Problem 3-11 Future Value of Reduced Spending [LO3-4] Brenda plans to reduce her spending by $80 a month. Calculate the future value of this increase in savings over the next 10 years. (Assume an annual deposit to her savings account, and an annual interest rate of 4 percent.) (Exhibit 1-A, Exhibit 1-B, Exhibit 1-C, Exhibit 1-D) Note: Use appropriate factor(s) from the tables provided. Round time value factor to 3 decimal places and final answer to 2 decimal places. Future value
- 2. A city is holding an annual marathon event and wants to produce t-shits. Alfonso was able to obtain previous years' demand and probability data as given in below table. The selling price is $10, cost is $5, and the salvage value is $1. Calculate all payoff numbers in the table and profit. Show work. How many shirts should they prepare? Prepare 1000 Prepare 2000 Prepare 3000 Demand=1000| Demand=2000 Demand=3000 30% 35% 35% Profit ISit 9 BU PDE LO PDE LO P L1 O Gl On x PDF 8 1 Po BU b Ve 20. ds E En 20 M Yo b An b M b An b An b Or b If IfB Or ô https://moodle.uowplatform.edu.au/mod/quiz/attempt.php?attempt=D4736363&cmid=2050011&page=37 When groups are established, social comparisons and competition exist between members. Select one: O True O False 21:28 o在這裡輸入文字來搜尋 后 )英 27/3/2021What is the 7p’s of a new coffee shop that sell coffees and desserts.