QUESTION 1 You are the mine manager of Mine X and you want to expand your operations. The feasibility study shows that you have two options to consider. Option A is to sell your product to a local consumer. Option B is to export your product. The feasibility study yielded the following results for Options A and B. Option A Total reserve base          80 million tons Capital required             R1 000 million Mining rate                    8 million tons per year Yield                              100% Production cost             R35,00 ROM per ton Sales price                     R80,00 per ton Tax rate                          30% NPV                               47,09 million IRR                                 22% Option B Total reserve base         80 million tons Capital required            R2 000 million Mining rate                   8 million tons per year Yield                              70% Production cost            R35,00 per ROM ton Beneficiation cost         R45,00 per ROM ton Transport cost               R30,00 per sales ton Sales price                    US$ 40 per ton Exchange rate               R7,00 per US$ Tax rate                         30% NPV                              R192 million IRR                                23% 1.1  Which option will you choose? Give reasons for your answer.  1.2  What is the payback period in years for both options?

Survey of Accounting (Accounting I)
8th Edition
ISBN:9781305961883
Author:Carl Warren
Publisher:Carl Warren
Chapter15: Capital Investment Analysis
Section: Chapter Questions
Problem 15.15E
icon
Related questions
Question

QUESTION 1

You are the mine manager of Mine X and you want to expand your operations. The feasibility study shows that you have two options to consider.

Option A is to sell your product to a local consumer.

Option B is to export your product. The feasibility study yielded the following results for Options A and B.


Option A

Total reserve base          80 million tons
Capital required             R1 000 million
Mining rate                    8 million tons per year
Yield                              100%
Production cost             R35,00 ROM per ton
Sales price                     R80,00 per ton
Tax rate                          30%
NPV                               47,09 million
IRR                                 22%


Option B

Total reserve base         80 million tons
Capital required            R2 000 million
Mining rate                   8 million tons per year
Yield                              70%
Production cost            R35,00 per ROM ton
Beneficiation cost         R45,00 per ROM ton
Transport cost               R30,00 per sales ton
Sales price                    US$ 40 per ton
Exchange rate               R7,00 per US$
Tax rate                         30%
NPV                              R192 million
IRR                                23%


1.1  Which option will you choose? Give reasons for your answer. 

1.2  What is the payback period in years for both options? 

Expert Solution
steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Future Value
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Survey of Accounting (Accounting I)
Survey of Accounting (Accounting I)
Accounting
ISBN:
9781305961883
Author:
Carl Warren
Publisher:
Cengage Learning
Corporate Fin Focused Approach
Corporate Fin Focused Approach
Finance
ISBN:
9781285660516
Author:
EHRHARDT
Publisher:
Cengage