Given the information provided below and a budget of $6,500,000, what is the most that Loyola Machining can pay for each manufactured unit? Assume one year is 250 working days and the order size is 5,200 units. Use the Total Supply Chain Cost Excel template for your analysis. Do not round intermediate calculations. Round your answer to the nearest cent. Price per unit: $ Annual Demand (D) 478,400 Price per Unit (P) ? Oversight Cost per Unit (0) $0.33 Transport Cost per Unit (Ct) $3.25 Order Cost (Co) $170 Cost to Store One Unit One Year (Ch) $9.00 Order Lead Time in Days (L) 30

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Chapter2: The Purchasing Process
Section: Chapter Questions
Problem 1GPE
icon
Related questions
Question
Given the information provided below and a budget of $6,500,000, what is the most that Loyola Machining can pay for each manufactured unit? Assume one year is 250 working days and the order size is 5,200 units.
Use the Total Supply Chain Cost Excel template for your analysis. Do not round intermediate calculations. Round your answer to the nearest cent.
Price per unit: S
20
1504
Annual
Demand (D)
478,400
555
Price per
Unit (P)
2
?
Oversight Cost
per Unit (0)
$0.33
Transport Cost
per Unit (Ct) (Co)
53.25
$170
Order Cost
Cost to Store One
Unit One Year (Ch)
$9.00
Order Lead Time
in Days (L)
30
Transcribed Image Text:Given the information provided below and a budget of $6,500,000, what is the most that Loyola Machining can pay for each manufactured unit? Assume one year is 250 working days and the order size is 5,200 units. Use the Total Supply Chain Cost Excel template for your analysis. Do not round intermediate calculations. Round your answer to the nearest cent. Price per unit: S 20 1504 Annual Demand (D) 478,400 555 Price per Unit (P) 2 ? Oversight Cost per Unit (0) $0.33 Transport Cost per Unit (Ct) (Co) 53.25 $170 Order Cost Cost to Store One Unit One Year (Ch) $9.00 Order Lead Time in Days (L) 30
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning