Lifang Wu owns an automated machine shop that makes precision auto parts. He has just compiled an input—output report for the grinding work center.                                                                                                                                                         Period 1 2 3 4 Total Planned input 70 70 85 85 Actual input 75 75 75 75 Deviation Planned output 75 75 75 75 Actual output 85 85 80 80 Deviation Initial​ backlog: 20 For the given information related to​ "inputs," the values for deviation and total​ are: The deviation in period 2​ =

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter11: Simulation Models
Section11.4: Marketing Models
Problem 35P
icon
Related questions
Question

Lifang Wu owns an automated machine shop that makes precision auto parts. He has just compiled an input—output report for the grinding work center.  

                                                                                                                                                       

Period

1

2

3

4

Total

Planned input

70

70

85

85

 

Actual input

75

75

75

75

 

Deviation

         

Planned output

75

75

75

75

 

Actual output

85

85

80

80

 

Deviation

         

Initial​ backlog: 20

         

For the given information related to​ "inputs," the values for deviation and total​ are:

The deviation in period 2​ =

units ​(enter your response as an​ integer, including a minus sign if​ necessary).

Note:-

  • Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
  • Answer completely.
  • You will get up vote for sure.
Expert Solution
steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,