The expected times and variances for the project activities are given below, critical path is A-D-F-H. What is the probability of the completing the project in 29 periods? ID Description A Pilot production B UD C E F G H Select channels of distribution Develop program Test market Patent Full production Ad promotion Release 50% 40% 70% 60% Predecessor None None None A A D C B,E,F,G te 6 7 4 4 10 16 3 2 Variance [(b-a)/6]² 3 4 225 10 2 1

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
ge 1:
e 2:
e 3:
e 4:
e 5:
e 6:
The expected times and variances for the project activities are given below, critical
path is A-D-F-H. What is the probability of the completing the project in 29 periods?
ID Description
A Pilot production
Select channels of
distribution
Develop program
Test market
Patent
Full production
Ad promotion
Release
B
C
D
E
F
G
H
0000
50%
40%
70%
60%
Predecessor
None
None
None
A
A
D
C
B,E,F,G
te
6
N
7
4
4
10
16
3
2
Variance
[(b-a)/6]2
3
4
2
2
5
10
2
1
Transcribed Image Text:ge 1: e 2: e 3: e 4: e 5: e 6: The expected times and variances for the project activities are given below, critical path is A-D-F-H. What is the probability of the completing the project in 29 periods? ID Description A Pilot production Select channels of distribution Develop program Test market Patent Full production Ad promotion Release B C D E F G H 0000 50% 40% 70% 60% Predecessor None None None A A D C B,E,F,G te 6 N 7 4 4 10 16 3 2 Variance [(b-a)/6]2 3 4 2 2 5 10 2 1
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.