Planned value (PV) is $111 Estimated time to completion is not unfavorable Estimated cost to completion ($000 omitted) is far more than $235 Estimated time to completion is 9.79 Cumulative actual value (AC) is more than $94 Schedule performance index (SPI) is less than 61% Estimated cost to completion variance, $000 omitted is less than $75 Estimated time to completion variance is less than 4.79 Cost performance index (CPI) is 72% Earned value (EV) is less than $68

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter8: Standard Costs And Variances
Section: Chapter Questions
Problem 7MC: When is the material price variance unfavorable? A. when the actual quantity used is greater than...
icon
Related questions
Question

9

Planned value (PV) is $111
Estimated time to completion is not unfavorable
Estimated cost to completion ($000 omitted) is far more than $235
Estimated time to completion is 9.79
Cumulative actual value (AC) is more than $94
Schedule performance index (SPI) is less than 61%
Estimated cost to completion variance, $000 omitted is less than $75
Estimated time to completion variance is less than 4.79
Cost performance index (CPI) is 72%
Earned value (EV) is less than $68
Transcribed Image Text:Planned value (PV) is $111 Estimated time to completion is not unfavorable Estimated cost to completion ($000 omitted) is far more than $235 Estimated time to completion is 9.79 Cumulative actual value (AC) is more than $94 Schedule performance index (SPI) is less than 61% Estimated cost to completion variance, $000 omitted is less than $75 Estimated time to completion variance is less than 4.79 Cost performance index (CPI) is 72% Earned value (EV) is less than $68
The following information is available. Select only correct answers.
Project planned duration,
months
Project budget, $000
omitted
Activity
Staffing
Blueprinting
Prototype Development
Full Design
Construction
Transfer
6
$170
Jan Feb Mar Apr May Jun comp
$9 $6
$7 $8
$5
$8
$4
$8
$6
95%
90%
65%
$10 55%
$30 45%
$10 35%
Transcribed Image Text:The following information is available. Select only correct answers. Project planned duration, months Project budget, $000 omitted Activity Staffing Blueprinting Prototype Development Full Design Construction Transfer 6 $170 Jan Feb Mar Apr May Jun comp $9 $6 $7 $8 $5 $8 $4 $8 $6 95% 90% 65% $10 55% $30 45% $10 35%
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Risk Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College