Problem 2 Below is information related to: • historical average processing times for Products A and B historical percentage of work center load required to produce Produdcts A and B • routing and standard times to produce Product B the product structure for Product B a MPS covering 3 periods for Products A and B. MPS in Units End Product 1 2 3 Processing Time A 50 45 25 wc Historical % End Product Hours/Unit В 30 25 30 100 40% A 0.80 200 50% в 1.6 300 10% B Routing and Standard Time Data End Product Lot Size Work Center Set Up (Hrs) Run Time/Unit (Hrs) Hrs/Unit B 40 100 1.25 E (3 required) 50 200 2 0.07 100 200 0.08 F 100 300 2 0.04 (2 required) B. Create a capacity bill for product B in the space provided. Consider lot sizes in your calculations. Capacity Bill for Product B

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question

Find the problem in the attachment

Problem 2
Below is information related to:
• historical average processing times for Products A and B
historical percentage of work center load required to produce Produdcts A and B
• routing and standard times to produce Product B
the product structure for Product B
a MPS covering 3 periods for Products A and B.
MPS in Units
End Product
1
2
3
Processing Time
A
50
45
25
wc
Historical %
End Product Hours/Unit
В
30
25
30
100
40%
A
0.80
200
50%
в
1.6
300
10%
B
Routing and Standard Time Data
End Product Lot Size Work Center Set Up (Hrs) Run Time/Unit (Hrs) Hrs/Unit
B
40
100
1.25
E
(3 required)
50
200
2
0.07
100
200
0.08
F
100
300
2
0.04
(2 required)
B. Create a capacity bill for product B in the space provided. Consider lot sizes in your
calculations.
Capacity Bill for Product B
Transcribed Image Text:Problem 2 Below is information related to: • historical average processing times for Products A and B historical percentage of work center load required to produce Produdcts A and B • routing and standard times to produce Product B the product structure for Product B a MPS covering 3 periods for Products A and B. MPS in Units End Product 1 2 3 Processing Time A 50 45 25 wc Historical % End Product Hours/Unit В 30 25 30 100 40% A 0.80 200 50% в 1.6 300 10% B Routing and Standard Time Data End Product Lot Size Work Center Set Up (Hrs) Run Time/Unit (Hrs) Hrs/Unit B 40 100 1.25 E (3 required) 50 200 2 0.07 100 200 0.08 F 100 300 2 0.04 (2 required) B. Create a capacity bill for product B in the space provided. Consider lot sizes in your calculations. Capacity Bill for Product B
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Consumer attitude
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,