Norton Industries is installing a new computer system. The activities, the activity times, and the project network are as follovs. Activity Time A 3 6 2 D 5 4 3 G 3 A E Start H Finish D B G
Q: - The mean number of air conditioning units assembled per month by Freeze, Inc. is 750 and the stand...
A: Given Information :- Mean (μ) =750, Standard Deviation (σ)=100 Break even point (BEP) = 500
Q: Cutey Barber Salon Cutey Barber Salon is a trendy barber salon that is located in a densely populate...
A: As lengthy as servicing times comprise an adverse impact for both client and service providers, Decr...
Q: - percent change in productivity for or no month thir vanr a multi nctor bn
A: Multifactor productivity indicating the proportion between total output and total input. Here, we wi...
Q: A manager is quite concerned about the recent deterioration of a section of the roof on a building t...
A: The decision tree is a strong and well-known method for separating and foreseeing. A decision tree i...
Q: 44. US Airlines receives an average of 500 calls per hourfrom customers who want to make reservation...
A: The following information is provided: The arrival rate is 500/hr The service rate is 20/hr Wage rat...
Q: 6.3) CASE STUDY: The last half decade has been an interesting one for General Motors (GM). Once a se...
A: Change management is described as a process that allows the introduction of transformation and trans...
Q: Ron Satter field's excavation company uses bothGantt scheduling charts and Gantt load charts.a) Toda...
A: The given information can be used as follows in order to prepare the gantt chart.
Q: The current date is day 275 and the following jobs are waiting to be processed at the same equipment...
A: Given-
Q: 1. A computer repair shop had received several complaints on the length of time it took to make repa...
A: As specified, I have solved the first question for you. Kindly find the solution from Step 2 onwards...
Q: Susan has just been hired as a professional SCUBA diver at a resort in Bali. She is a certified dive...
A: Productivity training is tied in with gaining more headway, significantly quicker. To accomplish you...
Q: Question attahed in image
A: Note: - As we can answer only up to three subparts we will answer the first three(a, b, and c) subpa...
Q: Malburn Construction Ltd. Manufactures and distributes window frames. The company uses 600,000 metal...
A: Note: - Since we can answer only up to three subparts we will answer first three subparts(1, 2, and ...
Q: John Doe, a fraud examiner, has been hired by ABC Corporation to investigate a shortage of cash, whi...
A: Business frauds are often called illegal activities or operations. Business fraud can be stated as a...
Q: data outright. As the purchaser you will have to utilize reverse price analysis, describe the formul...
A: For reverse pricing analysis, there is no one-size-fits-all method for determining the cost.
Q: How can robotics and automation improve the supply chain efficency in warehousing, distribution and ...
A: During the COVID-19 epidemic, enterprise warehouses struggled to keep up with the tremendous growth ...
Q: A newspaper stand operator has the following sales data for one- year sales of Fine magazine. Quanti...
A: Given below some of the calculations. Quantities sold per day No. of days quantity sold Profit fo...
Q: Chapter 8. In Problem Set 6, we worked on a problem for Flor’s Flours, a small business that produce...
A: From the given data: Let the decision variables be as shown below (all in lbs): Wheat Garba...
Q: A company makes two products, X and Y, using two machines, 1 and 2. Each unit of X that is produced ...
A:
Q: 4- George Kyparisis makes bowling balls in his Miami plant. With recent increases in his costs, he h...
A:
Q: Given the following list of items,(a) Calculate the annual usage cost of each item.(b) Classify the ...
A: The ABC analysis is the technique of inventory management that is used to identify the value of inve...
Q: A paper published in the Harvard Business Review points out a new way to calculate economic profit t...
A: An individual's productivity is how much work they can do in a given measure of time. It's a straigh...
Q: 5-17 Data collected on the yearly demand for 50-pound bags of fertilizer at Wallace Garden Supply ar...
A: Forecasting is the process of determining the estimated forecast for the future using the previous y...
Q: 1. Discuss project cost relative to project planning.
A: Project management is the management in which different types of skills and knowledge for the delive...
Q: The Average Lead Time is 10 days and the Average Daily Usage of widgets is 20. The company has deter...
A: Reorder point is described as the minimum number of units that any business or inventory needs to ha...
Q: ss how we, as construction manager, can avoid the delays in the construction. Use all theories neces...
A: You can frequently follow wild construction project costs back to a certain something: an inability ...
Q: g) Suppose that the profit contribution of component 3 decrease by $2.00 . Would the optimal solutio...
A:
Q: Discuss in detail the steps for Import of goods and equipment’s for a tertiary care teaching hospita...
A: A Small Introduction about Documentation The presentation ordinarily depicts the extent of the re...
Q: Identify and analyze one of the leading causes of hospital readmissions over the past 5 In your opin...
A: Hospital readmission is that the client will be getting admitted within 30 days after being discharg...
Q: Solve the game whose pay-off matrix is given by Player B B1 B2 B3 A1 1 3 Player A A2 -4 -3 A3 1 -1 1...
A: Game theory is a theoretical framework for conceiving social problems among competing players. Game ...
Q: The proposed Ghana Airways Airline project is being procured through a Public-Private Partnership (P...
A: Decision tree analysis can be stated as the approach of sketching or drawing a decision tree, which ...
Q: (a) What capacity plans do you think ESCOM should make for next year? Why? (6) What longer-term capa...
A: The following information is given: Year Forecast 0 100 1 140 2 195 3 27...
Q: Tyler bakes Cookies (C) and Breads (B) with the help of two ovens in his little bakery. The time tak...
A: since, the cookies and breads cannot be made in decimals, integer constraint will be kept to find th...
Q: The sensitivity range for an objective function coefficient is the range of values over which the op...
A: YES the statement is true. The sensitivity range for an objective function coefficient is the range ...
Q: A tender advert appeared in the print media on 12th March 2020 to run for four (4) weeks. A week fro...
A: The tender advertisement: It floated in the media on 12th March 2020 to run for 4 weeks. The tende...
Q: 4) The choice of technology revolves around two basic questions: (1) What is the desired amount of...
A: Choices of technology has important implications for capacity planning, facility layout, equipment c...
Q: With reference to project of an organization of your choice, describe how goods, works and services ...
A: Procurement is buying goods or services and is generally about business investing or spending. Busin...
Q: Managing quality is an important integral in operations management. In addition to being a critical ...
A: Quality is defined as an outcome, a feature of a product or service supplied to a client and the hal...
Q: Urgently need For a table manufacturing company, variable cost is $125.00 per Unit, rent is $2,537....
A: Contribution margin refers to the margin that gives clear picture about the aggregate amount of reve...
Q: eanie realizes that she has another project that needs to be completed by Saturday and wonders if sh...
A: A Small Introduction about Crashing Model The CRASH model has been proposed by Medical Research C...
Q: 1. A company that makes shopping carts for supermarkets and other stores recently purchased some new...
A:
Q: evelop a swot matrix for MacDonalds
A: SWOT is basically- S-strengths W-weaknesses O-opportunities T-threats
Q: Case Narrative: As a young investor with a moderate risk attitude, you consulted a financial adviser...
A: given, maximum PHP 650,000 DIAKOM TRAICING CURRENT = PHP 30 PER SHARE
Q: Max −A + 2B s.t. -2A + 3B ≤ 8 (Constraint 1) 6A - 2B ≤ 5 (Constraint 2) A + ...
A: a) Z is maximum when A = 1.4 and B = 3.6
Q: what is a turnkey contract what are advantage and disadvantages
A: Turnkey contracts are the type of contracts in which a contractor promises to build a project which ...
Q: With the use of a diagram, show (illustrate) the typical levels of uncertainty or project risks asso...
A: A project risk is a dubious occasion that could conceivably happen during a project. In spite of our...
Q: Explain the difference between past time focus and present time focus.
A: The difference between the past time focus and the present time focus can be stated as the conduct o...
Q: 10. Quarterly demand for Jaguar XJ8’s at a Tacloban Auto dealership is forecast with the equation, ...
A: Forecasting is used by companies to match supply with demand and to avoid opportunity costs issues. ...
Q: What does change management accomplish and what are the components of an effective change management...
A: As it is said that change is the law of nature so the business also undergoes number of changes on e...
Q: You have been asked to estimate the cost of 100 prefabricated structures to be sold to a local schoo...
A: Production costs mirror all of the costs associated with a company conducting its business while man...
Q: 12 A bill of lading that states"consigned toJ. Smith" is a ? A .short form bill of lading B.negoti...
A: A bill of lading is described as the document (legal) that is issued to a shipper by a carrier and i...
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 65 images
- 8 EARNED VALUE ANALYSIS The following project is reported to be at the end of its 8 week. Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Find the condition of the project at the this reporting period. PV AC Budget ($) Duration Actual Cost % D-8 Activity Predecessor (s) (week) ($) Complete 300 400 A 3 100 A3 В 4 200 180 100 B:4 C 7 250 300 90 A 8 600 400 50 400 200 В 40 150 180 F В 4 100 G C 4 100 200 40 500 H D, E 2 300 F, G 3 J H, I 1 100 ㅇ CO 프 (-)By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A CDEFGHI J Duration 85 2846 7 45 6 (days) Following Activity C,D EFGHIJJ * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? B BConsider the office renovation project data in Table 7.16. A“zero” time estimate means that the activity could take a verysmall amount of time and should be treated as a numericzero in the analysis.a. Based on the critical path, find the probability ofcompleting the office renovation project by 39 days.b. Find the date by which you would be 90 percent sure ofcompleting the project.
- B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4← Consider the following crash data for a project. Times are given in weeks. ACTIVITY A B C D E F How many week(s) of crashing are available for activity E in the table above? Activity E has sweeks of crashing available. What will be the cost of activity E if it is completed in 3 weeks? The cost will be $ NORMAL TIME 4 7 8 3 7 6 CRASH TIME 4 5 3 1 1 3 NORMAL COST ($) 1,400 5,000 5,700 2,400 1,100 2,800 CRASH COST ($) 1,400 6,200 8,700 3,800 5,900 5,200 (s) po TimeGeneral Foundry’s project crashing data are shown below. Crash this project to 13 weeks using CPM. What is the final time for each activity after crashing? What is the crash cost per week per activity and the total cost of crashing? TIME (WEEKS) COST ($) ACTIVITY IMMEDIATE PREDECESSORS NORMAL CRASH NORMAL CRASH A — 2 1 22,000 23,000 B — 3 1 30,000 34,000 C A 2 1 26,000 27,000 D B 3 2 48,000 49,000 E C 4 2 56,000 58,000 F C 3 2 30,000 30,500 G D, E 5 2 80,000 83,000 H F, G 2 1 16,000 19,000
- a. Determine the expected activity completion times. b. Identify the critical path. *Please answer letter A and B above. Note: to = optimistic, tm = most likely, and te = expected time.Given is a Project with network diagram and activity times as shown below. Activity Time (wks) A 13 B 5 Start с 14 A c) The Slack time of Activity C = Blank 3 weeks D D a) The Earliest Start (ES) time of Activity I = Blank 1 weeks 9 b) The Latest Start (LS) time of Activity B = Blank 2 weeks f) The Project Completion time = Blank 6 weeks d) The Earliest Finish (EF) time of Activity H = Blank 4 weeks e) The Latest Finish (LF) time of Activity B = Blank 5 weeks B F E 12 E F LL 17 H G 9 J H 15 - 15 J 2The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS ACTIVITY A ABCDEFGH B-E-G-H b. What is the critical path? A-C-F-H OA-D-F-H A-D-G-H A A B C,D D, E F,G Project completion time a LLL23312 TIMES (DAYS) m •WNNW: 3 2 2 3 4 4 4 4 b 5 3 3 4 11 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. days 565
- PERT-CPMYu and Mi Company is planning to computerize its accounting system. Its IT consultant has determined thefollowing activities required to complete this project together with the time estimates and precedence relationships. a. Determine the expected project completion time and the variance.b. What is the project’s critical path?c. Determine the probability that the project will be completed in 40 weeks or less.Consider the project described in the table below: Activity Duration A B C D E F G H 9 4 8 8 5 7 4 6 OEST-9 and LCT = 15 OEST=9 and LCT = 13 Immediate Predecessor What is the earliest start time (EST) and latest completion time (LCT) of activity B? OEST=9 and LCT = 20 OEST-9 and LCT-17 - A A A B B,C C,D E,F,GA solved PERT problem is detailed in the table below. The expected time and variance values and the critical activities are given in the table below. Answer the following questions by filling the blanks (WRITE YOUR ANSWERS TO 2 DECIMAL PLACES. DO NOT ROUND UP OR DOWN): a. The expected project completion time for this problem is and the standard deviation is . b. There is a 0.95 probability that the project will be completed by weeks. Activity Expected time Variance Critical? A 10 0.36 Yes B 7 0.11 No C 7 0.25 No D 3 0.48 Yes E 5 1.60 Yes F 7 0.69 No G 2 3.69 Yes