Q.14 At M3 Marketing a new marketing campaign development project for a client begins with two activities ideation and budgeting/contracting. Ideation, or coming up with ideas for the campaign, occurs in parallel with (i.e., at the same time as,) the budgeting/contracting work which determines the costs and terms of the relationship. These activities take four and three weeks, respectively. Once ideation is complete, advertising content drafting begins and lasts two weeks. When the budget is set and the ad drafting is complete, the activity to determine the advertising channels can begin. Determining the ad channels takes three weeks. When ad drafting is complete and the advertising channels are determined, two activities can start. First, final campaign collateral can be developed over the next six weeks. The second activity is rollout planning, which requires four weeks. After collateral development and rollout planning are finished, the advertising campaign rollout is executed over the next three weeks. After the campaign rollout, the new ad campaign is complete and can be handed over to advertising operations group. Durations and costs and completely crashed durations and costs for all activities are provided in the table below. a) To reduce the project’s planned duration by one week, which activity should be crashed first to minimize the impact on project cost as much as possible? 1. Channel Determination 2. Budget and Contract 3. Rollout Planning 4. Collateral Development 5. None of the answers are correct. b) After reducing the project’s planned duration by two weeks by using the least cost activity to crash, which activities are not critical? 1. Campaign Rollout 2. None of the answers are correct. 3. Ideation 4. Rollout Planning 5. Ad Drafting

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Q.14

At M3 Marketing a new marketing campaign development project for a client begins with two activities ideation and budgeting/contracting. Ideation, or coming up with ideas for the campaign, occurs in parallel with (i.e., at the same time as,) the budgeting/contracting work which determines the costs and terms of the relationship. These activities take four and three weeks, respectively.

Once ideation is complete, advertising content drafting begins and lasts two weeks. When the budget is set and the ad drafting is complete, the activity to determine the advertising channels can begin. Determining the ad channels takes three weeks.

When ad drafting is complete and the advertising channels are determined, two activities can start. First, final campaign collateral can be developed over the next six weeks. The second activity is rollout planning, which requires four weeks.

After collateral development and rollout planning are finished, the advertising campaign rollout is executed over the next three weeks. After the campaign rollout, the new ad campaign is complete and can be handed over to advertising operations group.

Durations and costs and completely crashed durations and costs for all activities are provided in the table below.

a) To reduce the project’s planned duration by one week, which activity should be crashed first to minimize the impact on project cost as much as possible?

1. Channel Determination

2. Budget and Contract

3. Rollout Planning

4. Collateral Development

5. None of the answers are correct.

b) After reducing the project’s planned duration by two weeks by using the least cost activity to crash, which activities are not critical?

1. Campaign Rollout

2. None of the answers are correct.

3. Ideation

4. Rollout Planning

5. Ad Drafting

Activity
Ideation
Budgeting/Contracting
Ad Drafting
Channel Determination
Collateral Develop
Rollout Planning
Campaign Rollout
ID
A
B
C
D
E
F
G
Normal
Duration
4
3
2
36
6
4
3
weeks
Normal Cost Crash Duration Crash Cost
$2,000
$2,900
$1,500
$2,200
$3,000
$3,000
$1,400
$3,500
$1,900
$1,800
$1,000
$3,000
$1,500
$1,200
2
2
2
1
4
3
2
weeks
Transcribed Image Text:Activity Ideation Budgeting/Contracting Ad Drafting Channel Determination Collateral Develop Rollout Planning Campaign Rollout ID A B C D E F G Normal Duration 4 3 2 36 6 4 3 weeks Normal Cost Crash Duration Crash Cost $2,000 $2,900 $1,500 $2,200 $3,000 $3,000 $1,400 $3,500 $1,900 $1,800 $1,000 $3,000 $1,500 $1,200 2 2 2 1 4 3 2 weeks
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.