Table Q3 Staff Readings Remarks 2.491 (BS); TBM 1 TBM 1 (24.918m) 2.469 (FS); 1.758 (BS) CP1 3.026 (IS) R1 2.267 (IS) R2 2.082 (IS) R3 1.176 (FS); 2.064 (BS) CP2 3.012 (FS); 1.25 (BS) CP3 3.052 (IS) R4 1.977 (IS) R5 2.036 (IS) R6 2.013 (IS) R7 2.157 (IS) R8 road surface immediately below B1 -3.896 (IS) B1 0.908 (FS); 1.736 (BS) CP4 1.25 (IS) R9 2.292 (IS) R10 2.102 (IS) R11 2.056 (IS) R12 3.511 (FS) TBM 2 TBM 2 (23.143m) BS= BACKSIGHT IS = INTERMEDIATE SIGHT; FS = FORESIGHT 3

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
icon
Concept explainers
Question
100%
Table Q3
Staff Readings
Remarks
2.491 (BS):
TBM 1
TBM 1 (24.918m)
2.469 (FS); 1.758 (BS)
CP1
3.026 (IS)
R1
2.267 (IS)
R2
2.082 (IS)
R3
1.176 (FS); 2.064 (BS)
CP2
3.012 (FS); 1.25 (BS)
CP3
3.052 (IS)
R4
1.977 (IS)
R5
2.036 (IS)
R6
2.013 (IS)
R7
2.157 (IS)
R8
road surface immediately below B1
-3.896 (IS)
B1
0.908 (FS); 1.736 (BS)
CP4
1.25 (IS)
R9
2.292 (IS)
R10
2.102 (IS)
R11
2.056 (IS)
R12
3.511 (FS)
TBM 2
TBM 2 (23.143m)
BS BACKSIGHT; IS = INTERMEDIATE SIGHT; FS = FORESIGHT
53
Transcribed Image Text:Table Q3 Staff Readings Remarks 2.491 (BS): TBM 1 TBM 1 (24.918m) 2.469 (FS); 1.758 (BS) CP1 3.026 (IS) R1 2.267 (IS) R2 2.082 (IS) R3 1.176 (FS); 2.064 (BS) CP2 3.012 (FS); 1.25 (BS) CP3 3.052 (IS) R4 1.977 (IS) R5 2.036 (IS) R6 2.013 (IS) R7 2.157 (IS) R8 road surface immediately below B1 -3.896 (IS) B1 0.908 (FS); 1.736 (BS) CP4 1.25 (IS) R9 2.292 (IS) R10 2.102 (IS) R11 2.056 (IS) R12 3.511 (FS) TBM 2 TBM 2 (23.143m) BS BACKSIGHT; IS = INTERMEDIATE SIGHT; FS = FORESIGHT 53
leveling field work
was conducted to
determinine the level of an exiting road
that runs road under the bridge. the points
CP1 to Cpy and points R1 - R 12
are
points
on
the road. Points B1 is underside
of
the bridge, complete the level book an
determine the headroom of the bridge.
perform all necerry checks
Transcribed Image Text:leveling field work was conducted to determinine the level of an exiting road that runs road under the bridge. the points CP1 to Cpy and points R1 - R 12 are points on the road. Points B1 is underside of the bridge, complete the level book an determine the headroom of the bridge. perform all necerry checks
Expert Solution
steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Knowledge Booster
Water resource systems analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning