Q3. A school cafeteria is operated by five persons performing the activities listed below in the average times shown: Activity Average Time, Sec. 1. Serve Salad and dessert 10 2. Pour drinks 30 3. Serve entree 60 4. Serve vegetables 20 5. Tally and collect payments 40 a. What are the bottleneck activity and the maximum service capacity per hour? b. Suggest a reallocation of activities that would increase capacity and use only four employees, and draw a product flow diagram. What is the capacity of your improved system? c. Recommend a way to maintain the serving capacity found in part b using only three

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter5: Network Models
Section5.3: Assignment Models
Problem 12P
icon
Related questions
Question
Q3. A school cafeteria is operated by five persons performing the activities listed below in the
average times shown:
Activity
Average Time, Sec.
1. Serve Salad and dessert
10
2. Pour drinks
30
3. Serve entree
60
4. Serve vegetables
20
5. Tally and collect payments
40
a. What are the bottleneck activity and the maximum service capacity per hour?
b. Suggest a reallocation of activities that would increase capacity and use only four
employees, and draw a product flow diagram. What is the capacity of your improved
system?
c. Recommend a way to maintain the serving capacity found in part b using only three
employees.
Transcribed Image Text:Q3. A school cafeteria is operated by five persons performing the activities listed below in the average times shown: Activity Average Time, Sec. 1. Serve Salad and dessert 10 2. Pour drinks 30 3. Serve entree 60 4. Serve vegetables 20 5. Tally and collect payments 40 a. What are the bottleneck activity and the maximum service capacity per hour? b. Suggest a reallocation of activities that would increase capacity and use only four employees, and draw a product flow diagram. What is the capacity of your improved system? c. Recommend a way to maintain the serving capacity found in part b using only three employees.
Expert Solution
steps

Step by step

Solved in 2 steps with 9 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,