The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: January February 1,400 May 2,200 1,500 June 2,100 March 1,800 July August 1,700 April 1,700 1,700 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $125 per unit. Inventory holding cost is $25 per unit per month. Ignore any idle-time costs. The plan is called plan A. Plan A: Vary the workforce level to execute a strategy that produces the quantity demanded in the prior month. The December demand and rate of production are both 1,600 units per month. The cost of hiring additional workers is $55 per unit. The cost of laying off workers is $75 per unit. Evaluate this plan. (Enter all responses as whole numbers.) Note: Both hiring and layoff costs are incurred in the month of the change. For example, going from 1,600 in January to 1,400 in February incurs a cost of layoff for 200 units in February. Ending Inventory Hire Stockouts Layoff (Units) Period Month Demand Production (Units) (Units) 1,600 1,600 December 1,600 1,400 200 1 January February 1,500 1,400 3 March 1,800 1,500 4 April 1,700 1,800 May 2,200 1,700 6 June 2,100 2,200 7 July 1,700 2,100 8 August 1,700 1,700

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months
as follows:
January
1,400
May
2,200
February
1,500
June
2,100
March
1,800
July
1,700
April
1,700
August
1,700
Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand.
Stockout cost of lost sales is $125 per unit. Inventory holding cost is $25 per unit per month. Ignore any idle-time
costs. The plan is called plan A.
Plan A: Vary the workforce level to execute a strategy that produces the quantity demanded in the prior month. The
December demand and rate of production are both 1,600 units per month. The cost of hiring additional workers is
$55 per unit. The cost of laying off workers is $75 per unit. Evaluate this plan. (Enter all responses as whole
питbers.)
Note: Both hiring and layoff costs are incurred in the month of the change. For example, going from 1,600 in January
to 1,400 in February incurs a cost of layoff for 200 units in February.
Hire
Layoff
Ending
Inventory
200
Stockouts
Period
Month
Demand
Production
(Units)
(Units)
(Units)
December
1,600
1,400
1,600
1,600
1
January
February
1,500
1,400
3
March
1,800
1,500
4
April
1,700
1,800
5
May
2,200
1,700
June
2,100
2,200
7
July
1,700
2,100
8
August
1,700
1,700
Transcribed Image Text:The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: January 1,400 May 2,200 February 1,500 June 2,100 March 1,800 July 1,700 April 1,700 August 1,700 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $125 per unit. Inventory holding cost is $25 per unit per month. Ignore any idle-time costs. The plan is called plan A. Plan A: Vary the workforce level to execute a strategy that produces the quantity demanded in the prior month. The December demand and rate of production are both 1,600 units per month. The cost of hiring additional workers is $55 per unit. The cost of laying off workers is $75 per unit. Evaluate this plan. (Enter all responses as whole питbers.) Note: Both hiring and layoff costs are incurred in the month of the change. For example, going from 1,600 in January to 1,400 in February incurs a cost of layoff for 200 units in February. Hire Layoff Ending Inventory 200 Stockouts Period Month Demand Production (Units) (Units) (Units) December 1,600 1,400 1,600 1,600 1 January February 1,500 1,400 3 March 1,800 1,500 4 April 1,700 1,800 5 May 2,200 1,700 June 2,100 2,200 7 July 1,700 2,100 8 August 1,700 1,700
Expert Solution
Step 1

Given-

Operations Management homework question answer, step 1, image 1

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.