Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Activity A B с Description Report generation Web scraping Testing Immediate Predecessor A, B Optimistic 1 4 1 Time (Weeks) Most Probable 8 9 1 Pessimistic 12 11 1

Understanding Management (MindTap Course List)
10th Edition
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Richard L. Daft, Dorothy Marcic
Chapter15: Managing Quality And Performance
Section: Chapter Questions
Problem 1GL: Create a Group Control System Step 1 Form into groups of three to five students. Each group will...
icon
Related questions
Question
You may need to use the appropriate technology to answer this question.
Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes
data from a collection of websites and then automatically generates a report for management on a daily basis.
Time (Weeks)
Activity
A
B
с
Description
Report generation
5
Web scraping
Testing
img20230305_11125728.pdf
Immediate
Predecessor
A, B
Optimistic
1
4
1
(a) Construct the project network. (Submit a file with a maximum size of 1 MB.)
Choose File No file chosen
Most Probable
8
9
1
Pessimistic
12
(d) Should you use the estimate in (b) or (c)?
O The probability estimate from (b) based on the critical path is more accurate.
The probability estimate from (c) based on both paths is more accurate.
O The probability estimates from (b) and (c) are equal.
11
1
(b) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)
0.9088
X
(c) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)
0.8303
X
Transcribed Image Text:You may need to use the appropriate technology to answer this question. Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Time (Weeks) Activity A B с Description Report generation 5 Web scraping Testing img20230305_11125728.pdf Immediate Predecessor A, B Optimistic 1 4 1 (a) Construct the project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen Most Probable 8 9 1 Pessimistic 12 (d) Should you use the estimate in (b) or (c)? O The probability estimate from (b) based on the critical path is more accurate. The probability estimate from (c) based on both paths is more accurate. O The probability estimates from (b) and (c) are equal. 11 1 (b) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) 0.9088 X (c) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) 0.8303 X
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Management (MindTap Course List)
Understanding Management (MindTap Course List)
Management
ISBN:
9781305502215
Author:
Richard L. Daft, Dorothy Marcic
Publisher:
Cengage Learning