Table 1 shows a direct time study data from an assembly line. Job element B is in automatic mode while other job elements are in manual operations. The delay allowance is 5%, fatigue allowance is 8% and personal allowance is 7%. Please use 4 decimal places for the rating value and 3 decimal places for your standard time. Table 1: Direct time study data Job Average Process Time Rating Element A 100 1+0.001(264) 1 B 25 1+ 0.002(264) 1-0.001(264) 1- 0.0005(264) C 40 100 E 200 Calculate standard time for Job Element A. Calculate standard time for Job Element B. Calculate standard time for Job Element C. Calculate standard time for Job Element D. iv. V. Calculate standard time for Job Element E. vi. Calculate the overall standard time for the whole process.

Elements Of Electromagnetics
7th Edition
ISBN:9780190698614
Author:Sadiku, Matthew N. O.
Publisher:Sadiku, Matthew N. O.
ChapterMA: Math Assessment
Section: Chapter Questions
Problem 1.1MA
icon
Related questions
Question
1.
Table 1 shows a direct time study data from an assembly line. Job element B is in automatic
mode while other job elements are in manual operations. The delay allowance is 5%, fatigue
allowance is 8% and personal allowance is 7%. Please use 4 decimal places for the rating
value and 3 decimal places for your standard time.
Table 1: Direct time study data
Job
Average
Rating
Element
Process Time
A
100
1+0.001(264)
B
25
1
1+ 0.002(264)
1-0.001(264)
1 - 0.0005(264)
C
40
100
E
200
i.
Calculate standard time for Job Element A.
ii.
Calculate standard time for Job Element B.
111.
Calculate standard time for Job Element C.
iv.
Calculate standard time for Job Element D.
V.
Calculate standard time for Job Element E.
vi.
Calculate the overall standard time for the whole process.
Transcribed Image Text:1. Table 1 shows a direct time study data from an assembly line. Job element B is in automatic mode while other job elements are in manual operations. The delay allowance is 5%, fatigue allowance is 8% and personal allowance is 7%. Please use 4 decimal places for the rating value and 3 decimal places for your standard time. Table 1: Direct time study data Job Average Rating Element Process Time A 100 1+0.001(264) B 25 1 1+ 0.002(264) 1-0.001(264) 1 - 0.0005(264) C 40 100 E 200 i. Calculate standard time for Job Element A. ii. Calculate standard time for Job Element B. 111. Calculate standard time for Job Element C. iv. Calculate standard time for Job Element D. V. Calculate standard time for Job Element E. vi. Calculate the overall standard time for the whole process.
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Dimensional Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Elements Of Electromagnetics
Elements Of Electromagnetics
Mechanical Engineering
ISBN:
9780190698614
Author:
Sadiku, Matthew N. O.
Publisher:
Oxford University Press
Mechanics of Materials (10th Edition)
Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:
9780134319650
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Thermodynamics: An Engineering Approach
Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:
9781259822674
Author:
Yunus A. Cengel Dr., Michael A. Boles
Publisher:
McGraw-Hill Education
Control Systems Engineering
Control Systems Engineering
Mechanical Engineering
ISBN:
9781118170519
Author:
Norman S. Nise
Publisher:
WILEY
Mechanics of Materials (MindTap Course List)
Mechanics of Materials (MindTap Course List)
Mechanical Engineering
ISBN:
9781337093347
Author:
Barry J. Goodno, James M. Gere
Publisher:
Cengage Learning
Engineering Mechanics: Statics
Engineering Mechanics: Statics
Mechanical Engineering
ISBN:
9781118807330
Author:
James L. Meriam, L. G. Kraige, J. N. Bolton
Publisher:
WILEY