The managers at AllBirds have operations in multiple countries, which operate on different financial management systems. This has been increasingly challenging for the company, so the Justin is looking to consolidate and integrate the financial management across all locations into a single software system that can operate across the national boundaries. This is a new, complicated and lengthy project, so Justin has identified a set of activity categories that will need to be carefully managed, as noted in the table. Draw the project network, and compute the expected time and variance for each activity.  Develop an activity schedule for this project, compute activity slack time and identify critical path.

Principles of Management
OER 2019th Edition
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax
Chapter15: Managing Teams
Section15.2: Team Development Over Time
Problem 2DQ: What does it mean for the three Rs to be in alignment? What is the potential risk of these not being...
icon
Related questions
Question

The managers at AllBirds have operations in multiple countries, which operate on different financial management systems. This has been increasingly challenging for the company, so the Justin is looking to consolidate and integrate the financial management across all locations into a single software system that can operate across the national boundaries.

This is a new, complicated and lengthy project, so Justin has identified a set of activity categories that will need to be carefully managed, as noted in the table.

  1. Draw the project network, and compute the expected time and variance for each activity. 

  2. Develop an activity schedule for this project, compute activity slack time and identify critical path.

Activities
A
B
с
D
E
F
G
H
I
Immediate
Predecessors
A
A
B, C
с
C
E
E, F
D, G, H
Optimistic
time (months)
2
0.5
1
23
1.5
4
3
6
Most probable
time (months)
3
1
2
3
5
3
7
5
8
Pessimistic
time (months)
5
2.5
3.5
6
8.5
5.5
10
8
12
Transcribed Image Text:Activities A B с D E F G H I Immediate Predecessors A A B, C с C E E, F D, G, H Optimistic time (months) 2 0.5 1 23 1.5 4 3 6 Most probable time (months) 3 1 2 3 5 3 7 5 8 Pessimistic time (months) 5 2.5 3.5 6 8.5 5.5 10 8 12
Expert Solution
steps

Step by step

Solved in 3 steps with 6 images

Blurred answer
Similar questions
Recommended textbooks for you
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College