In a job shop operation, four jobs may be performed on any of four machines. The hours required for each job on each machine are presented in the following table. The plant supervisor would like to assign jobs so that total time in minimized. Use the assignment method to find the best solution. MACHINE Y. JOB W A12 10 14 16 13 AIS 12 13 15 12 B2 B9 12 12 11 14 16 18 16

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
icon
Concept explainers
Topic Video
Question
100%
In a job shop operation, four jobs may be performed on any of four machines. The hours required for each job on each machine are presented in the following table. The plant supervisor would like to assign
jobs so that total time in minimized. Use the assignment method to find the best solution.
MACHINE
Y.
JOB
W
A12
10
14
16
13
AIS
12
13
15
12
B2
B9
12
12
11
14
16
18
16
Transcribed Image Text:In a job shop operation, four jobs may be performed on any of four machines. The hours required for each job on each machine are presented in the following table. The plant supervisor would like to assign jobs so that total time in minimized. Use the assignment method to find the best solution. MACHINE Y. JOB W A12 10 14 16 13 AIS 12 13 15 12 B2 B9 12 12 11 14 16 18 16
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 8 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,