Determine the Early Start, Early Finish, Late Start, Late Finish, Total Float, and Free of the activities A, B, C, D, and E and find the critical path. Activity ES Dur EF LS FF TF LF B SS/3 5. FF/S A C. 10 15 8
Q: 5. By using data below : a. Make a project network b. Determine the expected time needed to finish…
A: Note: Since you have posted multiple parts in the same questions we will be answering the first…
Q: You are given the following data for an activity: ES = 10 EF = 15 LS = 16 Which of the following can…
A: Activity duration is the total time taken by a particular activity to complete the project in…
Q: IMMEDIATE ACTIVITY PREDECESSORS D a) Choose the corect network to rep OA 08 b) Which activities are…
A: Find the Given details below: Activity ImmediatePredecessors Time(Weeks) A - 4 B - 3 C A 3…
Q: Describe what is meant by the pessimistic time in critical path method
A: It is a method based on the critical path and probabilistic time estimates. Activity times are…
Q: Prepare a schedule based on resources. There are only 3 resources available for each period.…
A: 1. Possible path Duration Maximum duration Critical path 1-2-7 = 2+6+2 = 10 No No 1-3-5-7 =…
Q: Activity a b Immediate Remarks m predeccessor A a = optimistic time 1 3 3 4 m = most likely time C 4…
A: Activity Predecessor to tm tp A - 1 2 3 B - 2 3 4 C A 4 5 6 D B 8 9 10 E C, D 2 5 8 F B…
Q: According to the project network below which activity is a merge activity? Sube Teat 1 K L. Systems…
A: Project management is the management in which special types of skills knowledge and technology is…
Q: Answer only question 2 1)List and explain the phases that mark the life of a project. 2) For…
A: Project management is usually accomplished in stages to further develop control and quality. This…
Q: 43 EST 43 С. ? A, ? F. ? 50 LST 50 E, 8 В, 15 15 D, 20 15 35 35 a) i) Explain what is meant by the…
A: Note: - Since the exact question that has to be answered is not specified we will answer the first…
Q: manager increased the time of activity which locate on the critical path (one weeks). ol project…
A: Below is the solution:-
Q: Find the following using A.O.A(activity on arrow method):- 1. The project's total duration 2. The…
A: Critical path is a way (as in PERT) that associates the undertakings in an interaction which are…
Q: Practice Question EVM: A simple project consists of five tasks and is scheduled to take 13 weeks to…
A: ACWP = The actual cost of work performed is the cost actually incurred & recorded in completing…
Q: 1. Define what the critical path method (CPM) is relative to project planning, and explain the…
A: Project management is the management in which unique types of knowledge, skills and resources are…
Q: Project ALPHA has 6 Acivities from A to Fas folows: Activity Duration Preceded By A 3 7 A 1 The Late…
A: Given: Activity Predecessors Duration A - 3 B A 9 C A 7 D B 5 E C 5 F E 1 Edge and…
Q: Suppose the Prime Minister promised to complete the project within 50 days. What are the chances of…
A: Probability is simply the chances of the particular task getting completed on its expected time. The…
Q: 4G+ 5:44 PM 0.3KB/s L l 87 220465982_1485159421836.. Apple Company presents the following PERT-CPM…
A: Given data is
Q: critical path should also be determined. Here are the activity times Immediate Activity (weeks)…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Q2: For the activities shown below determine: 1. The duration of project 2. The critical path by…
A: Find the Critical path and duration below: Critical Path :…
Q: Exercise(3) Draw the AON network, compute the ES, EF, LS, LF time for each activity and then find…
A: Given data is
Q: Find the critical path if activity H delayed 2 days Fill the table IPAS activity 1 Duration ES EF LS…
A: Given data is
Q: Activity A BEDC FGHI R 4 5 5 2 3 3 4 5 5 6 Duration (days) Following B,D,E C,F F F,G G G H,I R R…
A:
Q: All activity times are in days. 1. What is the expected project completion time ? ( in days) 2.…
A: Note - Hi! Thank you for the question, As per the honour code, we are allowed to answer three…
Q: 2- A project consists the activities shown bellow, all links are Finish to Start ( F-S) with Zero…
A: Given: Activity Immediate Predecessors Duration A - 4 B - 3 C A,B 6 D B 1 E D 7 F C 2…
Q: Activity Immediate Optimistic Most Likely Pessimistic Predecessor A 7 8 9 B 10 10 13 A 8 10 13 11 14…
A: Solution The expected completion time is given by - E=O+4M+P6 where O is optimistic time, M is most…
Q: Activity Immediate Optimistic Most Likely Pessimistic…
A: Activity Predecessor Optimistic Most likely Pessimistic A - 2 3 4 B - 2 4 6 C A 1 2 3 D B…
Q: H.W: Find the total duration of the project and determine the critical path for the activities shown…
A:
Q: What are dummy activities? Why are they used in activity-on arrow (AOA) project networks?
A: Dummy events include: When the exact logical relationship between two specific activities on the…
Q: Find the following using A.O.A(activity on arrow method):- 1. The project's total duration 2. The…
A: Project Duration: 30
Q: For the network shown below and the given time estimates, what is the estimated expected (mean) time…
A: The expected completion time is the time required to complete the project activities in the project…
Q: Example 2 (ADM) Activity Duration (day) Predecessor (s) Act. A 2 Act. B 3 Act. C 3 A Act. D 4 Act. E…
A: Given data is
Q: Follow up to previous question: 3) A company decides to plan a project, with activities, precedences…
A: Drawing the project network as shown in the diagram using AOA convention we represent the activities…
Q: nappens wn you to mahage a projects cost? HOw can principles oT the cost management process help…
A: ANSWER: It results in : Bad reputation, Project cost overruns, Project schedule delays, De…
Q: Construct a Gantt chart for the following set of activities and indicate the pro time and slack for…
A: A Gantt chart is a bar chart that displays a project's tasks together with their due dates and…
Q: The expected times and variances for the project activities follow. Complete the table showing which…
A: Forward Pass:Early Start = Maximum (or Highest) EF value from immediate Predecessor(s)Early Finish…
Q: estion 10 (2 points) ypically, the project charter and scope have been clarified before the pro ip.…
A: Whenever a project starts or comes in the initiation phase, there are certain things that need to be…
Q: Activity A BEDCFGHI 5 5 2 3 3 4 5 5 6 Duration (days) Following B,D,E C,F F F,G G G H,I R R Activity…
A:
Q: The table below contains activities for a Project. Determine the Activity Duration, Slack and state…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Identify the critical path for the following project activities and their required times to be…
A:
Q: Draw a Project Network and determine the critical path of this project? Activity Description…
A: Given data is
Q: What is the project duration?
A: THE ANSWER IS AS BELOW:
Q: 5. H,GF 21 Find total duration to finish the project And find critical oath By AoA method 3:33 PM
A: Activity Immediate Predecessors Duration A - 5 B - 12 C A 7 D C…
Q: 3. Does the delay of activity B delay all other activities in the plan? 4. What is the ES, EF, LS,…
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: 1. When will the activity be finished? 9 months 10 months 11 months 1 year 2. When will activity…
A: This question is related to the topic- project management and this topic fall under the operations…
Q: 2/ Find the project's total duration and date of completion (assume the project start date is…
A:
Q: 6. Suppose you are given the following data for a project: Activity Expected Activity Time (in days)…
A:
Q: Define what a WBS is relative to project planning, and the importance of the WBS in a project plan.
A: Work breakdown structure (WBS) is a technique for finishing a complex, multi-step project. It's a…
Q: a) Choose the correct project network. OA Start Start b) The critical path is S-U-W-Y The project…
A:
Q: Explain the different types of Project Management Skills? Elaborate the following with the help of…
A: Project management skills refers to the core abilities that are required to bring a project to its…
Step by step
Solved in 2 steps with 3 images
- You are the project manager of the software installationproject in Table 7.12. You would like to find the minimum-costschedule for your project. There is a $1,000-per-week penaltyfor each week the project is delayed beyond week 25. In addi-tion, your project team determined that indirect project costsare $2,500 per week.a. What would be your target completion week?b. How much would you save in total project costs with yourschedule?By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A CDEFGHI J Duration 85 2846 7 45 6 (days) Following Activity C,D EFGHIJJ * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? B BDue to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. A project network with 11 activities and 13 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity F. Activity B…
- Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. (b) Develop an activity schedule. (Round your answers to two decimal places.) (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project…Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. (b) Develop an activity schedule. (Round your answers to two decimal places.) (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project…2. Joe and Noël have just gotten engaged. As they are both business students, they thought they'd try to plan their wedding preparation as a project. Here's the WBS they've determined is necessary for a simple but elegant wedding. Assume all durations are deterministic. Although perhaps not realistic to real wedding planning, by using the standard calendar in Project Libre (use default working days in software). Task ID Task Name Duration Predecessor 1 Begin Wedding Planning (milestone) 0 days --- 2 Select Site&Date 3 wks 1 3 Hire Officiant 1 wk 2 4 Hire Caterers 2 wks 1 5 Pick Menu 4 days 4 6 Order Invitations 2 wks 2,5 7 Sent Invitations to Guests 1 wk 6 8 Collect RSVPs 6 wks 7 9 Tell Caterer headcount & Order food 1 wk 8 10 Shop for Wedding Gown 4 wks 1 11 Select Bridesmaids Dresses 4 wks 10 12 Bride goes on Diet 6 wks 10 13 Get Wedding Gown altered 2 wks 12 14 Get Bridemaids' Dresses altered 4 wks 11 15 Order Flowers 2 wks 11 16…
- Dave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managers8 EARNED VALUE ANALYSIS The following project is reported to be at the end of its 8 week. Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Find the condition of the project at the this reporting period. PV AC Budget ($) Duration Actual Cost % D-8 Activity Predecessor (s) (week) ($) Complete 300 400 A 3 100 A3 В 4 200 180 100 B:4 C 7 250 300 90 A 8 600 400 50 400 200 В 40 150 180 F В 4 100 G C 4 100 200 40 500 H D, E 2 300 F, G 3 J H, I 1 100 ㅇ CO 프 (-)ACTIVITY WK(S) PRECEDES CRASH COST/WEEK A(START $370 $120 $220 1 $140 F(END) 3 $400 Suppose that Rafay is only given 8 weeks (instead of 10) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (weeks) A O week(s) B1 week(s) C 2 week(s) E O week(s) F Oweek(s) What is the total crashing cost? $ nothing (Enter your response as a whole number.) PLEASE SHOW ME HOW TO GET THE CALUCLATION ON MY OWN SHOW YOUR STEPS i DO KNOW THAT CC-NC/NT-CT BUT I DONT KNOW WHAT FIGURES GOES WHERE AND WHY B с E 3 2 4 B,C E F F
- The following information has been computed from aproject:Expected total project time = T = 62 weeksProject variance (s2p ) = 81What is the probability that the project will be completed18 weeks before its expected completion date?ces Mailings Po V ates) EE E AL Review View Tell me $ Text Predictions: On 4 BIU 1. Evergreen Company wants to construct a new office building. The company has contracted a construction management contractor for this project. Given below are the details of a construction project. ✓ ✓ ✓ % Activity A 5 B C D ¶ E F — a) Construct the project network (AON) diagram for Evergreen Company and list all possible activity paths and their duration. b) Determine Evergreen Company's critical path(s). What is the duration of project competition? c) Determine the ES, EF, LS, LF, and floats for each activity. d) Construct a Gantt chart for Evergreen Company's project. AaBbCcDdEe Normal A STR 6 Predecessor(s) Duration (days) 1 2 A A B B, C E AaBbCcDdEe No Spacing !!! 3 2 1 1 & 7 E Do AaBbCcL AaBbCcDd AaBb AaBbCeDdE Heading 1. Heading 2 Title Subtitle * 00 8 I 9 Focus ( ) 0 Comm > St FAssume we are planning to develop a room reservation system that is estimated to have 400 story points of features. Let’s say our team’s velocity on two-week sprints ranges between 20 and 25 story points. Our project will start on Dec 1, 2021. If our customer wants the project to be in production by end of June 22, how likely will the project be successful? Why? Show your calculations.