! Required information [The following information applies to the questions displayed below] The Air Force Museum Foundation has commissioned the purchase of 16 Four F Sixes, pre-World War II aircraft. They will be built completely from scratch to the exact specifications used for the originals. As further authentication, the aircraft will be made using the technology and manufacturing processes available when the originals were built. Each of the 16 airplanes will be flown to Air Force and aviation museums throughout the country for exhibition. Aviation enthusiasts can also visit the production facility to see exactly how such aircraft were built in 1938. Soren Industries wants to bid on the aircraft contract and asked for and received certain cost information about the Four F Sixes from the Air Force. The information includes some of the old cost data from the builders of the original aircraft. The available information is for the total accumulated time as the 1st, 8th, and 32nd aircrafts, respectively, were completed. The data reflect a learning rate of 80%. Output 1 8 32 Total Hours 1,250 5,120 13,107 Required: 1. If Soren Industries expects that the manufacturing time and learning rate will be the same as it was in 1938, how many hours will it take to build the 16 aircraft for the Air Force Museum Foundation? Assume also that the learning that took place in the 1930s is no longer applicable, and that learning begins anew at 1,250 hours for the first unit. (Do not round intermediate calculations. Round yo final answer to the nearest whole number.) Estimated hours

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
Required information
[The following information applies to the questions displayed below.]
The Air Force Museum Foundation has commissioned the purchase of 16 Four F Sixes, pre-World War II aircraft. They will
be built completely from scratch to the exact specifications used for the originals. As further authentication, the aircraft will
be made using the technology and manufacturing processes available when the originals were built. Each of the 16
airplanes will be flown to Air Force and aviation museums throughout the country for exhibition. Aviation enthusiasts can
also visit the production facility to see exactly how such aircraft were built in 1938.
Soren Industries wants to bid on the aircraft contract and asked for and received certain cost information about the Four F
Sixes from the Air Force. The information includes some of the old cost data from the builders of the original aircraft. The
available information is for the total accumulated time as the 1st, 8th, and 32nd aircrafts, respectively, were completed. The
data reflect a learning rate of 80%.
Output
1
8
32
Total Hours
1,250
5,120
13,107
Required:
1. If Soren Industries expects that the manufacturing time and learning rate will be the same as it was in 1938, how many hours will it
take to build the 16 aircraft for the Air Force Museum Foundation? Assume also that the learning that took place in the 1930s is no
longer applicable, and that learning begins anew at 1,250 hours for the first unit. (Do not round intermediate calculations. Round your
final answer to the nearest whole number.)
Estimated hours
Transcribed Image Text:Required information [The following information applies to the questions displayed below.] The Air Force Museum Foundation has commissioned the purchase of 16 Four F Sixes, pre-World War II aircraft. They will be built completely from scratch to the exact specifications used for the originals. As further authentication, the aircraft will be made using the technology and manufacturing processes available when the originals were built. Each of the 16 airplanes will be flown to Air Force and aviation museums throughout the country for exhibition. Aviation enthusiasts can also visit the production facility to see exactly how such aircraft were built in 1938. Soren Industries wants to bid on the aircraft contract and asked for and received certain cost information about the Four F Sixes from the Air Force. The information includes some of the old cost data from the builders of the original aircraft. The available information is for the total accumulated time as the 1st, 8th, and 32nd aircrafts, respectively, were completed. The data reflect a learning rate of 80%. Output 1 8 32 Total Hours 1,250 5,120 13,107 Required: 1. If Soren Industries expects that the manufacturing time and learning rate will be the same as it was in 1938, how many hours will it take to build the 16 aircraft for the Air Force Museum Foundation? Assume also that the learning that took place in the 1930s is no longer applicable, and that learning begins anew at 1,250 hours for the first unit. (Do not round intermediate calculations. Round your final answer to the nearest whole number.) Estimated hours
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L