Question 23 As part of a project appraisal, a Future Value (FV) of £8900 in 2 years time, is discounted at a rate of 9% per annum. Calculate the Present Value (PV). (to 2 d.p.)

Managerial Accounting
15th Edition
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:Carl Warren, Ph.d. Cma William B. Tayler
Chapter12: Capital Investment Analysis
Section: Chapter Questions
Problem 3BE
icon
Related questions
Question

6

Question 23
As part of a project appraisal, a Future Value (FV) of £8900 in 2 years time, is discounted
at a rate of 9% per annum. Calculate the Present Value (PV).
(to 2 d.p.)
The following information is required for Questions 24 and 25.
A discount rate of 8.1% per annum is being used to calculate the Net Present Value (NPV) of a project.
The table below shows a student's attempt to find the NPV.
Unfortunately a significant error has occurred in one of the discount factors (DF) and hence the PV for that year.
Year
Cash In
Cash Out
Cashflow
DF
PV
1600
-1600
1
-1600
1100
200
900
0.92507
832.56
2
1000
300
700
0.85575
599.03
3
900
400
500
1.26321
631.61
4
800
400
400
0.73231
292.92
Question 24
Decide in which Year the error occurred and state the correct discount factor.
(to 5 d.p.)
(Only correct discount fa
Question 25
For the Year in which the error occurred, work out the correct PV.
(to 2 d.p.)
Question 26
Copy and paste this table elsewhere to find the Net Present Value (NPV) of the whole project using a discount rate of 9.3%.
Year
Cash In
Cash Out
Cashflow
DF
PV
2900
-2900
1
-2900
1
1600
100
1200
200
3
1100
300
(to 2 d.p.)
The following information is required for Questions 27 and 28.
For each of the datasets displayed in Questions 27 and 28 choose the number from the list
below which is the mostly likely value of the product moment correlation coefficient, r.
-4
-1
-0.9
-0.4
0.4
0.9
1 4
Question 27
90
80
70
60
50
40
30
20
10
20
40
60
80
100
Question 28
100
90
80
70
60
50
40
30
20
10
20
40
60
80
100
Transcribed Image Text:Question 23 As part of a project appraisal, a Future Value (FV) of £8900 in 2 years time, is discounted at a rate of 9% per annum. Calculate the Present Value (PV). (to 2 d.p.) The following information is required for Questions 24 and 25. A discount rate of 8.1% per annum is being used to calculate the Net Present Value (NPV) of a project. The table below shows a student's attempt to find the NPV. Unfortunately a significant error has occurred in one of the discount factors (DF) and hence the PV for that year. Year Cash In Cash Out Cashflow DF PV 1600 -1600 1 -1600 1100 200 900 0.92507 832.56 2 1000 300 700 0.85575 599.03 3 900 400 500 1.26321 631.61 4 800 400 400 0.73231 292.92 Question 24 Decide in which Year the error occurred and state the correct discount factor. (to 5 d.p.) (Only correct discount fa Question 25 For the Year in which the error occurred, work out the correct PV. (to 2 d.p.) Question 26 Copy and paste this table elsewhere to find the Net Present Value (NPV) of the whole project using a discount rate of 9.3%. Year Cash In Cash Out Cashflow DF PV 2900 -2900 1 -2900 1 1600 100 1200 200 3 1100 300 (to 2 d.p.) The following information is required for Questions 27 and 28. For each of the datasets displayed in Questions 27 and 28 choose the number from the list below which is the mostly likely value of the product moment correlation coefficient, r. -4 -1 -0.9 -0.4 0.4 0.9 1 4 Question 27 90 80 70 60 50 40 30 20 10 20 40 60 80 100 Question 28 100 90 80 70 60 50 40 30 20 10 20 40 60 80 100
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Market Efficiency
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub