Q: PWA public works administration write a summary explaining the purpose of PWA write two potential…
A: PWA is known as the administration of the Public work which came into existence in 1939 and was…
Q: a) Table 2a below illustrates the tasks to be performed for the delivery of a new software package.…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(i,…
Q: Find one of the critical paths CP from the choices below. A-1-3-6-8-9 B-1-2-4-6-9 C-1-2-4-6-7-9…
A: The network diagram is the graphic representation of the project. The project involves the…
Q: A life cycle model specifies the criteria for entering and exiting each phase. When may a phase…
A: Life cycle shows the working from the start to the end of the procedures
Q: Explain the latest start time in critical path method
A: The concept "late start" depends on the final point in time when the plan's action will begin in…
Q: a. Introduction PPE GLOVEb. Objective of Project/Manufacturing Processc. History of Company/Product…
A: The workers of the company are the integral part and base of the company. The protection of the…
Q: Case study - a new distribution centre for Pick n Pay in johannesburg. Which capacity strategies are…
A: Capacity strategy is related to the raw material needs of the firm. It helps the manufacturer to…
Q: The information (in minutes) shown in Table, pertains to a package filling operation at the Black…
A: In a business operation many activities are carried out and many process are associated with one…
Q: Discussion on reasons of lowering productivity Conclusion. In mangaement a construction project
A: The production rate is the ratio of the number of goods produced and the times spent producing them.…
Q: From the following table calculate and identify the Total distance travelled per month for layout A…
A: Given data: Products Products per month (load/units) Distance per product (feet) Layout…
Q: Can you Give me Five (5) Feasibility title considering four types operational, technical, economic,…
A: As the name implies, a feasibility analysis is used to determine the viability of an idea, such as…
Q: Activity Name Description or Instruction Please calculate the VCC, VFD, TVFD for this imported…
A: The detailed solution is given in Step 2.
Q: The process used for patient registration, consultation, blood test, X ray and other tests in a…
A: Operations management is an area of management dealing with production, storage and delivery of…
Q: Case study You have recently been appointed as the new IT risk manager of a countrywide online…
A: Below mentioned are the various causes of network breaches: 1. The first reason of network breach is…
Q: Any proposed Process layout or servicescape for beverage industry ?
A: A careful study of the layout covers external transportation facilities; stores; production…
Q: The work breakdown structure (WBS) for building a house (levels 1 and 2) is shown below: a) Add two…
A: A Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical disintegration of the work…
Q: Using AOA, diagram the network describedbelow for Lillian Fok’s construction project. Calculate…
A: Given data is
Q: Write Current situation and Problem/Opportunity statement, analysis of options and recommendations…
A: For a new student lounge or setting area, I believe that there is a vast opportunity as the students…
Q: Develop the network for planning and construction of the new hospital at Arnold Palmer.
A: A project schedule network diagram shows the sequential and analytical connection between tasks in a…
Q: Develop a product structure (BOM) (product structural tree). Develop a time phase structure (Gantt…
A: Product structure is a kaleidoscopic leveled deterioration of a product, ordinarily known as the…
Q: As the Operations Manager of Shane Manufacturing Ltd., you are given the task to balance the…
A: Assembly line balancing is a quantitative approach where there are infeasible options are given for…
Q: Classify each of the following as nominal, ordinal, interval, or ratio data and explain. a. the…
A:
Q: The work breakdown structure (WBS) for building a house (levels I and 2) is shown below: a)…
A: Given data is
Q: From the following table calculate and identify the Total distance travelled for per month for…
A: Given, roducts Products per month (load/units) Distance per product (feet) Layout A…
Q: The table below contains information about an environmental clean-up project in the township of…
A: Identify the activity that has no predecessors. These activities will be the initial activities. The…
Q: Design decisions include ________. Group of answer choices Facility layout Forecasting Inventory…
A: Production is the process of converting raw materials and resources into finished products and…
Q: Schedule the following activities using CPM: АСTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 2 B A 3 A…
A: ES = maximum (EF of all immediate predecessor) EF = ES + duration Minimum project duration = largest…
Q: DEFINE Critical path analysis
A: Critical path analysis is the project management tool used for scheduling, organizing, planning and…
Q: Typically, who is developing the design/drawing to an engineering or construction projects?
A: Construction and the engineering project, simply related to being a project is the organized process…
Q: a. Given the following diagram for a product, determine the quantity of each component required to…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: Question one: The Sail-Sea is a boat manufacturer. The assembly location is available for the…
A: Format used for drawing the Network diagram:
Q: An equipment installation job in the completion stage can be completed in 40 days of 8 hours day…
A: Given Information: Case 1: Completion time = 40 days Working hours = 8 hours per day Number of men…
Q: Case study You have recently been appointed as the new IT risk manager of a countrywide online…
A: Executive Summary: DirectToCust has been confronting a great deal of safety worries over the most…
Q: An equipment installation job in the completion stage can be completed in 40 days of 8 hours day…
A: given, 40 males can finish a job in 40 days denotes each employee per day is concluding 1/ (40*40)…
Q: work(s) effectively with Cellular layout a. All of the choices bwireless telecommunication C. part…
A: A cell layout is a designing process that is involved in making a layout consisting of dissimilar…
Q: In May 2017, LAX, the world's 4th largest airport, relocated 15 airlines in a three-night (five…
A: Observation research refers to the study of the participant's behaviour in a given surrounding. The…
Q: Titanic Cruise Company plans on releasing it’s new “Superliner” cruise ship in time for the peak…
A: Let xi be the number of days of stay in the port of respective city. i.e., x1 is the number of days…
Q: The Carry-on Luggage Company must set up an assembly line for a wheeled carry-on bag. Forecasts show…
A: Note: Since you have posted a question with multiple subparts, we will solve the first three…
Q: Case Study ABC Construction Company is preparing a network for laying the foundation of a new…
A: Network diagram: It is the representation of the activities and tasks and events related to a…
Q: Explain with aid of practical examples the following: 1. Scope creep 2. WBS 3. Scope statement
A: Project scope can be defined as that part of the project planning that involves the determination…
Q: Explain the difference between the service projects and revenue projects
A: The difference between the service and revenue projects are :
Q: As the project manager, discuss the risk management process you think might have identified the…
A: Introduction to risk analysis: It is the process which help to access the potential risk which could…
Q: Container Terminals Superstructure planning in container terminal not only a task that targets the…
A: Introduction Compartment terminals or holder ports (utilized conversely) are the terms assigned for…
Q: very time table suggests two things; Plurality of activity and an expanse of time. Putting these two…
A: Please find the attached time table as per the given case-
Q: After six months of work on the project’s site, your company collected the following information…
A: Given: Budget at Completion = BAC = $ 156,478.00 After 6 months of work, Planned Value = PV =…
Q: CRASHING AND COST PLAN Problem 3 From the following data perform crashing the project. Ti7me in…
A: The question is related to Crashing a Project. The details regarding the same are given. We will…
Q: Explain with an example, A Service Project with a "Do-Nothing" Alternative?
A: The 'Do Nothing' alternative represents a course of action. It is important to consider the…
Q: To develop a WBS structure for a project “Design and Manufacturing of shaft in the Mechanical…
A: WBS is a tool that provides guidance for schedule development and control by providing detailed cost…
List 4 front stages of a car repair facility, university, a consulting firm and an airline
Step by step
Solved in 2 steps
- Scenario 4 Sharon Gillespie, a new buyer at Visionex, Inc., was reviewing quotations for a tooling contract submitted by four suppliers. She was evaluating the quotes based on price, target quality levels, and delivery lead time promises. As she was working, her manager, Dave Cox, entered her office. He asked how everything was progressing and if she needed any help. She mentioned she was reviewing quotations from suppliers for a tooling contract. Dave asked who the interested suppliers were and if she had made a decision. Sharon indicated that one supplier, Apex, appeared to fit exactly the requirements Visionex had specified in the proposal. Dave told her to keep up the good work. Later that day Dave again visited Sharons office. He stated that he had done some research on the suppliers and felt that another supplier, Micron, appeared to have the best track record with Visionex. He pointed out that Sharons first choice was a new supplier to Visionex and there was some risk involved with that choice. Dave indicated that it would please him greatly if she selected Micron for the contract. The next day Sharon was having lunch with another buyer, Mark Smith. She mentioned the conversation with Dave and said she honestly felt that Apex was the best choice. When Mark asked Sharon who Dave preferred, she answered, Micron. At that point Mark rolled his eyes and shook his head. Sharon asked what the body language was all about. Mark replied, Look, I know youre new but you should know this. I heard last week that Daves brother-in-law is a new part owner of Micron. I was wondering how soon it would be before he started steering business to that company. He is not the straightest character. Sharon was shocked. After a few moments, she announced that her original choice was still the best selection. At that point Mark reminded Sharon that she was replacing a terminated buyer who did not go along with one of Daves previous preferred suppliers. What should Sharon do in this situation?Scenario 4 Sharon Gillespie, a new buyer at Visionex, Inc., was reviewing quotations for a tooling contract submitted by four suppliers. She was evaluating the quotes based on price, target quality levels, and delivery lead time promises. As she was working, her manager, Dave Cox, entered her office. He asked how everything was progressing and if she needed any help. She mentioned she was reviewing quotations from suppliers for a tooling contract. Dave asked who the interested suppliers were and if she had made a decision. Sharon indicated that one supplier, Apex, appeared to fit exactly the requirements Visionex had specified in the proposal. Dave told her to keep up the good work. Later that day Dave again visited Sharons office. He stated that he had done some research on the suppliers and felt that another supplier, Micron, appeared to have the best track record with Visionex. He pointed out that Sharons first choice was a new supplier to Visionex and there was some risk involved with that choice. Dave indicated that it would please him greatly if she selected Micron for the contract. The next day Sharon was having lunch with another buyer, Mark Smith. She mentioned the conversation with Dave and said she honestly felt that Apex was the best choice. When Mark asked Sharon who Dave preferred, she answered, Micron. At that point Mark rolled his eyes and shook his head. Sharon asked what the body language was all about. Mark replied, Look, I know youre new but you should know this. I heard last week that Daves brother-in-law is a new part owner of Micron. I was wondering how soon it would be before he started steering business to that company. He is not the straightest character. Sharon was shocked. After a few moments, she announced that her original choice was still the best selection. At that point Mark reminded Sharon that she was replacing a terminated buyer who did not go along with one of Daves previous preferred suppliers. What does the Institute of Supply Management code of ethics say about financial conflicts of interest?market analysis(case study) in electronics store.
- Company: ABC Civil Engineering - an engineering firmSituation: ABC company has recently made significant cuts in staff and the workload on existingemployees has increased. A major RFP is dueCharacters: Ted Waltz – Managing Director of ABC EngineeringElaine Tillman – Civil Engineer____________________________Elaine Tillman looked at her watch – it was 7:30 pm. Just then she knew she would not make it to her son’s final high school basketball game. It took her a moment to collect herself and wipe the tear that had started down her face and onto the ragged-edged 100 plus page RFP she was working on. The RFP,the largest opportunity that ABC Civil Engineering had a chance to bid on in 6 months, was far fromready for the 9:00 AM deadline the following day.Normally in this situation, Elaine would have collaborated with a proposal team putting together such a big proposal but, since the economic down turn hit, ABC has had to make significant cuts in its staff. It started with administrative…Company: ABC Civil Engineering - an engineering firmSituation: ABC company has recently made significant cuts in staff and the workload on existingemployees has increased. A major RFP is dueCharacters: Ted Waltz – Managing Director of ABC EngineeringElaine Tillman – Civil Engineer____________________________Elaine Tillman looked at her watch – it was 7:30 pm. Just then she knew she would not make it to her son’s final high school basketball game. It took her a moment to collect herself and wipe the tear that had started down her face and onto the ragged-edged 100 plus page RFP she was working on. The RFP,the largest opportunity that ABC Civil Engineering had a chance to bid on in 6 months, was far fromready for the 9:00 AM deadline the following day.Normally in this situation, Elaine would have collaborated with a proposal team putting together such a big proposal but, since the economic down turn hit, ABC has had to make significant cuts in its staff. It started with administrative…Q1) solve the following mcqs a) At Khaleej Corporation, managers drew up a three-stage plan as they prepared for layoffs. First, they warned employees several months ahead that layoffs were inevitable. Soon thereafter, they held on-site presentations at all locations to explain to employees why the layoffs were needed and to provide as much information as they could about what employees should expect. Represents an example of?" Provide assistance to displaced workers Help survivors thrive Both A & B More Communication is significant b) "An army officer gives his directions on a certain task, his cadets are compelled to follow his instructions. This is an example of ___. " Expert Referent Reward Legitimate c) _____ is the person who serves as one of the key persons in managing change initiatives. Change agent CEO CFO CIO
- What is feasibility analysis?Q1) solve the following mcqs a) At Khaleej Corporation, managers drew up a three-stage plan as they prepared for layoffs. First, they warned employees several months ahead that layoffs were inevitable. Soon thereafter, they held on-site presentations at all locations to explain to employees why the layoffs were needed and to provide as much information as they could about what employees should expect. Represents an example of?" Provide assistance to displaced workers Help survivors thrive Both A & B More Communication is significant b) Rational decision-making approach ideally implies ______ decisions. Programmed Non-programmed Rational Non-rationalBriefly state 3 recommendation for 'Mamak' restaurant to improve facilities and their service of the restaurant.
- 1. Read the following case study and answer the questions: London Elevator Repair London Elevator Repair (LER) provides a maintenance and repair service for a variety of elevator systems. Its customers include department stores and other business organizations throughout the London. The elevator systems include conventional lifts, paternosters, and escalators. Customers can take out a maintenance contract with LER, for which they pay on an annual basis. One maintenance contract can cover several elevators (for example, all of the escalators in a department store). Due to their nature, some elevators are covered by an individual contract (for example, a paternoster would have its own contract rather than be included in a contract for the maintenance of conventional lifts). Hence each customer can have more than one maintenance contract. The hourly rate to be charged for engineers’ time is agreed as part of the contract negotiations. In addition to the work carried out under…Scenario 3: A problem with paper You are a franchisee for Fatto’s Burger Palace in a small college town (“where friends meet to eat”). The specialties of the house are the “Giant Burger Supreme” and the “Hound Doggie,” both of which contain 26% or less fat. Business is good, especially when the college dietician decides to put soy stew on the menu in the dining halls. Recently, agitation by environmental extremists has forced the restaurant to abandon the convenient clam shell boxes of polystyrene in favor of paper boxes. The latter are a little more expensive, but take up less space. They are somewhat difficult and time-consuming to fold. Customers are now complaining about the oil stains on the inside of the burger box. Water tends to seep through and make the package limp in some cases. This has required putting more napkins in each order. In addition, the blazing red Fatto’s symbol on the top of the boxes now has fuzzy edges, whereas it was sharp and crisp on the clam shell boxes.…Industrial Engineering Department 4. Due to increasing population, the aspiration is to raise their standard of living and further improve the quality of life. In what way human can improve the standard-of living or quality of life? Picture / Situation Advantages Page 2 I 4 Q +